ABIC simple Works Contract (Tara) Flashcards

1
Q

What should you do if you are wanting to include special conditions?

A

Get a lawyer to write any special conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

if you are using the default document order of precedence, should you still write it in?
And what does large scale over small scale mean?

A

Yes. Still write it in because then everyone knows it’s deliberate (Nicole)

Large vs. small scale means 1:20 drawings will override 1:100 for example.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the builders responsibility when they are committing by signing the contract under A3?

A

They are promising to be able to build the building off the documents that have been provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does A5 Warranties of owner clarify in terms of liability to materials?

A

the owner warrants that all materials comply with the building code. However, if the contractor: a - Is or becomes aware that the owners this five materials you don’t or will not comply, or B - has a reasonable doubt about whether the owners specified materials do or will comply with the building code Then the contractor must promptly give the owner a notice and a copy to the architect, identifying the relevant owners specified materials and stating that they may not be compliant with the building code and not be fit for the intended purpose. If the owners best five materials are not compliant with the building code and the contract are has not given such a notice, then the warranty in clause 85.5 does not apply and is of no effect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what are the three types of risks on site and three types of insurances to cover the risks that builders should have?

A

Building works insurance: covers the physical things on the site. The existing building should be included.

Workers compensation: risk of people getting hurt

Public Liabilty: damage or hurt to third parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Does the ABIC SW include and spot to nominate the date of site possession for the contractor?

A

No. It just says a 10 days after signing of the contract or otherwise nominated.

But the ABIC Major Works contract does.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does section A of the ABIC-SW contract cover?

A

Cooperative contracting

Obligations of the contractor

Warranties by the contractor

Obligations of the owner

Warranties by the owner

Architect to administer contract

Architects instruction

Disputing architects certificate or written decision

Disputing architects failure to act

Failure to give written certificate, written decision or notice is not acceptance

Compensation is sole remedy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

At what point in the contract timeline does the builder have to hold insurance over the site which is unique to the ABIC contract?

A

Final completion.

Others will only request them to hold insurance until practical completion.

This is so that they have insurance for when they are working on site rectifying defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the owner needs to Inform architect and contractor of alteration to financial
position when?

A

immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The contractor must begin works within how many days of site possession?

A

10 working days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The contractor or owner must Notify architect in writing of discrepancy in documents when?

A

Promptly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is the release of 50% of security?

A

Within the time shown in item 10 of schedule 1 after issue of notice of
practical completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is the full security released?

A

Within the time shown in item 10 of schedule 1 after issue of
final certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The contractor must notify and seek instruction due to latent condition within how many days?

A

within 5 working days of discovery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How long does the architect have to respond an dgive written instruction regarding a latent condition?

A

Promptly/as soon as practible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The contractor must submit a detailed claim within what time frame?

A

Within the time agreed, or within 20 working days of

receiving instruction or becoming aware of event

17
Q

When does the contractor have to notify the architect of any delays?

A

Within 2 working days of becoming aware of delay and Within 2 working days of becoming aware of end of delay

18
Q

The contractor must Give architect official documents for occupation and
evidence of successful commissioning tests within how many days from practical completion?

A

Within agreed time for architect’s inspection or if none, 10 working days

19
Q

Architect must issue progress certificate within how many days?

A

Within 10 business days after receipt of claim

20
Q

The architect or owner can terminate the ABIC contract due to insolvency within what time period?

A

Immediately

21
Q

When is an instruction automatically a variation?

A

An instruction from the architect to resolve a discrepancy, an ambiguity, or an omission that
is not in accordance with the order of precedence referred to in clause B2, is an instruction for a *variation.