Transmission Flashcards
What kind of Switchyard Scheme
Breaker & Half
What kind of Switchyard Scheme?
Double Bus, Single Breaker
What kind of Switchyard Scheme?
Double Bus, Double Breaker
What kind of Switchyard Scheme?
Double Bus, Double Breaker
What kind of Switchyard Scheme?
Main & Transfer
What kind of Switchyard Scheme?
Ring
What device has the IEEE device number of 21?
Distance Relay
What device has the IEEE Device number of 27?
Under Voltage Relay
What device has IEEE device number of 52?
AC Circuit Breaker
What device has the IEEE device number 50?
Instantaneous Over Current Relay
What device has the IEEE device number of 51?
AC Inverse Time Over Current Relay
What device has the IEEE device number 87
Differential Relay
What is a major reason for identifying the transfer capabilities of the transmission system?
- Mitigate transmission constraints in real-time
- Proactively avoid system problems
- Identify all bottled generators
- Maximize income of the company
Proactively avoid system problems
Automatic load shedding schemes should consider all of the following except?
- Power flow levels
- Rate of voltage decay
- Voltage
- Generator MW output
Generator MW Output
Your system planning group has determined that the Total Transfer Capability is 475 MW, but the posted Available Transfer Capability is 425 MW. If current transmission reservations total 375, how much capacity is available for reserving?
50 MW - must hold to posted limit
What does TLR stand for?
Transmission Loading Relief
-Multi-step procedure that guides action of Reliability Entities when taking steps to manage transmission system congestion
What would be the expected impact on a line’s operating capacity for the next day if the current temperature is 83F and the forecasted temperature is 98F?
- Capacity would increase
- Capacity would double
- Capacity would not change
- Capacity would decrease
Capacity would not change
If a transmission operator has to remove a transmission facility from service, which of the following do they have to provide notification to?
- All TOPs in interconnection
- Distribution providers
- All PSEs w/transmission service
- Potentially affected TOPs
Potentially affected TOPS
IROL stands for?
Interconnection Reliability Operating Limit
-If violated could lead to instability, uncontrolled separation , or Cascading outages that adversely could impact reliability of BES
SOL stands for?
System Operating Limit
-Value such as MW, MVAr, Amperes, Frequency or Volts
When utilizing psuedo-tie, time varying component is added to what portion of BA’s tie-line bias ACE equation?
- Actual Interchange component
- Scheduled interchange component
- Actual Frequency component
- Scheduled frequency component
- Actual Interchange component
Which of the following substation bus arrangements often initially designed to be later expanded to breaker & a half arrangement?
- Main & Transfer
- Ring
- Double-bus-double-breaker
- Single-bus
Ring
System voltage has dropped below nominal. You decide to place a capacitor bank on service. What do you expect?
A. The capacitor bank’s output will be greater than nominal due to needs of the system.
B. This is a bad decision as the capacitor bank will cause voltage to drop further.
C. The capacitor bank’s output will be less than nominal due to system conditions.
D. This is a bad decision as the capacitor bank will not provide the necessary MVARs.
C. The capacitor bank’s output will be less than nominal due to system conditions.
Why are SVCs often placed near windfarms?
A. To compensate for the variable MW output of the windfarm.
B. To absorb the excess reactive power produced by the windfarm.
C. To compensate for the sub-synchronous resonation produced by the windfarm.
D. To provide dynamic reactive power the wind turbines cannot provide.
D. To provide dynamic reactive power the wind turbines cannot provide.