What EEA level has All available generation resources in use but there may be concern?
EEA 1
What EEA Level has load management procedures in effect & operating reserves may be in danger?
EEA 2
What EEA level occurs when load shed may be imminent or in progress?
EEA 3
How long is the Contingency Event Recovery Period?
15 Minutes
How long is the Contingency Reserve Recovery Period?
90 Minutes
How long must a BA have to deliver FRO from the start of an event?
52 Seconds
How long from the beginning of an event does a BA have to notify RC if they are unable to calculate ACE?
45 minutes (must be 30 consecutive minutes not able to calculate)
How often does a BA, TOP & RC need to test Alternative Interpersonal Communications Capability? If test fails, how long to initiate contingency action or repair?
Monthly test, 2 hours to take action or repair
How long does a BA TOP & RC have to notify entities of a Interpersonal Communication Capability that lasts longer than 30 minutes?
less than 60 minutes
How long does each entity have to report disturbances per their operating plan?
24 hours or by close of next business day
How often are Black Start Resources (BSR) tested?
Every 3 years
How long do you have to transition from Primary Control Center to Backup Control Center?
< 2 Hours
If RC receives Emergency Notification from TOP or BA, how long do they have to notify other BAs/TOPS in area / or neighboring RCs?
30 minutes
During EEA 1 & 2, BA must give updates to RC how often?
Every Hour
How often shall RCs, BAs & TOPs test their primary control center’s key data exchange capabilities?
90 days
If Key Redundant Data Exchange fails, how long does an RC have to initiate action to restore redundant functionality?
Within 2 Hours
How often shall RCs & TOPs ensure Real Time Assessments performed?
Every 30 minutes
What organization issues Geo-Magnetic Activity alerts?
National Oceanic and Atmospheric Administration (NOAA)
Reactive resources shall be dispersed and located _____ so that they can be applied effectively and quickly when contingencies occur.
- electrically
- geographically
- sparingly
- externally
Electrically
Your system has experienced a system shutdown and you are in the process of restoring your system. A generator in a particular area of your system is pushing MVAR out to the system. As you restore another transmission line, without restoring additional load, what would be the expected impact on the generator during the line restoration?
- MW output increases
- MVAR output decreases
- MW & MVAR stay the same
- MVAR output increases to maximum
MVAR output decreases
Which of the following must a TOP ensure the availability and location of within its area to meet the needs of the restoration plan?
- Reactive reserves
- Sufficient generation
- Black Start capability
- Transmission paths
Black Start capability
How often is the Reliability Coordinator required to perform a real-time assessment of the system?
30 minutes
Load reduction plans have to be able to be implemented in what time frame?
30 minutes
During a restoration effort that involves the restoration of islands, load restoration pick-ups should not exceed what percentage of synchronized generation capacity?
5%
What is the threshold for having to report a loss of firm load that last more than 15 minutes?
10% of previous year peak generation
If a system operator identifies that its Contingency Analysis program has stopped working, which of the following actions should they take?
- Request Operations Support personnel to run system studies
- Ask their neighboring systems to run studies for them
- Swap to all RTU backup communications channels
- Immediately call in additional personnel to man the backup control facility
Request Operations Support personnel to run systems studies
GMD activity can impact transformers in a multitude of ways, a means for monitoring the transformer for impacts of GMD include which of the following?
- Change in noise from transformer
- Change in oil viscosity
- Decrease in transformer oil temperature
- Decrease in transformer nitrogen pressure
Change in noise from transformer