Topic C- Negotiate Project Agreements Flashcards
Negotiations
Agreement documents include a Statement of Work (SOW) or major deliverables, a schedule w/milestones & dates, performance reporting expectations, pricing and payment terms, inspection, quality requirements, and acceptance criteria warranty & future support, incentives or penalties, insurance and performance bonds, subcontractor approvals, terms & conditions, change request handling, termination clauses & dispute resolution.
Enablers
- Analyze the bounds of the negotiations for agreement
- Assess priorities and determine ultimate objective
- Verify objective of the agreement is met.
- Participate in agreement negotiations
- Determine a negotiation strategy.
Deliverables
Service Level Agreement, Performance Report, Resource calendars, Go-live blackouts
Tool
Negotiation Skills, Expert Judgement, Lessons Learned
Service Level Agreements (SLAs)
a contract between a service provider (internal or external) and the end user that describes the level of service expected from the service provider.
Product Backlog
reflects not only a list of desired capabilities, written as User Stores, but also a list that is prioritized, with the highest business value and highest business risk things list first. Product backlog is owned by the customer- in Scrum through the role of the Product Owner.
*important feature in agile approach
Name 4 prioritization techniques
Kano Model, MoSCoW (MSCW) Analysis, PairedComparison Analysis, 100 points model
Kano Model
Identifying certain features or capabilities as Basic, performance, or excitement helps in the prioritization of which capabilities are truly must-have, what features may create meaningful competitive differentiators.
MoSCoW (MSCW) Analysis
Categorize features as Must Have, Should Have, Could Have, and Won’t Have (for now), Helps customers organize their thinking about what are truly must have capabilities, and enables identification of a Minimum Viable Product (MVP)
Paired Comparison Analysis
Looking at each pair of stories and prioritizing one over the others.
100 Point Method
Each stakeholder is given 100 points and can multi-vote their points across all the stories, which then give a weighted priority when combined.
Work Performance Data
the raw observations and measurements identified during activities being performed to carry out the project work.
*Agile projects may also include stories completed and accepted, progress through a product backlog and team delivery of stories against iteration plan.
Expert Judgement
used as key input by PMs to help assess needs, identify potential solutions and approaches, and ensure understanding of the larger project context.
Resource Calendar
identifies working days, shifts, and when specific resources are made available to the project.
-the calendar will be used to determine which resources (people, equipment, material, etc) are available during a planned activity period and should be taken into account when estimating project activities.
lessons-learned register
a project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository.
*Agile teams schedule a ceremony called a retrospective at the end of each iteration to identify potential issues, identify potential solutions & improve the processes the team uses to improve its overall performance,