Time Terminology Flashcards

1
Q

Activity

A

A piece of the project that must be completed (performed); sometimes called a “task”; can be divided into smaller pieces; typically has an assigned resource, cost amount, and expected duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity List (Output/Input)

A

A detailed list of activities that project team members use to know what work on the project they are responsible for completing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity-on-arrow (AOA)

A

A network diagramming method in which activities are shown on arrows and connected at nodes to show the sequence of activities. Also known as ADM, AOL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity-on-node (AON)

A

A network diagramming method in which activities are shown on the boxes or circles of the network diagram and connected via arrows. Also known as PDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Backward Pass

A

A network diagramming method that calculates the late start (LS) and late finish (LF) dates for each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bar Chart (Tool)

A

A chart that shows a time relationship between the activities of the project; also commonly called a Gantt chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

BiPert

A

A model for parallel programs with ingoing (inclusive) and outgoing (excusive) links

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Burst

A

The separation (or divergence) of activities on a network diagram from a central node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Calendar Unit

A

The smallest time unit used in project schedules such as minutes, hours, shifts, days, weeks, months, quarters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Control Schedule

A

The process of monitoring and updating the progress of the project and managing changes to scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Crashing

A

A duration compression technique in which more people are added to critical path activities to shorten the duration of the critical path or other impacted areas of the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Critical Chain Method (Technique)

A

A schedule technique used to evaluate the amount of float on the network paths; used to determine the minimum overall duration of the diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path

A

The series of activities that shows the overall duration of the project; can change as the project evolves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Critical Path Method (CPM) (Technique)

A

A network analysis method used to calculate total project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define Activities

A

The identification of appropriate activities to complete the project deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Dependency

A

A relationship between activities represented in the way activities are sequenced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Develop Schedule

A

The process of using activity sequences, duration estimates, and resources to create the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Discretionary Dependency (Soft Logic)

A

A dependency in which the project manager (or other decision maker) can choose to allow it to be a dependency or not, depending upon the needs of the project (Ex: Buying a plane ticket before booking a hotel reservation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Dummy Activities

A

A zero duration activity used in the arrow diagramming method (ADM) to show a logical relationship; represented graphically with an arrow having a dashed line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Duration

A

The overall amount of time on a project or activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Early Finish Date (EF)

A

The earliest time an activity can finish based on the network logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Early Start Date (ES)

A

The earliest time an activity can start based on the network logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Effort

A

The amount of labor needed to complete an activity or work package; typically measured in hours, days, or weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Estimate (Output/Input)

A

A logical, educated prediction of some project component; typically includes a tolerance of accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Estimate Activity Durations

A

The process of estimating the number of work periods (hours, days, weeks) to accomplish the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Estimate Activity Resources

A

Determination of resources (people, material, equipment) needed for a project, including the determination of when (or how much of) the resources are needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

External Dependency

A

A dependency that lies outside the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Fast Tracking

A

A schedule compression technique in which the main focus is to find activities that can be done in parallel and to adjust the activity sequences to reflect this adjustment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Finish-to-finish Dependency (FF)

A

A dependency used on project scheduling in which one activity cannot finish until the activity it is dependent upon finishes (Activity B cannot finish until Activity A finishes.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Finish-to-start Dependency (FS)

A

The default dependency type (with most project scheduling software) in which one activity cannot start until the one it is dependent upon finishes (Activity B cannot start until Activity A finishes .)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Float

A

The amount of time an activity can be delayed (slip) without causing a delay to the successor(s) activities, or the final finish date of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Forward Pass

A

A network diagram technique that calculates the early start (ES) and early finish (EF) dates for each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Free Slack (Free Float)

A

The amount of time an activity can be delayed without causing slippage (delay) to the early start of any subsequent activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Gantt Chart

A

The horizontal bar chart used in project management to show a time relationship. between activities. Also called a bar chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Imposed Date

A

A fixed date for an activity or milestone

36
Q

Lag

A

A delay to a successor activity from the predecessor (Ex: Activity A finishes then has a three day wait before Activity B can begin.)

37
Q

Late Finish Date (LF)

A

The latest time an activity can be finished without delaying the project finish date

38
Q

Late Start Date (LS)

A

The latest time an activity can start without delaying the project finish date

39
Q

Lead

A

Acceleration to a successor from the predecessor (Ex: Activity A finishes . But with a three-day head start, Activity B can begin three days before Activity A finishes.)

40
Q

Logical Relationship

A

An analytical association between two or more components of a project schedule

41
Q

Mandatory Dependency (Hard Logic)

A

A required dependency on a project; cannot be ignored (Ex: You must pour the foundation of a house before you can begin framing it.)

42
Q

Master Schedule (Tool)

A

A high level schedule which displays summary information associated with activities, deliverables, milestones, and WBS components

43
Q

Merge

A

A coming together (convergence) of activities on a network diagram

44
Q

Milestone Schedule (Tool)

A

A high level schedule which displays summary information associated with activities and
milestones

45
Q

Network Diagram

A

A schematic of logical relationships that make up the flow of activities on the project; always drawn from left to right

46
Q

Network Logic

A

The connecting of activities on the network diagram to establish the structure of the network diagram

47
Q

Network Path

A

A non-stop series of activities from the start to the finish of the network diagram

48
Q

Node

A

A point in a schedule network

49
Q

Path Divergence

A

A burst on the network diagram where the output of an activity goes to more than one activity

50
Q

PERT Weighted Average

A

An estimating technique used to take the pessimistic, optimistic, and realistic (most likely) estimates to achieve a cumulative estimate

51
Q

Precedence Diagramming Method (PDM)

A

A network diagramming process in which activities are represented in boxes

52
Q

Precedence Relationship

A

The logical relationship between activities as depicted in a precedence diagram

53
Q

Predecessor Activity

A

An activity that determines when its successor activity can begin

54
Q

Program Evaluation and Review Technique (PERT)

A

A project management estimation technique used when estimates for individual activities are questionable

55
Q

Project Calendar

A

A calendar that indicates working and non-working dates and shifts for the project

56
Q

Project Network Diagram

A

A view of the logical relationship (sequencing) of project activities

57
Q

Project Schedule

A

The document that lists the dates for performing project activities and meeting project milestones

58
Q

Project Schedule Network Diagram

A

A graphical representation of the logical relationships between project activities

59
Q

Project Time Management

A

The processes associated with an attempt to complete the project on time

60
Q

Resource Calendar

A

A calendar in the project management plan and schedule that shows working and non-working days

61
Q

Rolling Wave Planning (Technique)

A

A progressive elaboration approach to managing a schedule where the initial phases are defined at a detailed level with the remaining work at a high level: as the initial phases are done, the remaining phases are planned.

62
Q

Schedule

A

The planned dates, sequencing , resources , and durations for activities and milestones on a project

63
Q

Schedule Baseline

A

A schedule version over a specific time period that is used as the basis for scheduled activities comparison

64
Q

Schedule Compression (Technique)

A

The process of shorting the project schedule without modifying the scope of the project (Ex: crashing and fast tracking)

65
Q

Schedule Management Plan

A

Document that decomposes work packages, establishes the network diagram, determines required resources, determines activity durations, integrates activity components into a schedule, and deals with schedule changes and updates

66
Q

Schedule Milestone

A

A major event in the project schedule; typically involves the start or completion of a major component of the project

67
Q

Schedule Model

A

A model used in schedule network analysis to create the project schedule

68
Q

Schedule Network Analysis

A

A technique used to determine early and late start dates and early and late finish dates of project activities

69
Q

Scheduled Finish Date

A

The planned finish date for an activity, work package, or other piece of the schedule

70
Q

Scheduled Start Date

A

The planned start date for an activity, work package, or other piece of the schedule

71
Q

Sequence Activities

A

The process of determining and documenting the logical relationships between activities on the project

72
Q

Slack (Float)

A

The amount of time an activity can be delayed (slip) without causing a delay to the successor(s) activities, or the final finish date of the project

73
Q

Start-to-finish Dependency (SF)

A

A dependency used on project scheduling in which one activity cannot finish until the activity it is dependent on starts (Ex: Activity 8 cannot finish until Activity A starts)

74
Q

Start-to-start Dependency (SS)

A

A dependency used on project scheduling in which one activity cannot start until the activity it is dependent on starts (Activity 8 cannot start until Activity A starts.)

75
Q

Subnetwork

A

A section of a network diagram; can be associated with a work package or some other type of logical decomposition

76
Q

Successor

A

An activity that follows an activity logically connected to it

77
Q

Summary Activity

A

An activity that sums up the detailed activities underneath it; typically used to evaluate work packages and facilitate executive reporting

78
Q

Target Completion Date (TC)

A

A requested project completion date that can be a constraint for the project

79
Q

Target Finish Date (TF)

A

The date that the project (or activity) is anticipated to be completed

80
Q

Target Schedule

A

A preliminary schedule that can be used during initial stages of Planning; could differ from the baseline schedule at the conclusion of Planning

81
Q

Target Start Date (TS)

A

The planned start date of the project or activity

82
Q

Task

A

An activity to be completed on the project

83
Q

Three-point Estimate (Technique)

A

An estimating technique that can be applied to schedule or budget; uses three estimates for each activity; uses an optimistic, pessimistic, and realistic (most likely) estimate

84
Q

Total Slack (Total Float)

A

The amount of time an activity can slip (be delayed) from its early start date without delaying the overall finish date

85
Q

Variance

A

A result that is outside of the expected result.

86
Q

Work Performance Information (Output/Input)

A

Data associated with the completion of work on the project; can include deliverable status, actions associated with preventative and corrective measures, and change requests