Acronyms Flashcards

1
Q

PM (General)

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PMP (General)

A

Project Manager Professional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CAPM (General)

A

Certified Associate in Project Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PgMP (General)

A

Program Manager Professional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PMA (General)

A

Positive Mental Attitude

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PMI (General)

A

Project Management Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PMBOK (General)

A

Project Management Book of Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PWBS (General)

A

Program Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IO (General)

A

Inputs/Outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ITTO (General)

A

Inputs/Tools & Techniques/Outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

TMI (General)

A

Too Much Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

KBTN (General)

A

Kick Butt and Take Names

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ASQ (Framework)

A

American Society for Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PMO (Framework)

A

Project/Program Management Office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

CCB (Integration)

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PMIS (Scope)

A

Project Management Information System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

WBS (Scope)

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

ADM (Time)

A

Arrow Diagraming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

AOA (Time)

A

Activity on Arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

AOL (Time)

A

Activity on Line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

AON (Time)

A

Activity on Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

CPM (Time)

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

EF (Time)

A

Early Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

ES (Time)

A

Early Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

FF (Time)

A

Finish to Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

FS (Time)

A

Finish to Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

GERT (Time)

A

Graphical Evaluation Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

LF (Time)

A

Late Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

LS (Time)

A

Late Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

PDM (Time)

A

Precedence Diagraming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

PERT (Time)

A

Program Evaluation Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

RBS (Time)

A

Resource Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

SF (Time)

A

Start to Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

SS (Time)

A

Start to Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

TC (Time)

A

Target Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

TF (Time)

A

Target Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

TF (Time)

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

TS (Time)

A

Target Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

AC (Cost)

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

ACWP (Cost)

A

Actual Cost of Work Performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

BAC (Cost)

A

Budget at Completion

42
Q

BCR (Cost)

A

Benefit Cost Ratio

43
Q

BCWP (Cost)

A

Budgeted Cost of Work Performed

44
Q

BCWS (Cost)

A

Budgeted Cost of Work Scheduled

45
Q

CPI (Cost)

A

Cost Performance Index

46
Q

CV (Cost)

A

Cost Variance

47
Q

DDB (Cost)

A

Double Declining Balance

48
Q

EAC (Cost)

A

Estimate at Completion

49
Q

EPV (Cost)

A

Expected Present Value

50
Q

ETC (Cost)

A

Estimate to Complete

51
Q

EV (Cost)

A

Earned Value

52
Q

EVM (Cost)

A

Earned Value Management

53
Q

EVT (Cost)

A

Earned Value Technique

54
Q

FV (Cost)

A

Future Value

55
Q

IRR (Cost)

A

Internal Rate of Return

56
Q

OOM (Cost)

A

Order of Magnitude

57
Q

NPV (Cost)

A

Net Present Value

58
Q

PV (Cost)

A

Planned Value or Present Value

59
Q

ROI (Cost)

A

Return on Investment

60
Q

ROM (Cost)

A

Rough Order of Magnitude

61
Q

SPI (Cost)

A

Schedule Performance Index

62
Q

SV (Cost)

A

Schedule Variance

63
Q

TCPI (Cost)

A

To Complete Performance Index

64
Q

VAC (Cost)

A

Variance at Completion

65
Q

COQ (Quality)

A

Cost of Quality

66
Q

FMEA (Quality)

A

Failure Mode and Effect Analysis

67
Q

JIT (Quality)

A

Just in Time

68
Q

LCL (Quality)

A

Lower Control Limit

69
Q

LSL (Quality)

A

Lower Specification Limits

70
Q

TQM (Quality)

A

Total Quality Management

71
Q

UCL (Quality)

A

Upper Control Limit

72
Q

USL (Quality)

A

Upper Specification Limits

73
Q

VE (Quality)

A

Value Engineering

74
Q

VOC (Quality)

A

Voice of the Customer

75
Q

EMV (Risk)

A

Expected Monetary Value

76
Q

RBS (Risk)

A

Risk Breakdown Structure

77
Q

SWOT (Risk)

A

Strengths, Weakness, Opportunities, Threats

78
Q

BOM (Procurement)

A

Bill of Materials

79
Q

CPF (Procurement)

A

Cost Plus Free

80
Q

CPFF (Procurement)

A

Cost Plus Fixed Fee

81
Q

CPIF (Procurement)

A

Cost Plus Incentive Free

82
Q

CPPC (Procurement)

A

Cost Plus Percentage of Cost

83
Q

CR (Procurement)

A

Cost Reimbursable

84
Q

FFP (Procurement)

A

Firm Fixed Price

85
Q

FP (Procurement)

A

Fixed Price

86
Q

FPEPA (Procurement)

A

Fixed Price Economic Price Adjustment

87
Q

FPIF (Procurement)

A

Fixed Price Incentive Free

88
Q

IFB (Procurement)

A

Invitation for Bid

89
Q

PO (Procurement)

A

Purchase Order

90
Q

PTA (Procurement)

A

Point of Total Assumption

91
Q

RFB (Procurement)

A

Request for Bid

92
Q

RFI (Procurement)

A

Request for Information

93
Q

RFP (Procurement)

A

Request for Proposal

94
Q

RFQ (Procurement)

A

Request for Quote

95
Q

RFT (Procurement)

A

Request for Tender

96
Q

SOW (Procurement)

A

Statement of Work

97
Q

SR (Procurement)

A

Share Ratio

98
Q

T&M (Procurement)

A

Time and Materials

99
Q

TC (Procurement)

A

Target Cost

100
Q

TP (Procurement)

A

Target Profit

101
Q

OBS (Human Resources)

A

Organizational Breakdown Structure

102
Q

RAM (Human Resources)

A

Responsibility Assignment Matrix