Time Management Flashcards

1
Q

The Time Management Process

A
  • Define activities
  • Sequence activities
  • Estimate activity resources
  • Estimate activity durations
  • Develop schedule
  • Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Three ways to plan and manage time with WBS

A
  1. high level WBS. milestone plan
  2. Scheduled work packages
  3. Scheduled activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe activity in a Critical Path method

A
Activity number
Responsibility
Duration
Activity task description
Early Start
Early finish
Late Start
Late finish
Total float (EF-LF)
Free float (relative to successor)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Chain Planning Method

A
  • Work packages estimate is for shortest time possible.

- Buffers are defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CCPM Planning of Buffers

A
  • Plan with explicit buffers at the end.
  • Finish task as fast as possible.
  • Plan only net times for tasks.
  • Plan feeding buffers for lateral arms