Time Management Flashcards
1
Q
The Time Management Process
A
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity durations
- Develop schedule
- Control schedule
2
Q
Three ways to plan and manage time with WBS
A
- high level WBS. milestone plan
- Scheduled work packages
- Scheduled activities
3
Q
Describe activity in a Critical Path method
A
Activity number Responsibility Duration Activity task description Early Start Early finish Late Start Late finish Total float (EF-LF) Free float (relative to successor)
4
Q
Critical Chain Planning Method
A
- Work packages estimate is for shortest time possible.
- Buffers are defined.
5
Q
CCPM Planning of Buffers
A
- Plan with explicit buffers at the end.
- Finish task as fast as possible.
- Plan only net times for tasks.
- Plan feeding buffers for lateral arms