Time Flashcards
What are the inputs to Plan Schedule Management?
Project Mgmt Plan
Project Charter
EEFs
OPAs
What are the 7 Time Process steps?
- Plan Schedule Management
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity durations
- Develop schedule
- Control schedule
What are inputs to define activities?
Schedule mgmt plan
Scope baseline
What are tools and activities to define activities?
Decomposition
Rolling Wave Planning
Expert judgement
What are outputs to define activities?
Activity List
Milestone List
What is Rolling Wave Planning?
Concept that utilizes the progressive elaboration planning in planning.
What is Control Account?
A point placed in a WBS above the work package level to help estimating when all the details aren’t immediately available at the work package level.
What is Planning Packaging?
The planning package is a piece of the WBS between the control account and the work package.
Enter cards about Sequence Activities.
TBD
What is a network diagram?
A network diagram is a schematic of project activities and is the tool used to evaluate schedule compression techniques such as crashing and fast tracking.
What are the five types of diagramming types?
Precedence Diagramming Method (PDM) Activity on Node (AON) Arrow Diagramming Method (ADM) Activity on Arrow (AOA) Activity on line (AOL)
What is the GERT diagramming?
Diagramming technique that uses feedback loops as iterations are completed.
What are four types of predecessors?
Finish to start: A must be completed before B begins
Finish to Finish: B cannot finish until A is finished
Start to start: When A starts, B can start
Start to finish: A starts before B finish
What is lag?
Lag is delay between activities
What is lead?
Use lead when something can begin bf its predecessor is done.
What are the inputs to Estimate Activity Resources?
- Schedule mgmt plan
- Activity list
- Resource calendar
- Risk register
- Activity cost est
- Activity attributes
- EEFs
- OPAs
What are tools and techs for Estimate Activity Resources?
1 Expert judgement 2 Alternative analysis 3 Published estimating data 4 Bottom up estimating 5 Proj mgmt software