Test Reivew Flashcards
While the __________ identifies the work to be done, the _________ identifies the people who will do the work
- Work Breakdown Structure (WBS)
* Organizational Breakdown Structure (OBS)
__________= BCWP – ACWP
Cost Variance
Contracts of _____ or more require a formal EVM system validation.
$50M
For contracts awarded after July 1, 2012 the _______________________ has replaced the Contractor performance reports and and Integrated Master Schedule (IMS) contractual requirements.
Integrated Program Management Report (IPMR)
There are _____ formats for the integrated program management report (IPMR)
7
The ____________________ is the contractor’s time-phased plan for accomplishing the work on the contract. It establishes the scope, schedule, and budget targets for the program.
Performance Measurement Baseline (PMB)
For the EVM accounting system the PM must be able to account for both labor and ___________ costs
Material
The _______________________ is a formal review conducted jointly between the government and the contractor to assess the validity of control account budgets, resources, and time phasing. It is mandatory for all EVM contracts
The Integrated Baseline Review (IBR)
_____________ provide a forum for communicating across different functional areas, used to clarify design requirements and design maturity, helps determine whether to proceed with development, establishes common baselines and is event, not calendar driven
Technical Reviews
During the ______________ top-level design for each configuration item function and interface is evaluated to determine if it is ready for detailed design
Preliminary Design Review (PDR).
What are the three configuration baselines.
- functional baseline
- allocated baseline
- ***product baseline
The overall system level baseline which is established during the Technology Maturation and Risk Reduction Phase is the _____________ Baseline
Functional
The _________________ baseline is established latter in the EMD Phase and is the basis for a production contract
Product Baseline
The Acquisition Program Baseline (APB) is developed by the __________for Milestone B, and is updated prior to each Milestone.
PM
Only the _________________________ can approve changes to the APB.
Milestone Decision Authority (MDA)