2611 - Earned Value Management Flashcards

1
Q

While the __________ identifies the work to be done, the _________ identifies the people who will do the work

A
  • Work Breakdown Structure (WBS)

* Organizational Breakdown Structure (OBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a tool that allows both Government and contractor Program Managers (PMs) to have visibility into technical, cost, and schedule planning, performance, and progress on their contracts.

A

Earned Value Management (EVM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

___________-= BCWP – ACWP

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

____________= BCWP – BCWS

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

______________-= BCWP/ACWP

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

___________= BCWP/BCWS

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contracts of _____ or more require a formal EVM system validation

A

$50M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

___________________is an integrated management system; coordinates work scope, schedule, and budget goals, and objectively measures progress towards these goals.

A

Earned Value Management (EVM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The___________________________________ is the only organization recognized by DoD to perform EVMS Validation.

A

Defense Contract Management Agency (DCMA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The __________________________is responsible for conducting audit reviews of the contractor’s accounting system policies, procedures, and activities.

A

Defense Contract Audit Agency (DCAA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

For contract’s awarded prior to July 1, 2012, the __________________is a contractually required report, prepared by the contractor, containing performance information derived from the internal EVMS.

A

Contract Performance Report (CPR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

For contracts awarded after July 1, 2012 the _______________________ has replaced the Contractor performance reports and and Integrated Master Schedule (IMS) contractual requirements.

A

Integrated Program Management Report (IPMR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

There are _____ formats for the integrated program management report (IPMR)

A

7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

______________ indicates how much over or under budget the project is.

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

________________indicates how much ahead or behind schedule the project is.

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

________________________measures how efficiently the contractor is performing the work based on the original planned budget.

A

Cost Performance Index (CPI)

17
Q

What are the three basic elements of performance measurement

A
  • Cost performance
  • Schedule considerations
  • Accomplishment of technical performance requirements
18
Q

The___________________________ is the sum of the time-phased BCWS for all work, planning, and summary level packages.

A

Performance Measurement Baseline (PMB)

19
Q

The ____________________ is the contractor’s time-phased plan for accomplishing the work on the contract. It establishes the scope, schedule, and budget targets for the program.

A

Performance Measurement Baseline (PMB)

20
Q

Performance Measurement Baseline (PMB) development follows a 3 step process:

A
  • Define the work (WBS)
  • Schedule the work
  • Allocate budgets
21
Q

_______________are management points for planning and control since they represent the work assigned to one responsible organizational element on one program WBS.

A

Control accounts

22
Q

What are the different methods to measure performance against the Performance Measurement Baseline.

A
  • 0-100 Method: Once job is finished, value is earned (short duration)
  • 50/50 Method: Earn 50% when start, earn 50% when completed
  • Value Milestone Method: Assign budgets to milestones and earn as each milestone is reached
  • Completed or Equivalent Unit Method: Count units being fabricated or completed operations that go into a unit
  • Planning Package (Rolling Wave): Lock in budgets prior to beginning work.
23
Q

For the EVM accounting system the PM must be able to account for both labor and ___________ costs

A

Material

24
Q

What are the two aspects of Labor cost?

A
  • Performance: Did we use more hours than planned to accomplish the work?
  • Rates: Did the work cost us more than planned?
25
Q

What are the two aspects of Material cost?

A

Price: Did the material we used cost more than we planned?

• Usage: Did we use more materials than planned?

26
Q

The _______________________ is a formal review conducted jointly between the government and the contractor to assess the validity of control account budgets, resources, and time phasing. It is mandatory for all EVM contracts

A

The Integrated Baseline Review (IBR)

27
Q

DCMA performs two major types of EVMS surveillance:

A
  • System Surveillance

* Program / Contract Surveillance

28
Q

Who are the Key DCMA players involved in the surveillance

A

 EVM Monitor – Inspects to ensure system compliance and monitors metrics to evaluate contract performance
 Administrative Contracting Officer (ACO) – Approves contractor’s EVMS system and ensures contractual EVMS requirements are met
 Program Integrator (PI) (ACAT I/II Programs)- Leads a multi-functional Program Support Team (PST). Takes input from EVM Monitor, ACO and other functional experts (e.g. Quality, Manufacturing, Supply Chain) to provide “insightful analysis” based on all inputs including EVM analysis if contractually required

29
Q

The 32 EVMS guidelines in _______________provide a framework to evaluate the adequacy of a contractor’s EVM system.

A

ANSI/EIA-748