2615 - APB Breaches Flashcards
The Acquisition Program Baseline (APB) is developed by the __________for Milestone B, and is updated prior to each Milestone.
PM
Only the _________________________ can approve changes to the APB.
Milestone Decision Authority (MDA)
The __________________________defines the space between the Key Performance Parameter (KPP) objectives and thresholds in which trade-offs can be made between cost, schedule and performance without requiring MDA approval.
Acquisition Performance Baseline (APB)
What are the performance parameters considered by the user to be the most essential, and expressed in threshold and objective values
Key Performance Parameters (KPPs
The PM has the flexibility tot work within the _________________ between threshold and objective parameters.
trade space.
When a program deviation occurs, the _______________ must follow certain procedures.
PM
When a program deviation occurs the PM must notify the MDA _________ and has __________ to explain the reasons for the deviation and the steps taken to get the program back on track
- Immediately
* 30 Days
Within ______________ of the deviation, the PM must explain to the MDA the reason for the deviation and what steps need to be taken to bring the program back on track.
30 days
The _______________________ is APB approved at MS B or program initiation, whichever occurs later
Original Baseline Estimate
A Significant Breach occurs when you exceed the current baseline by __________ or the original baseline by __________
- +15%
* +30%
For a ___________ Breach, the service secretary notifies congress within 45 days of unit cost report (eg program deviation report) DOD submits a Selcected Action Report (SAR) with required unit cost breach information
Significant
Cost, schedule, and performance parameters are______________; a change in one parameter can affect the others.
interrelated
A________________ is a Congressional unit cost reporting requirements for Major Defense Acquisition Programs
Nunn-McCurdy Breach
During a _______, in addition to notification and SAR, the USD(AT&L) shall Determine the root cause(s) of the critical cost growth in consultation with the Director, Cost Assessment and Program Evaluation (CAPE), and carry out an assessment.
“Critical Breach”.
The obligation authority for the program is suspended if Congressional reporting timelines are not met for both __________ and _________Nunn-McCurdy Breaches.
- “significant”
* “critical”