2615 - APB Breaches Flashcards

1
Q

The Acquisition Program Baseline (APB) is developed by the __________for Milestone B, and is updated prior to each Milestone.

A

PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Only the _________________________ can approve changes to the APB.

A

Milestone Decision Authority (MDA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The __________________________defines the space between the Key Performance Parameter (KPP) objectives and thresholds in which trade-offs can be made between cost, schedule and performance without requiring MDA approval.

A

Acquisition Performance Baseline (APB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the performance parameters considered by the user to be the most essential, and expressed in threshold and objective values

A

Key Performance Parameters (KPPs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The PM has the flexibility tot work within the _________________ between threshold and objective parameters.

A

trade space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When a program deviation occurs, the _______________ must follow certain procedures.

A

PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When a program deviation occurs the PM must notify the MDA _________ and has __________ to explain the reasons for the deviation and the steps taken to get the program back on track

A
  • Immediately

* 30 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Within ______________ of the deviation, the PM must explain to the MDA the reason for the deviation and what steps need to be taken to bring the program back on track.

A

30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The _______________________ is APB approved at MS B or program initiation, whichever occurs later

A

Original Baseline Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A Significant Breach occurs when you exceed the current baseline by __________ or the original baseline by __________

A
  • +15%

* +30%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

For a ___________ Breach, the service secretary notifies congress within 45 days of unit cost report (eg program deviation report) DOD submits a Selcected Action Report (SAR) with required unit cost breach information

A

Significant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost, schedule, and performance parameters are______________; a change in one parameter can affect the others.

A

interrelated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A________________ is a Congressional unit cost reporting requirements for Major Defense Acquisition Programs

A

Nunn-McCurdy Breach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

During a _______, in addition to notification and SAR, the USD(AT&L) shall Determine the root cause(s) of the critical cost growth in consultation with the Director, Cost Assessment and Program Evaluation (CAPE), and carry out an assessment.

A

“Critical Breach”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The obligation authority for the program is suspended if Congressional reporting timelines are not met for both __________ and _________Nunn-McCurdy Breaches.

A
  • “significant”

* “critical”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Unit costs can be tracked by comparing Current Estimate to Current Baseline Estimate, and to ______________

A

Original Baseline Estimate