Test Chapter 9_Program Analysis Flashcards

1
Q

The PRIMARY purpose of program analysis as it is used in government is to

A

help decision-makers to sharpen their judgments about program choices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

While there is no complete method for program analysis that is agreed to by all the experts and is relevant to all types of problems, the MOST important element in program analysis involves the

A

development of alternatives and the definition of objectives or criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Electronic data processing is a particularly valuable tool of analysis in situations where the analyst has a processing problem solving

A

large input, many operations, and small output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In order for an analyst to use electronic data processing to solve an analytic problem, the problem must be clearly defined.
The BEST way to prepare material for such definition in electronic data processing is to

A

prepare a flow diagram outlining the steps in the analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

There is a wide variety in the types of computer memory available and a wide range of information processing tasks. Significant trade-offs exist between size, speed, and cost. In a situation where large capacity and low unit cost are most important than access speed, the BEST memory system is the

A

magnetic disk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Interactive or conversational programming is important to the program analyst ESPECIALLY for

A

testing trial solutions in rapid sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Program analysis often calls for recommendation of a choice between competing program possibilities that differ in the timing of major costs.
Analysts using the present value technique by setting an interest or discount rate are in effect arguing that, other things being equal,

A

postponing expenditures is advantageous at some measurable rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Of the following, the formula which is MOST appropriately used to estimate the net need for a given type of service is that net need equals

A

(client population x standard) - current supply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The purpose of feasibility analysis is to protect the analyst from naïve alternatives and, and MOST generally, to

A

anticipate potential blocks to implementation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

On the basis of the above data, it appears that the one alternative which is dominated by another alternative is Alternative

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the feasibility constraint is absolute and fixed, then the critical trade-off is between

A

lower cost and higher effectiveness on one hand and faster timing on the other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A classification of an agency’s activities in a program structure is MOST useful if it highlights

A

trade-offs that might not otherwise be considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CPM, like PERT, is a useful tool for scheduling large-scale, complex processes. In CPM, the critical path is the

A

longest path through the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Classical evaluative research calls for the use of control groups. However, there are practical difficulties in collecting data on individuals to be used as “controls” in program evaluations.
Researchers may attempt to overcome these difficulties by

A

using experimental demonstration projects with participants in the different projects serving as comparison groups for one another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During the course of an analysis of the remaining “life” of a certain city’s landfill for refuse disposal, there was a great deal of debate about the impact of changing rates of garbage generation on the amount of landfill needed and bout what rates of garbage generation to expect over the next decade. Faced with the need to attempt to resolve this debate, an analyst would construct a simple model of the refuse disposal system and

A

do a sensitivity analysis to test the impact of alternative assumptions about refuse generation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The limitations of traditional surveys have fostered the development and use of panels. A panel is

A

A group of respondents that serves as a continuous source of survey information

17
Q

The difference between sensitivity analysis and risk analysis is that risk analysis

A

includes an estimate of probabilities of different values of input factors

18
Q

A decision tree, although initially applied to business problems, is a graphic device which is useful to public analysts in

A

formulating the structure of alternatives

19
Q

The purpose of a management information system in an agency is to

A

structure data relevant to managerial decision-making

20
Q

The analyst could REASONABLY conclude regarding productivity that

A

it is Impossible to make a judgment about the productivity of the firefighting staff without a judgment about the value of a response to false alarm

21
Q

In the design of a productivity program for the sanitation department, the BEST measure of productivity would be

A

Tons of refuse collected per truck shift

22
Q

The cohort-survival method for estimating future population has been widely employed. In this method,

A

Net migration within cohorts is assumed to be zero

23
Q

Cost-effectiveness and cost-benefit analysis represent a systematic approach to balancing potential losses against potential gains as a prelude to public action. In addition to limitations based on difficulties of measurement and inadequacies in data that are typical of systematic program analysis, cost-benefit analysis suffers from a serious conceptual flaw in that

A

The definition of benefit or cost does not typically distinguish to whom benefits or costs accrue

24
Q

If you were asked to develop a total cost estimate for one year for a program involving both a capital improvement and operating costs, the BEST way to estimate the capital cost component would be to

A

Divide the amortized cost of the capital improvement by the projected life of the improvement

25
Q

In comparing the costs of two or more alternative programs, it is important to consider all relevant costs.
The MOST important principle in defining “relevant cost” is that

A

Only marginal or incremental cost should be considered in the estimate

26
Q

Different techniques for projecting future costs may be suitable in different situations. Assume that it is necessary to estimate the future costs of maintaining garbage collection vehicles.
Under which of the following conditions would it be advisable to develop
A cost-estimating equation rather than to use unadjusted current data?

A

When it is expected that more complex equipment will replace simpler equipment

27
Q

A comparison between two correlated means obtained from a small sample

A

T-test

28
Q

A comparison of three or more means.

A

Analysis of variance

29
Q

A comparison of the divergence of observed frequencies with those expected on the hypothesis of equal probability of occurrence.

A

X2 test (Chi-squared)

30
Q

A comparison of the divergence of observed frequencies with those expected on the hypothesis of a normal distribution.

A

X2 test (Chi-squared)

31
Q

A comparison between two uncorrelated means obtained from small samples

A

T-test

32
Q

There are many different models for evaluative research.

A time-series design is an example of a _______ experimental design.

A

Quasi

33
Q

In policy research, as in all kinds of research, it is important to develop research hypotheses early.
The MAIN purpose of a research hypothesis is to

A

Serve as a guide to the kind of data that must be collected in order to answer the research question.

34
Q

While descriptive and casual research are not completely separable, there has been a distinct effort to move in the direction of casual research.
Such an effort is epitomized by the use of

A

Predictive models and measures of deviation from predictions

35
Q

The one of the following which BEST describes a periodic report is that it

A

Provides a record of accomplishments for a given time span and a comparison with similar re spans in the past

36
Q

The PRIMARY purpose of including pictorial illustrations in a formal report is usually to

A

Present details that are difficult to describe verbally