Test Chapter 3_Contracts I Flashcards

0
Q

The most common approach used by a prime contractor to hold its subcontractors to their initial bids is the doctrine of promissory estoppel. In order to bind a subcontractor to its bid price, the prime contractor must prove each of the following EXCEPT that the

A

Subcontractor’s bid was formally accepted by the prime contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Which type of specification in a construction contract is intended to invite the greatest amount of competition?

A

Open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Written or graphic instruments issued prior to the execution of a contract, which modify or interpret the bidding documents by additions, deletions, clarifications, or corrections, are generally referred to as

A

Addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of warranty is used to limit the manufacturer’s responsibility in a construction contract?

A

Material-only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following statements represents the most important difference between drawings and specifications?

A

Specifications segregate information in order to aid in forming subcontracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The usual fidelity bond arrangement used in construction contracts is used to protect the contractor against

A

Dishonest acts of an employee such as theft, forgery or embezzlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Each of the following is a common purpose of an agreement in construction contract documents EXCEPT to

A

List the technical specifications that must be adhered to in the construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following is an Attribute that might be considered for the ceiling subsystem in a performance specification?

A

Fire safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Of the following types of hold-harmless clauses, ________ indemnification used in construction contracts indemnifies the owner and/or architect engineer even when the party indemnified is solely responsible for the loss.

A

Broad-form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Unit kitchens are an item that would be described under the _____ Division heading in the CSI Masterformat of specifications.

A

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following information is usually described in contract specifications?

A

Test and code requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The PRIMARY advantage associated with unit-price construction contracts is

A

Open competition on projects involving quantities of work that cannot be accurately forecast at the time of bidding or negotiation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following information is usually shown on drawings?

A

Interrelation of materials, equipment and space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following is/are typical purposes of a changed-condition clause in a construction contract?
I. To protect the owner from unforeseen increases in project costs
II. To reduce the contractor’s liability for the unexpected
III. To alleviate the need for including large contingency sums in the bid

A

II, III

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In construction contracts, a special warranty most frequently applies to the work of a(n)

A

Subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The MAIN advantage associated with the use of bid bonds as security for submitted proposals is that they

A

don’t immobilize appreciable sums of a contractor’s money

16
Q

Under most statutes governing contract law, a prime contractor may be relieved from its bid at any time after the opening of bids by the DOCTRINE OF MISTAKE. Which of the following are conditions that would support an argument for applying the doctrine of mistake?
I. Mistake relates to a material feature of the contract
II. Mistake is one of judgement, rather than fact
III. Owner is put in a status quo position, to the extent that he suffers no serious prejudice except the loss of his bargain
IV. Mistake is of a mechanical or clerical nature

A

I, III, IV

17
Q

Which of the following is NOT typically a disadvantage associated with the use of retainage arrangements in construction contracts?

A

Tends to sacrifice workmanship for speed of completion

18
Q

What is the term for a detailed compilation of the quantity of each elementary work item that is called for on the project?

A

Takeoff

19
Q

Which of the following is NOT one of the general types of specifications used in construction contracts?

A

Surety

20
Q

When negotiating a cost-plus contract, the owner and contractor must pay particular attention to each of the following considerations EXCEPT

A

The number of work units to be performed in executing the project

21
Q

According to construction contract law, what is the term for a promise by a party called the guarantor to make good the mistake, debt, or default of another party?

A

Guaranty

22
Q

In a technical section that has been written according to the CSI standard format, which of the following descriptions would be sequenced FIRST?

A

Summary

23
Q

In a construction contract, addendum changes to __________ are typically sequenced first.

A

Prior addenda

24
Q

Which of the following is typically added to a construction contract as a means of providing financial protection to a contractor?
I. Value engineering clause
II. Escalation clause
III. Escape clause

A

II, III