TBPPE: Time Flashcards

1
Q

Time (Scheduling) Management Step - Sequence Activities:

A

Identify and document the logical relationships between project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Time (Scheduling) Management Step - Estimate Activity Durations

A

Estimate the time required to complete each activity in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Time (Scheduling) Management Step -Develop Schedule:

A

Calculate the start and end times of the project activities and establish the overall project schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Time (Scheduling) Management Common Tools:

A

1) Network Diagram
2) Gantt Chart
3) Project Calendar
4) Milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Network Diagram:

A

Shows the chronological relationship between scheduled activities (tasks) (which are typically derived from the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Network Diagram - Early State (ES):

A

The earliest possible date on which an activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Network Diagram - Late Start (LS):

A

The latest possible date that an activity may begin without delaying the project (or a milestone)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network Diagram - Merge Activity:

A

An activity with two or more immediate predecessors (tasks flowing in)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Network Diagram - Burst Activity:

A

An activity with two or more immediate predecessors (tasks flowing out)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Network Diagram - Float (aka Slack, Total Float):

A

The amount of time an activity may be delayed from its early start without delaying the finish of the project. Float = (LS-ES) or (LF-EF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Uses of Network Diagram Step - Forward Pass:

A

By path, start at the beginning, add all durations together. Result: Duration of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Uses of Network Diagram Step - Backward Pass:

A

By path, start at the end, subtract all durations. Result: Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Uses of Network Diagram Step - Path Analysis:

A

By path, review each path for least amount of float. Result: Critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3 Steps to apply the Forward Path:

A

1) Add all activity times along each path as moving forward (ES + Duration = EF)
2) Carry the EF time to the activity nodes immediately succeeding the recently completed node. The EF becomes the ES of the next node.
3) If the succeeding node is a merge point, the largest preceding EF becomes the ES for that node.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

3 Steps to apply the Backward Path:

A

1) Subtract activity times along each path as moving backward (LF - Duration = LS)
2) Carry back the LS time to the activity nodes immediately preceding the recently completed node. The LS becomes the LF of the next node.
3) If the preceding node is a burst point, the smallest succeeding LS becomes the LF for that node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Critical path :

A

1) Path with the least floor path with the least float/slack time
2) Longest of all paths through the project
3) Gives the amount of scheduling flexibility

17
Q

Common options to shorten the Project/Reduce the Critical Path:

A

1) Eliminate tasks on the critical path
2) Re plan serial paths to become parallel
3) Shorten the duration of critical path tasks or of early tasks
4) Shorten longest tasks
5) Shorten easiest tasks
6) Shorten tasks that cost the least to speed up

18
Q

Gantt Charts Milestones:

A

1) Activities of “zero duration”
2) Take no time and consume no resources
3) Record significant events or deliverables
4) Serve as reminder to check on overall project status at key points

19
Q

Common Options typically applied to accelerate (crash) a Project:

A

1) Improve productivity of existing project resources
2) Change working methods employed
3) Reduced scope
4) Fast Track the project
5) Overtime work
6) Add resources to the Project Team

20
Q

Decision and Cost of accelerating a project is a Cost-Benefit Trade-off decision…

A

S = (Crash Cost - Normal Cost) / (Normal Time - Crash Time)