TBPPE: Time Flashcards
Time (Scheduling) Management Step - Sequence Activities:
Identify and document the logical relationships between project activities
Time (Scheduling) Management Step - Estimate Activity Durations
Estimate the time required to complete each activity in the project
Time (Scheduling) Management Step -Develop Schedule:
Calculate the start and end times of the project activities and establish the overall project schedule baseline
Time (Scheduling) Management Common Tools:
1) Network Diagram
2) Gantt Chart
3) Project Calendar
4) Milestones
Network Diagram:
Shows the chronological relationship between scheduled activities (tasks) (which are typically derived from the WBS
Network Diagram - Early State (ES):
The earliest possible date on which an activity can start
Network Diagram - Late Start (LS):
The latest possible date that an activity may begin without delaying the project (or a milestone)
Network Diagram - Merge Activity:
An activity with two or more immediate predecessors (tasks flowing in)
Network Diagram - Burst Activity:
An activity with two or more immediate predecessors (tasks flowing out)
Network Diagram - Float (aka Slack, Total Float):
The amount of time an activity may be delayed from its early start without delaying the finish of the project. Float = (LS-ES) or (LF-EF)
Uses of Network Diagram Step - Forward Pass:
By path, start at the beginning, add all durations together. Result: Duration of project
Uses of Network Diagram Step - Backward Pass:
By path, start at the end, subtract all durations. Result: Float
Uses of Network Diagram Step - Path Analysis:
By path, review each path for least amount of float. Result: Critical path
3 Steps to apply the Forward Path:
1) Add all activity times along each path as moving forward (ES + Duration = EF)
2) Carry the EF time to the activity nodes immediately succeeding the recently completed node. The EF becomes the ES of the next node.
3) If the succeeding node is a merge point, the largest preceding EF becomes the ES for that node.
3 Steps to apply the Backward Path:
1) Subtract activity times along each path as moving backward (LF - Duration = LS)
2) Carry back the LS time to the activity nodes immediately preceding the recently completed node. The LS becomes the LF of the next node.
3) If the preceding node is a burst point, the smallest succeeding LS becomes the LF for that node
Critical path :
1) Path with the least floor path with the least float/slack time
2) Longest of all paths through the project
3) Gives the amount of scheduling flexibility
Common options to shorten the Project/Reduce the Critical Path:
1) Eliminate tasks on the critical path
2) Re plan serial paths to become parallel
3) Shorten the duration of critical path tasks or of early tasks
4) Shorten longest tasks
5) Shorten easiest tasks
6) Shorten tasks that cost the least to speed up
Gantt Charts Milestones:
1) Activities of “zero duration”
2) Take no time and consume no resources
3) Record significant events or deliverables
4) Serve as reminder to check on overall project status at key points
Common Options typically applied to accelerate (crash) a Project:
1) Improve productivity of existing project resources
2) Change working methods employed
3) Reduced scope
4) Fast Track the project
5) Overtime work
6) Add resources to the Project Team
Decision and Cost of accelerating a project is a Cost-Benefit Trade-off decision…
S = (Crash Cost - Normal Cost) / (Normal Time - Crash Time)