Project Initiation and Initial Planning Flashcards

1
Q

Stakeholder:

A

Any party that is interested in or affected by the outcome of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Stakeholder analysis:

A
  • Who gets the output
  • Who provides the input
  • Managers of input providers or output recipients
  • Who has related responsibilities
  • Who gets the reward and benefits
  • Who suffers the penalties and consequences
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Stakeholder analyses drives:

A
  • Project organisation/governance design
  • Project process definition
  • Communication planning
  • Detailed requirements analysis
  • Risk planning
  • Resting and training
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Governance:

A

The framework by which the project is directed and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Key Roles - The Project Sponsor (Executive):

A

Authorizes and funds the project (via the Business Case), makes executives decisions beyond the Project Manager’s authority, has the power to overcome issues/ conflicts/remove barriers to project success (or cancel the project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Key Roles - Project Steering Committee or Board:

A

Provides senior level guidance to the project and facilitates integration of the PM team with functional units. Project Control and Assurance role. May also act as Change Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Key Roles - Project Manager

A

Leads projects activities and the day-to-day management of the project. Responsible for project delivery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project Management Team (Project Support):

A

Supports the project manager (e.g. on administrative tasks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Team (Team Managers):

A

Perform (coordinates) project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Charter:

A

A document that formally authorises the Project and assigns a Project Manager, includes elements:

1) Objectives & Business Case
2) High-Level Scope/State of Work
3) High-Level Budget Information
4) High-Level Timelines/Target Dates
5) Project Organization/Governance Information
6) Success Criteria
7) Initial Set of Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly