TBPPE: Resources Flashcards
1
Q
Main types of resources:
A
1) People with specific skills -> who will do what
2) Equipment (including all elements of the HW infrastructure)
3) Software infrastructure and tools
4) Facilities
2
Q
Resource Planning Techniques:
A
1) Responsibility Matrix
2) Resource Gantt Chart
3) Resource Loading Histogram
4) Resource Loading Table and Resource Levelling
3
Q
Resource Loading Histogram:
A
The amount of individual resources that an existing schedule requires over time
4
Q
Resource Levelling:
A
Revolving resource conflicts (including Overallocation) or achieving a smoother distribution of resources (mainly by delaying tasks based on their slack)