Task relationship Flashcards

1
Q

Finish-to-start (FS)

A

Task A must complete before Task B can begin. This is the most common relationship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Start-to-start (SS)

A

This relaltionship means Task A must start before Task B can start. This relationship allows both activities to happen in tandem.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Finish-to-finsih (FF)

A

This relationship means Task A must complete before Task B does. Ideally, two tasks must finish at exactly same time, but this is not always the case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Start-to-finish (SF)

A

This relationship is un-usual and is rarely used. It requires Task A to start so that Task B may finish. It is also known as just in time (JIT) scheduling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly