Strategy and MPC System Design Flashcards
Two key issues in the design of a firm’s MPC system are:
(i) linking MPC system design to the firm’s competitive strategy and (ii) integrating MRP and JIT systems.
MPC System Design in MTS Environment
MPS is stated in end items, which are produced to forecast demands
Customer orders are filled directly from stock
Procedures for monitoring accuracy of demand forecasts are required
Main source of uncertainty is forecast errors
MPC System Design in ATO Environment
Planning BOM is used to represent “average” product
Component production is controlled by the MPS with planning BOM, while final assembly is controlled by the FAS (Final Assembly Schedule)
Main source of uncertainty is product mix
MPC System Design in MTO Environment
MPC system needs to encompass preproduction engineering design activities as well as manufacturing and supplier operations
Customer orders are the MPS unit
The backlog of customer orders is used for:Estimating material and capacity requirementsCustomer order promising
Major source of uncertainty is the time requirements to complete each customer order
Integrating MRP and JIT
MRP is a push system, where we plan production and produce according to the planEffective system in a volatile environment represented by frequent design changes and/or volatile demandsRequires timely and accurate data collection as well as computational requirements
JIT uses a pull system, where production is triggered by actual consumptionsOperate effectively in a stable environment
MRP and JIT can be combined in various ways
Hybrid System #1: Kanban with MRP Planning
Can be used to deal with design changes and some degree of demand volatility while taking advantage of a pull system
Perform MRP for a short planning horizon (e.g., 2~3 weeks)
Determine total component demand during the planning horizon and calculate the number of kanban cards needed
Dispatch two outputs to the shop floor
Kanban cards
Dispatch list (i.e., normal output of an MRP system)
Hybrid System #1: Kanban with MRP Planning Part 2
A work center is authorized to produce a part only if it has a kanban card and the part is on the dispatch list
The work center does not produce the part if
The part is on the dispatch list but a kanban card is not received •It means the part will be needed but has not yet been consumed
It receives a kanban card but the part is not on the dispatch list•It means the part has been consumed but should be phased out due to a design change
Hybrid System #2: MRP for Capacity and Long Leadtime Items
Can be used when the design of the product is relatively stable but the demand patterns are still too volatile to allow for using a pure pull system
Control production by using a pull system (such as kanban)
Use MRP for
Planning for long leadtime items
Calculating capacity requirements and determining capacity levels/types accordingly
Calculating the number of kanban cards needed