Capacity Planning and Management Flashcards

1
Q

Capacity Planning and Management

Consists of Three Parts

A

Resource Planning

Rough-Cut Capacity Planning (RCCP)

Detailed Capacity Planning (CRP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Capacity planning and management addresses two managerial problems:

A

Match capacity to plans–by either providing sufficient capacity to execute plans or adjusting plans to meet available capacity.

Make capacity decisions considering customer service and capacity utilization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Capacity Planning in the MPC System

3 Ranges

A

Long Range

  1. Resource Planning
  2. RCCP

Medium Range
1. CRP

Short Range

  1. Finite Scheduling
  2. Input/OutPut Control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Links to MPC Modules

5 Parts

A
  1. RP
    Linked to strategic planning and sales and operations planning (SOP)

Plant and equipment investments, workforce level, etc.

  1. RCCP
    Linked to master production schedule (MPS)
    Converting MPS into requirements for key resources
  2. CRP
    Linked to material requirements planning (MRP)
    Calculating time-phased capacity requirements to execute material plans generated by MRP
  3. Finite Scheduling
    Linked to material requirements planning and shop floor control
    Detailed production scheduling within exact capacity constraints
  4. Input/Output Control
    Linked to shop floor control
    Monitoring actual consumption of capacity during the execution of detailed production plans
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The primary objective of RCCP and CRP techniques

A

is to estimate capacity requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Rough-cut capacity planning (RCCP)

Defined As

A

Capacity planning using overall factors (CPOF)
Capacity bills
Resource profiles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Capacity Planning Using Overall Factors (CPOF)

A

Simplest RCCP technique

Based on planning factors from historical data
Standard total production hours per unit of each product
Overall historical % workloads on work centers

Total capacity requirements are estimated from MPS and standard total production hours per unit of each product

The estimate is allocated to work centers based on overall historical workloads (rather than workloads on work centers of individual products)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Capacity Bills

Defined As

A

A bill of capacity is developed for each end product from its BOM and routing data

The bill of capacity indicates total standard time required to produce one unit of an end product by work center

The capacity requirements for each work center is estimated from the bills of capacity and the MPS data

Requires more data than CPOF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Resource Profiles

A

Rough-cut capacity planning technique that considers production leadtime information
Using operations setback charts

Provides time-phased projections of capacity requirements for individual work centers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CPOF (Capacity Planning Using Overall Factors) is simplest, but valid to use only when

A

when workloads on work centers are similar for all products or product mixes are relatively stable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Capacity bills provides more-direct linkage between

A

individual products and the capacity required for individual work centers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Resource profiles consider production

A

leadtime information, while CPOF and capacity bills do not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Capacity requirements planning (CRP) differs from

A

the rough-cut capacity planning procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CRP

4 Parts

A

Utilizes time-phased material plans from MRP

Takes into account components in stock

Accounts for the current status of work-in-process

Takes into account demand for service parts and other demands not accounted for in the MPS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

MRP and CRP procedures

A

MRP generates material plans without considering capacity limits (infinite loading)
CRP calculates capacity requirements to examine the capacity implications of those plans
Assumes that if one knows of capacity requirements well in advance, either capacity or plan can be adjusted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Advanced planning and scheduling (APS)

A

Plan materials and capacity simultaneously
Better capacity utilization, faster total production leadtime, lower work-in-process inventories
* APS may also stand for Advanced Production Scheduling

17
Q

Finite scheduling

A

(or finite loading) is not only a shop scheduling process but also an important part of advanced planning and scheduling
In finite scheduling, work centers are scheduled only up to their capacity limits
Establishes detailed schedules (start and finish times) of each job for each work center
When a work center’s capacity is not sufficient for all planned jobs, prioritization rules determine which jobs will be shifted to later times

18
Q

Vertical loading

A

Scheduling a work center–independently

19
Q

Horizontal loading

A

All work centers required to complete a job are taken into account

The highest-priority job is scheduled in all of its work centers, then the job with the next highest priority, and so on

Horizontal loading can be extended to entire product structure (end products, sub-assemblies, and components)

20
Q

Forward scheduling

A

(or front scheduling)

Starts with the current date scheduling into the future, where each job is completed as early as possible

21
Q

Backward scheduling

A

(or back scheduling)

Scheduling jobs backward from their due dates

22
Q

Capacity Monitoring with Input/Output Control

A

One key capacity management issue concerns the match between planning and execution

Capacity data in input/output analysis are usually expressed in hours

Actual input/output vs. planned input/output in each period for each work center

Differences between plan and actual must be addressed

23
Q

Actual/planned input and output

A

Planned input = Expected arrivals of jobs, expressed in standard hours

Actual input = Actual arrivals of jobs, expressed in standard hours

Planned output = Planned production hours
Results from staffing level, hours of work, etc.

Actual output = Actual quantities completed, expressed in standard hours

“Expressed in standard hours” means quantities multiplied by standard hour per unit

24
Q

Actual Input vs. Planned Input

A

If actual input consistently larger or smaller than planned input, forecasting should be revisited.

25
Q

Actual Output vs. Planned Output

A

If actual output is consistently larger or smaller than planned output, standard time should be updated.

26
Q

Actual Input vs. Acutal Output

A

If actual input is consonantly larger or smaller than actual output, capacity should be charged.