Production Activity Control Flashcards

1
Q

PAC

A

production activity control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Production Activity Control in the MPC System

A

Shop-floor Scheduling and Control (SFC)

Vendor Scheduling and Follow-Up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Production activity control (PAC) defined

A

Production activity control (PAC) concerns the execution of material plans.
PAC includes shop-floor scheduling and control (SFC). Many firms also assign vendor scheduling and follow-up to PAC. Order release is becoming more a part of PAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Linkage between MRP/CRP and PAC

A

MRP/CRP TO PAC is maaterial and capacity plans

PAC TO MRP/CRP IS Status information: Completions of operations, order closeout
Warning signals: Inadequacies in material and capacity plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Shop-Floor Scheduling and Control (SFC) Activities DEFINED AS

A

Schedule start and completion dates for each work order (or shop order) at each work center

Ensure the required materials, tools, personnel, and information are available when needed

Monitor and control the progress of work orders

Report work center efficiency, operation times, scrap, and so on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SFC Data Requirements

A

Item master
Item number/description, lead time, lot size

Bill of materials
Product structure

Work center master
Work center number, number of shifts per week, number of machine/labor hours per shift

Routing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Routing

A

Routing data for each part are essential inputs

Lead times for each operation typically consist of four elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Routing data for each part are essential inputs

QUESTIONS

A

What operations are performed to make the part
Which work center will perform each operation
How long each operation will take

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lead times for each operation typically consist of four elements

A
Queue time (time spent waiting to be processed)
Setup time (time to prepare the work center)
Run time (operation time per piece × lot size)
Move time (delay waiting to be moved plus time spent moving to the next work center)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Production Activity Control Technique

A

Operation setback chart
Gantt chart
Priority sequencing rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Priority Sequencing Rules

A

Sequencing: Determining the order of job processing at a work center

Priority sequencing rules (or priority rules) are simple heuristics used to select the order in which jobs will be processed

Commonly used priority sequencing rules
Earliest due date 
Shortest processing time
Order slack 
Slack per operation
Critical ratio
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Priority Sequencing Rules

Earliest part due date:

A

Schedule the job with the earliest due date of the part first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Priority Sequencing Rules

Earliest operation due date:

A

Schedule the job with the earliest due date of the current operation first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Priority Sequencing Rules

Shortest processing time (or shortest operation next):

A

Schedule the job with the shortest processing time first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Order slack:

A

Schedule the job with the least order slack first
Order slack = Time until the part due date – Total processing time remaining

Total processing time remaining is the sum of the setup times and run times of all remaining operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Slack per operation:

A

Divide the order slack by the number of remaining operations, and then schedule the job with smallest value first

17
Q

Critical ratio:

A

Schedule the job with the lowest critical ratio first

Critical ratio = “Time until the part due date” /”Lead time remaining “

Lead time remaining includes all elements of manufacturing lead time (queue, setup, run, and move times) for all operations that have not been completed

Sometimes total processing time remaining is used instead of lead time remaining