Stages of a Project (15 marks) 2022 Flashcards

1
Q

The ‘Principal’s Bond’ is released:

  • Concept & Preliminary Design
  • Contract Administration and Observation
  • Defects Liability Period
  • Detailed Design
  • Final Account settlement period
  • Developed Design
  • Practical Completion
  • Pre-design
  • Procurement
A

At the Final Account settlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Variation Price Requests, if required, are issued and costed
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Architect evaluates the tender prices received
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Either the Architect or Quantity surveyor prepares the Payment Schedules
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The specification is produced and double checked
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Detailed Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Principal takes over the contract works insurance in a new build project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Architect first considers and estimates the amount of documentation that will be required for the project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Pre-Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Principal and Architect can identify any newly discovered defects that require fixing under the contract to the satisfaction of the Architect
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Defects Liability Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The structural consultant’s requirements are coordinated with the mechanical services drawings to identify any significant clashes
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Developed Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Retentions are collected
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration and Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Architect assists the Client in developing and expanding the initial outline brief
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Concept and Preliminary Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Final preparation and compilation of the construction documentation occur to enable contract prices to be obtained
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Detailed Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The Architect issues Notices to Tenderers
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The most useful time to identify and locate existing underground
services locations
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Concept and Preliminary Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly