Stages of a Project (10 marks) 2018 Flashcards
The Architect proposes a fee for their services to the Client
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Pre-design
The contractor proposes a cost or contract sum to the client to carry out the contract works
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Procurement
The contractor completes agreed deferred works and minor errors
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Defects Liability Period
Tenders are evaluated by the Architect
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Procurement
A topographical survey is undertaken by a registered land surveyor
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Pre-design (1) or Concept & Preliminary (0.5)
The client takes over contract insurances from the contractor for a new building
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Practical Completion
Construction documentation is finalized by the Architect for Building Consent
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Detailed Design
Liquidated Damages are first charged to the contractor where the project has not been completed according to the agreed program
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Contract Administration & Observation
The specification is completed by the architect
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Detailed Design
Consultants’ requirements are first incorporated into the design prior to their full coordination
* Detailed Design
* Contract Administration and Observation
* Pre-design
* Final Account settlement period
* Developed Design
* Defects Liability Period
* Concept Design & Preliminary Design
* Procurement
* Practical Completion
Concept & Preliminary Design