Costing, Procurement, Tendering (4 marks) Flashcards
At the end of the Concept Design stage of a project, indicative outline costs of a project can be prepared by:
a) The Quantity Surveyor using a single line estimate
b) The Quantity Surveyor using an abbreviated elemental estimate
c) The Quantity Surveyor using an abbreviated elemental estimate or the Architect using a single line estimate
d) The Quantity Surveyor using a detailed elemental estimate or the Architect using an abbreviated elemental estimate
c) The Quantity Surveyor using an abbreviated elemental estimate or the Architect using a single line estimate
When a client relays a budget to the Architect, which of the following needs to be established:
a) If the Consultants’ fees are included or additional
b) If GST is included or additional
c) If GST and Consultants’ fees are included or additional
d) If GST, Consultants’ fees, project costs and fit out items are included or additional
d) If GST, Consultants’ fees, project costs and fit out items are included or additional
The most accurate estimates for building costs at the Detailed Design stage of a project are produced by:
a) The Quantity Surveyor
b) The Cadastral Surveyor
c) The Architect
d) The Contractor
a) The Quantity Surveyor
An abbreviated elemental cost estimate for a housing project:
a) Is based on using rates per metre squared to calculate costs
b) Is based on costing 4-5 key elements
c) Is based on costing 12-13 key elements
d) Is based on costing 20-50 key elements
c) Is based on costing 12-13 key elements
A Schedule of Quantities:
a) Is always used on large construction projects
b) Is prepared by the architect
c) Saves time for the chosen contractors when pricing tenders
d) Is used to establish the costs of a project in the developed design stage
c) Saves time for the chosen contractors when pricing tenders
Fit out items:
a) Are always included in the Architect’s price of the building
b) Are always excluded in the Architect’s price of the building
c) Are either included or excluded as noted in the Architect’s price of the building
d) Are either included or excluded as noted in the cost plan of the building
d) Are either included or excluded as noted in the cost plan of the building
At the Concept Design stage of a project, outline indicative costs of the project can most easily be given by:
a) The Quantity Surveyor using a detailed elemental estimate or the Architect using an abbreviated elemental estimate
b) The Quantity Surveyor using a single line estimate
c) The Quantity Surveyor using an abbreviated elemental estimate
d) The Quantity Surveyor using an abbreviated elemental estimate or the Architect using a single line estimate
d) The Quantity Surveyor using an abbreviated elemental estimate or the Architect using a single line estimate
$/m2 cost estimates:
a) Are often used by Architects to establish the first order of cost for a project where set rates are used
b) Are often used by Architects to establish the first order of cost for a project where rates need to be carefully chosen to suit the project
c) Are often used by Quantity Surveyors to establish the first order of cost for a project
d) Are often used by Architects right the way through all of the project stages
b) Are often used by Architects to establish the first order of cost for a project where rates need to be carefully chosen to suit the project
An abbreviated elemental cost estimate for a housing project:
a) Is based on using rates per metre squared to calculate costs
b) Is based on costing 4-5 key elements
c) Is based on costing 12-13 key elements
d) Is based on costing 20-50 key elements
c) Is based on costing 12-13 key elements
When a client relays a budget to the Architect, which of the following needs to be established:
a) If the Consultants’ fees are included or additional
b) If GST is included or additional
c) If GST and Consultants’ fees are included or additional
d) If GST, Consultants’ fees, project costs and fit out items are included or additional
d) If GST, Consultants’ fees, project costs and fit out items are included or additional
In a design and build contract:
a) The Architect employs the Contractor
b) The Contractor employs the Architect, either as part of their company or as a consultant to the construction company
c) The Contractor employs the Architect, always as a part of their
company
d) The Principal employs the Contractor and the Architect
b) The Contractor employs the Architect, either as part of their company or as a consultant to the construction company
Using the Tender process to procure a Contractor:
a) Enables the lowest price to always be achieved
b) Enables the best Contractor to be sourced based on the assessment criteria setup at the time of opening tenders
c) Enables the best Contractor to be sourced based on the assessment criteria setup at the time of tender preparation
d) Enables the best Contractor and the lowest price to always be achieved
c) Enables the best Contractor to be sourced based on the assessment criteria setup at the time of tender preparation
NTT’s (Notices to Tender) are:
a) Sent out to only the Contractors who ask questions to clarify the contract documents
b) Sent out to all Contractors to clarify the contract documents irrespective of who asked the questions
c) Sent out to all Contractors to clarify the contract documents irrespective of who asked the questions, and are dated
d) Sent out to all Contractors to clarify the contract documents irrespective of who asked the questions, and are dated and numbered
d) Sent out to all Contractors to clarify the contract documents irrespective of who asked the questions, and are dated and numbered
In evaluating tenders, the following processes are followed:
a) Tenders are negotiated to ensure the lowest price is understood
b) Tenders are clarified to ensure the lowest price is understood
c) Tenders are clarified to ensure comparisons are equitable and the lowest price is understood
d) Tenders are negotiated to ensure comparisons are equitable and the lowest price is understood
c) Tenders are clarified to ensure comparisons are equitable and the lowest price is understood
Who best estimates building costs at the Detailed Design stage of a project:
a) A Quantity Surveyor
b) A Cadastral Surveyor
c) The Architect
d) The Contractor
a) A Quantity Surveyor