Stages of a Project (15 marks) 2020 Flashcards
Retentions are partially released for the first time
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Practical Completion
The Architect considers the contract prices submitted by the contractors
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Procurement
Liquidated damages become payable on several occasions
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Contract Administration & Observation
Variation Price Requests are costed
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Contract Administration & Observation
The Client agrees the Architect’s proposed fee
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Pre-design
The architect assists the client to expand and clarify the initial outline brief
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Concept and Preliminary Design
The specification is completed by the consultant team
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Detailed design
The ‘Contractor’s Performance Bond’ is released
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
At Practical Completion
A Schedule of payment is prepared by either the Architect or the
Quantity Surveyor
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Contract Administration & Observation
&
Pre-design
Door Schedules are produced and double checked
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Detailed design
The latest stage that a Resource Consent application should be made for a project that is not a Permitted Activity under the Auckland Unitary Plan, so that the Client’s risk and expenditure is kept to a minimum
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Developed design &
Concept design
Consultants required for the project are identified for the project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Concept and preliminary design
Minor defects are remedied to the satisfaction of the Architect
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Defects Liability Period
the Architect first considers the approximate amount of documentation that might be required for a project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Pre-design
An indicative cost for the project is prepared by the Quantity Surveyor to see if the project is viable with respect to costs and brief requirements
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Concept and Preliminary Design
&
Start of developed design