Stages of a Project (15 marks) 2020 Flashcards

1
Q

Retentions are partially released for the first time
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The Architect considers the contract prices submitted by the contractors
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Liquidated damages become payable on several occasions
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variation Price Requests are costed
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Client agrees the Architect’s proposed fee
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Pre-design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The architect assists the client to expand and clarify the initial outline brief
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Concept and Preliminary Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The specification is completed by the consultant team
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Detailed design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The ‘Contractor’s Performance Bond’ is released
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

At Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A Schedule of payment is prepared by either the Architect or the
Quantity Surveyor
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Contract Administration & Observation
&
Pre-design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Door Schedules are produced and double checked
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Detailed design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The latest stage that a Resource Consent application should be made for a project that is not a Permitted Activity under the Auckland Unitary Plan, so that the Client’s risk and expenditure is kept to a minimum
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Developed design &
Concept design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Consultants required for the project are identified for the project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Concept and preliminary design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Minor defects are remedied to the satisfaction of the Architect
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Defects Liability Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

the Architect first considers the approximate amount of documentation that might be required for a project
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Pre-design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An indicative cost for the project is prepared by the Quantity Surveyor to see if the project is viable with respect to costs and brief requirements
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement

A

Concept and Preliminary Design
&
Start of developed design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly