Stages of a Project (10 marks) 2019 Flashcards
A ‘Variation’ to the contract is issued
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Contract Administration and Observation
A geotechnical survey is instructed for establishing the nature of the land beneath the proposed building footprint
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Concept & Preliminary Design
A ‘Bonus for Early Completion’ of the project is paid out
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
At Practical Completion or start of Defects Liability Period
The last stage where the amount of contract works insurance required for the project can be established
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Start of Procurement; end of Detailed Design
The ‘Principal’s Bond’ is released
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Final account
The Client presents their design brief to the Architect for the first time
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Pre-design
The earliest stage that a Resource Consent application can be made to establish the likelihood of consent success for a project typology that is not a Permitted activity under the Auckland Unitary Plan and to minimize the Client’s financial input into a project that may not proceed
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Concept & Preliminary Design
Minor defects are remedied to the satisfaction of the Architect
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Defects Liability Period
The Quantity Surveyor can establish a reasonably accurate and comprehensive cost plan for the proposed project, incorporating all of the Consultants’ design requirements to meet the Client’s brief
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Detailed Design
The Contractor issues a ‘Progress Payment’ claim
* Concept & Preliminary Design
* Contract Administration and Observation
* Defects Liability Period
* Detailed Design
* Final Account settlement period
* Developed Design
* Practical Completion
* Pre-design
* Procurement
Contract Administration and Observation