SPP DOC 301 - Section 7 Flashcards
1
Q
What is section 7 about?
A
CONTRACTOR – SEPARATE CONTRACTORS – SUB-CONTRACTORS RELATIONS
2
Q
Who has the right to let other contractors in connection to the work?
A
Owner
3
Q
Who provides other contractors the opportunity for introduction and storage of materials and shall properly connect and coordinate his work with theirs?
A
Contractor
4
Q
Who shoulders the cost of defective work?
A
The responsible party
5
Q
To whom shall the contractor inform to any defects done by sub-contractors?
A
Architect
6
Q
The owner is not responsible for these three reasons:
A
- death of disease contracted by the contractor or employees
- contractor’s plant or materials