1
Q

Owner’s Responsibilities (first three)

A
  • Provide FULL INFO of his req for the project
  • designate a representative authorized to act on his behalf
  • ISSUE ORDERS to the general contractor ONLY THROUGH the architect
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Owner’s Responsibilities (second three)

A
  • FURNISH or DIRECT the Architect
  • PAY for architectural and all other engineering and allied services req for the project
  • PAY for the design and consulting services
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Owner’s Responsibilities (last three)

A
  • Arrange and pay for such legal, auditing, insurance, counseling and other services
  • Pay for all reimbursable expenses incurred in the project
  • if owner notices anything that may impair the project’s success, he shall give notice to the Architect
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Architect’s Fee is based on what?

A

Project Construction Cost (PCC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When shall the additional compensation be required?

A

When the Architect has to render additional services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Type of payment for scale models, 3D models and walk-thru presentations

A

Separate payment by the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If the Architect renders additional professional services due to changes ordered by the owner after approval of the architect’s outputs, who will pay the architect?

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How will the Owner pay the architect if the work is abandoned or suspended in whole or in part?

A

Owner shall pay the architect corresponding to the amount due at the stage of suspension or abandonment of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the maximum suspension of months before the fee for the remaining works shall be doubled?

A

6 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The architect’s fee is a ____ amount.

A

net

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

All designs, drawings, models, specifications and other contract documents and copies thereof, prepared, duly signed, stamped and sealed and furnished as instruments of service, are the intellectual property and documents of whom?

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

During the progress of work, who shall furnish the Architect a copy of the records of expenses being incurred on the construction?

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

All Design and Placement of Signs still have to be approved by whom?

A

the Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

It means the cost of the completed building to the Owner, including the structure, plumbing/sanitary and electrical fixtures, mechanical equipment, elevators, escalators, air-conditioning system, fire protection system, alarm and clock system, communications and electronic system, elements attached to the building and all items indicated in the plans, designs, drawings and specifications prepared by the Architect and his consultants.

A

Project Construction Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Are the fees for the Architect, the Engineer, the Specialist Consultants or the salaries of the construction inspectors included in the PCC?

A

Naur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Regular Design Services include:

A

Project Definition Design
Schematic Design Phase
Design Development Phase
Contract Documents Phase
Bidding or Negotiation Phase
Construction Phase