SOE Questions Flashcards

1
Q

Can you explain the RICS Rules of Conduct and their importance for chartered surveyors?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do the five ethical principles (honesty, integrity, competence, service, respect, and responsibility) influence the behavior of a chartered surveyor?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the new Rules of Conduct, and how do they apply to both individual members and firms?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you describe the structure of the RICS, including its professional groups and bodies like Lionheart?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is it essential for surveyors to understand the ethical requirements set out by the RICS?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you explain how you handled the situation when the contractor on the 50 Berkeley Street project did not include overheads and profit in their tender? Why was transparency important in this case?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you ensure fairness and transparency in tendering processes on your projects, such as at 50 Berkeley Street?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you manage confidentiality and trust on Project A while working under a Non-Disclosure Agreement (NDA)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why did you use an alias when market testing the Stage 2 design for Project A, and how did this affect the procurement process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you balance maintaining professional integrity with the need to safeguard confidential project information?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you describe how you advised the contractor on Berners Street about declining their offer of a meal during the interim valuation process? Why is maintaining professional boundaries important in such cases?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you manage conflicts of interest in situations where personal and professional boundaries might overlap, such as in social settings with contractors?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When a contractor requested a 10-day extension during the tender process for the 21-29 Glasshouse Street project, how did you ensure the process remained transparent and fair for all bidders?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you ensure consistency in communication when advising both clients and contractors during the tendering process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What factors do you consider when advising clients on fair and transparent decision-making, particularly when they are faced with requests for tender extensions or changes?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why is it important to establish and maintain strong client relationships from the beginning of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How do you ensure that you are providing a professional service to clients throughout a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Can you explain the importance of identifying a client’s key objectives (time, cost, quality, and risk) at the outset of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How do you tailor your approach to client care when the client has conflicting priorities, such as cost versus quality?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is your understanding of your company’s complaints handling procedure?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

When would you escalate a complaint to the RICS, and what is the process for doing so?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the significance of communicating potential risks to the client, and how do you manage this communication?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Can you describe how you built a positive relationship with the client on the 50 Stratton Street project? What actions did you take to maintain this relationship?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How did you ensure effective communication with the client when presenting the MEP items in the Stage 4 change control register at 50 Stratton Street?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Can you provide an example of how you identified the client’s key objectives on the Clifton Street project and how this influenced your decision-making?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How did you balance the client’s priorities of cost certainty and obtaining a competitive price for the works during the Clifton Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Can you explain how attending regular meetings contributed to building trust and a high level of service with the client on the 50 Stratton Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How do you communicate technical or complex changes to clients who may not have a technical background, as you did for the MEP items at 50 Stratton Street?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Can you provide an example where you had to manage client expectations effectively, particularly when dealing with changes in project scope or cost?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Why is effective communication important in your role as a surveyor, and how do you demonstrate competence in written, oral, and presentation skills?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Can you explain how communication skills vary when using different formats, such as emails, calls, and in-person meetings?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How has attending the in-house seminar at Exigere helped you improve your communication and presentation skills?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is the importance of adapting your communication style depending on the audience (e.g., clients, contractors, or colleagues)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

How do you ensure that your written communication, such as emails or reports, is clear, concise, and professional?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What are the key elements of a successful presentation, and how do you prepare for them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Can you describe a situation where effective communication prevented a misunderstanding or resolved an issue?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Can you describe how you used your communication skills to chair meetings at 36-38 Berkeley Square and manage contrasting opinions? How did you ensure the objectives were addressed?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How did you apply your communication training when explaining post-contract changes and their cost impacts during meetings?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What techniques did you use to ensure that all parties, including the contractor, understood and accepted your valuation rules during negotiations at 36-38 Berkeley Square?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Can you provide an example of a difficult conversation you had with a contractor or client and how you managed it using effective communication techniques?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

How did you structure and communicate the pricing schedule for the 21-29 Glasshouse Street project to ensure that all contractors could submit accurate and comparable tender returns?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

What methods did you use to clearly explain technical or financial aspects of a project to non-technical stakeholders, such as clients or contractors?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

How did you balance diplomacy and assertiveness when negotiating costs with contractors or other project stakeholders?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Can you explain the significance of the Health and Safety at Work Act 1974 and how it impacts employers and employees in the construction industry?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What are the Construction (Design and Management) Regulations 2015 (CDM 2015), and how do they influence health and safety practices in the construction sector?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

How do the CDM regulations assign greater responsibility to designers after the 2015 update?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What are some key principles of health and safety that you learned from studying the RICS Surveying Safely guide?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

How do you ensure you follow safe procedures on a building site to protect both yourself and others?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Why is health and safety important in construction, and what are the main regulations that guide health and safety practices?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Can you outline the primary health and safety risks in construction projects, and how do you mitigate them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Can you describe how your first aid training has equipped you to handle basic health and safety incidents on-site?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Can you explain the issue you identified regarding the ductwork passing through a fire compartment on the 50 Berkeley Street project? How did you address this, and what impact did it have on health and safety compliance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

How do you assess health and safety risks when reviewing design information, as you did during the 50 Berkeley Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

How did you use health and safety knowledge during the 21-29 Glasshouse Street project to review and compare the Principal Designer’s information with the contractors’ submissions in the tender process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Can you give an example of when you identified a potential health and safety risk during the tendering process, and how you communicated this to the project team?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

How do you ensure that contractors’ health and safety submissions during tender processes meet industry standards, as in the 21-29 Glasshouse Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What procedures do you follow to assess the health and safety compliance of designs, and how do you ensure risks are mitigated before construction begins?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Can you explain the basic principles of accounting that are relevant to your role as a quantity surveyor?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

What is the purpose of a profit and loss account statement, and how is it used to assess a company’s financial performance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

How would you interpret a balance sheet, and what does it tell you about a company’s financial position?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

What is a cashflow forecast, and why is it important for both a business and a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

How would you interpret a balance sheet, and what does it tell you about a company’s financial position?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What is a cashflow forecast, and why is it important for both a business and a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Can you explain the key differences between a profit and loss account, balance sheet, and cashflow forecast?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

How do accounting principles impact a quantity surveyor’s role in managing a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Why is it important for a contractor to provide financial accounts in a PQQ (Pre-Qualification Questionnaire) submission, and what financial information is typically reviewed?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Can you explain the key elements of a comprehensive business plan and why they are important for an organization?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

What is the purpose of setting short, medium, and long-term strategic targets in business planning?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

How do external factors, such as market conditions, influence business planning and performance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

What is the significance of quarterly team meetings in reviewing business plans and strategic objectives at Exigere?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Can you explain how businesses assess resource levels and overhead costs, such as IT, HR, and finance, during the planning process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Why is it important for businesses to monitor and adjust their strategic targets in light of changing market conditions?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

How do overhead costs impact business profitability, and why must they be considered in business planning?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Can you explain the key principles of conflict avoidance in construction projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

What are the main forms of Alternative Dispute Resolution (ADR), and how do they differ from one another (negotiation, mediation, adjudication, and arbitration)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Can you describe the advantages and disadvantages of each ADR method (negotiation, mediation, adjudication, arbitration)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

How is dispute resolution typically handled within standard form JCT contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

What mechanisms for dispute resolution are included in JCT contracts, and how are they applied?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Why is early risk management important in avoiding disputes during construction projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

How does risk management contribute to conflict avoidance in the construction process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

What is the role of the RICS Black Book on conflict avoidance and dispute resolution in guiding industry best practices?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Can you explain how the RICS Black Book on risk management helps reduce the likelihood of disputes?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

What are the typical causes of conflict in construction projects, and how can they be managed or avoided?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

How does mediation differ from adjudication in terms of process and outcome?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Can you explain the concept of arbitration and how it applies within the construction industry?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

What is the role of negotiation in resolving conflicts, and when is it most effective?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Can you describe the steps involved in an adjudication process under a JCT contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

How does the timing of conflict resolution impact the outcome of a dispute in construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Can you explain the key principles of the Data Protection Act 2018 and how it implements GDPR (General Data Protection Regulation)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

What are the core requirements for handling data fairly, lawfully, and transparently under GDPR?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Why is it important to ensure that data is not stored without prior consent, and how do you ensure compliance with this requirement in your work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Can you explain what is meant by “using our taxonomy” when managing data, and why it is important for maintaining consistency and confidentiality?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

What steps must be taken to maintain the confidentiality of data when handling sensitive information, especially in a construction or quantity surveying context?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

How do you ensure that data received is stored and managed in line with GDPR and the Data Protection Act 2018?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

What are the main sources of data used for preparing cost estimates in your work, and how do you assess their reliability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

What factors do you consider, such as time and location, when using historical data to prepare estimates, and how do these affect the accuracy and relevance of the data?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

How do you decide when it is appropriate to use internal benchmarks, market testing, or external references such as SPON’S or BCIS for cost estimates?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Can you explain the role of market testing in ensuring that cost data remains accurate and up to date?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

What challenges have you encountered in sourcing and managing data for cost estimates, and how do you address these challenges?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Why is it essential to understand the limitations of data sources like BCIS and SPON’S, and how do you ensure that the data is used correctly?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

How do you ensure the accuracy and relevance of external data when preparing estimates for a specific project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Can you explain the importance of maintaining data integrity when preparing cost estimates and how you ensure the data is reliable?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

How does data management relate to risk management in construction cost estimation and project planning?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Can you explain the key principles of the Equality Act 2010 and how it promotes inclusive environments?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

What are the different types of discrimination protected under the Equality Act 2010?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

How does the Equality Act 2010 apply to the construction and surveying professions, and what are its implications for project teams?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Why is it important to embrace diversity and accept people from all backgrounds in the workplace and in professional settings?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

How can building healthy working relationships with both internal colleagues and external project teams promote inclusivity in the work environment?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Can you explain how the Equality Act 2010 framework helps ensure non-discriminatory practices in construction projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

What are some key factors to consider when promoting inclusive environments on construction sites or within project teams?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

How do inclusive environments contribute to better teamwork and overall project success?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

What are the potential consequences of failing to comply with the Equality Act 2010 in a professional environment?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

What steps can you take to ensure that all team members are treated equally and fairly during the life of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

How can you contribute to promoting an inclusive culture within your organization and on project teams?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

What steps can you take to ensure that all team members are treated equally and fairly during the life of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

How do you ensure that project teams, including external contractors and consultants, align with inclusive and non-discriminatory practices?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Can you explain the role of inclusive environments in promoting health, safety, and wellbeing on construction sites?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Why is it important for surveyors to be aware of their obligations under the Equality Act 2010 when working on diverse projects or teams?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Can you explain the three pillars of sustainability (social, economic, and environmental) and their significance in construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

How does the concept of sustainability ensure that present needs are met without compromising the ability of future generations?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

What are some examples of renewable and efficient technologies used in construction, and how do they contribute to sustainability (e.g., air source heat pumps, rainwater harvesting, PV panels)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

How do air source heat pumps, rainwater harvesting systems, and PV panels contribute to a building’s sustainability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Can you explain what BREEAM is and its role in assessing a building’s sustainability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

What is the WELL Building Standard, and how does it differ from BREEAM in terms of sustainability criteria?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

How does a BREEAM assessment measure sustainability across the different stages of a project, such as procurement, design, and construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

What are the key sustainability criteria under BREEAM, and how do they affect the cost and design of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

What is the importance of considering operational sustainability in addition to the sustainability of procurement, design, and construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Can you explain how sustainability is integrated into the construction process and why it is important for the built environment?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

How does aiming for sustainability certifications (such as BREEAM or WELL) impact the cost of a project’s design and construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

What is the role of a quantity surveyor in ensuring that a project meets its sustainability goals?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Can you describe how social sustainability is considered in the construction process and what measures are typically taken?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

How do economic factors influence the decision-making process when aiming for sustainable design and technologies?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

What are the main environmental challenges faced by the construction industry, and how can sustainable practices help address them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

How do energy-efficient technologies (such as PV panels or air source heat pumps) help reduce the overall carbon footprint of a building?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Can you explain the importance of rainwater harvesting in contributing to water conservation and sustainability in buildings?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

What are the potential trade-offs between sustainability goals and project costs, and how can these be balanced in a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

How do sustainable practices affect a project’s life cycle costs, and how are these considered in the planning stages?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

What are some of the challenges in implementing sustainable technologies on construction projects, and how can these be overcome?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Can you explain the difference between a cost estimate and a cost plan?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

What are the main sources of cost data you use when preparing a cost plan or cost estimate? How do you ensure their reliability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

How does market testing contribute to developing an accurate cost estimate for a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

What role do recent tenders, published cost data, SPONS, and BCIS play in your cost planning process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Why is it crucial to report costs accurately, and what implications does this have for clients?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

What are some external cost drivers that can affect a project’s cost plan, and how do you account for them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Can you explain how location, time, and market forces influence the adjustments made to cost plans?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

How do you assess the relationship between shape and space in terms of its impact on building cost and efficiency?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

What do the terms net to gross efficiency, wall to floor ratio, and storey height mean, and how do they affect overall building costs?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

How does net to gross efficiency influence the design and profitability of a building project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

In what ways does the wall to floor ratio impact construction costs and project feasibility?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Why is storey height a significant factor in the cost planning of a building project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

What techniques do you use to ensure that your cost estimates remain realistic and accurate throughout the design process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

How do you analyze the impact of these design concepts on the overall profitability of a building project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

How can design decisions influence the construction cost and overall project budget?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

What challenges might arise when trying to balance design aspirations with cost constraints, and how do you address them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Can you discuss any specific methodologies or software you use in the preparation of cost estimates and plans?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

How does the concept of efficiency in design relate to overall project profitability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

How do you ensure your cost estimates are adaptable to changes in project scope or market conditions?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

In your experience, how do different project delivery methods impact cost planning and estimation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Can you describe the various market sectors you have worked in for cost estimates and cost plans, and what unique challenges each sector presents?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

In preparing a cost plan for the MEP works at 20 Giltspur Street, what specific challenges did you face in ensuring that the costs were based on the latest and most accurate information?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

How did you ensure effective communication with the design team and the Services Consultant during the preparation of the cost plan?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Can you describe the various market sectors you have worked in for cost estimates and cost plans, and what unique challenges each sector presents?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

In preparing a cost plan for the MEP works at 20 Giltspur Street, what specific challenges did you face in ensuring that the costs were based on the latest and most accurate information?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Can you explain the significance of clearly highlighting any incomplete design elements in your cost plans, and how did you document these?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

How did you ensure effective communication with the design team and the Services Consultant during the preparation of the cost plan?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

What assumptions did you make regarding the life safety requirements at Stage 3 of the 20 Giltspur Street project, and how did you ensure these assumptions were communicated to stakeholders?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Describe the process you followed to prepare an order of cost estimate for the 1 Welbeck Street healthcare fit-out. What sources did you utilize?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

How did you determine the cost for specialist elements such as Medical Imaging Equipment, Medical Gas, and AV Equipment during the 1 Welbeck Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

What strategies did you employ to obtain cost advice from the market for the specialist elements mentioned in your experience?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

What methods do you use to ensure the accuracy and reliability of the data included in your cost estimates and plans?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

How do you incorporate contingency drawdown and provisional sum expenditure into your cost reporting process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

How do you approach the preparation of monthly cost reports during the construction phase, and what key elements do you include in these reports?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Can you explain how you track the financial position from the approved budget to the forecast final cost in your cost reports?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

How did your in-house training influence your approach to cost estimating and planning during your projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Can you discuss the importance of benchmarking in the cost estimation process and how it has impacted your work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

Describe any challenges you faced in reconciling client expectations with budgetary constraints during the cost planning process.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

How do you adapt your cost estimates and plans when new information or changes occur during the design phase?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

Can you explain how your cost planning has evolved from the initial stages of the project through to the construction phase?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

What tools or software do you use for cost estimation and planning, and how do they enhance your work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

How do you assess and mitigate risks associated with cost planning and estimating during the various stages of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

In your experience, how does collaboration with the design team affect the overall success of the cost planning process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

Can you elaborate on the specific macro-economic conditions that influenced the 5% increase in tender prices for 20 Giltspur Street? How did these factors impact the overall project budget?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

How do you assess and incorporate tender price inflation into your cost plans, and what tools do you use for this analysis?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

Describe the process you followed to communicate the 5% increase in major MEP plant equipment costs to the client. What rationale did you provide?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

In your experience, how does effective communication with the client influence their decision-making during the budgeting process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

Can you explain the significance of including the 5% increase in the stage 4 change register? How does this practice impact project accountability?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
187
Q

During the 50 Stratton Street project, how did you identify and quantify the impact of the change to the basement smoke ventilation system on the overall cost?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
188
Q

Describe how you presented the change control report to the client regarding the cost increases. What key elements did you highlight?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
189
Q

How did you anticipate the increased stage 4 cost plan total before the design was completed, and what assumptions did you make?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
190
Q

What strategies did you recommend for value engineering measures to help the client stay within budget? Can you provide specific examples?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
191
Q

Discuss the decision-making process you followed when advising the client to switch from a natural ventilation system to a hybrid mechanical system. What factors did you consider?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
192
Q

In the Clifton Street project, how did you assess the potential cost savings of switching to a hybrid VRF system? What criteria did you use?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
193
Q

Can you explain how omitting the AET system resulted in both cost savings and the additional 300 ft² of NIA? What calculations did you perform to support this recommendation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
194
Q

How do you manage and mitigate risks associated with changes in design that impact costs, such as the ones seen in the 50 Stratton Street project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
195
Q

What role do you believe collaboration with design teams plays in effective cost planning and control, particularly during stage 4 design?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
196
Q

How do you track and report on cost variances during the construction phase to ensure the project remains within budget?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
197
Q

What challenges did you face while implementing value engineering measures, and how did you overcome them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
198
Q

Describe any lessons learned from your experience at 20 Giltspur Street that have influenced your approach to future cost planning and design economics.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
199
Q

How do you ensure that the assumptions made during the cost planning process are realistic and achievable given the project’s constraints?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
200
Q

How do you keep abreast of changes in market conditions that affect material and labor costs, and how do you integrate this knowledge into your work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
201
Q

Reflect on how your experiences in cost planning for these projects have prepared you for future challenges in the field of design economics and quantity surveying.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
202
Q

What are the main features of the JCT suite of contracts that you have worked with, and how do they differ from the NEC contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
203
Q

Can you explain the advantages and disadvantages of using standard forms of contract compared to bespoke forms of contract? In what situations might a bespoke contract be more suitable?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
204
Q

Describe the essential elements that make up a valid contract. How do these elements ensure the enforceability of a contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
205
Q

What is consideration in contract law, and why is it important for a contract to be valid?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
206
Q

Can you explain the terms Relevant Events and Relevant Matters as they pertain to the contracts you have studied or worked with? How do they affect contract performance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
207
Q

What are Liquidated Damages (LADs), and how are they calculated within a contract? Can you provide an example of when they might be applied?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
208
Q

How does the concept of retention work in contract practice? What is its purpose, and how is it typically managed?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
209
Q

Discuss the key contractual mechanisms such as interim payments and practical completion. How do they influence cash flow and project management?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
210
Q

What is meant by making good defects, and how is this process typically handled under JCT contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
211
Q

How do you approach valuing changes in a contract? What methodologies or principles do you follow?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
212
Q

In your experience, how can a clear understanding of contract terms help prevent disputes between parties?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
213
Q

What role do you believe contract practice plays in the successful delivery of a project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
214
Q

Can you provide an example of a situation where a misunderstanding of a contract term could lead to a dispute?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
215
Q

How do you keep yourself updated on the latest changes and updates to standard forms of contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
216
Q

What is the importance of contractual documentation in managing a construction project? How does it contribute to overall project success?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
217
Q

How do you ensure that all parties involved in a project understand the contractual obligations and requirements?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
218
Q

Describe a scenario where understanding the principles of contract law has helped you in your work or studies.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
219
Q

How does your knowledge of Contract Law enhance your understanding of practical contract applications in the construction industry?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
220
Q

Can you explain the concept of contractual risk? How can effective contract practice help mitigate these risks?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
221
Q

Reflect on a learning experience during your studies or time at Exigere that has deepened your understanding of contract practice.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
222
Q

Can you describe the process you followed when conducting interim valuations for the Berners Street project? How did you ensure that the assessment of the contractor’s payment application was fair and accurate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
223
Q

When conducting interim valuations, what specific elements of the work do you review, and how do you decide the appropriate amount to recommend for payment?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
224
Q

How did you ensure that the payment recommendations were issued in a timely manner and in accordance with the JCT Design and Build 2016 contract? What are the consequences of not issuing a payment recommendation on time?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
225
Q

In your experience, what are the key aspects of JCT Design and Build 2016 that must be carefully considered when reviewing payment applications?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
226
Q

How do you manage any discrepancies or disagreements between the contractor’s payment application and your assessment? Can you provide an example from your experience?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
227
Q

Explain how you used JCT software to draft the Minor Works with Contractors Design 2016 Contract for the Glasshouse Street project. What were the most important aspects of populating the Contract Particulars?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
228
Q

How did you determine the appropriate rates for Liquidated Damages (LADs) and Completion Dates when populating the Contract Particulars for the Glasshouse Street strip-out?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
229
Q

Can you describe the process of compiling and issuing a full Contract pack to the Client’s legal team? What documents did you include, and why were they important for the successful execution of the contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
230
Q

What steps did you take to ensure the correct application of retention within the Minor Works with Contractors Design 2016 Contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
231
Q

What challenges did you face when preparing the Schedule of Amendments for the contract, and how did you resolve them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
232
Q

How did you ensure that the Contract Sum Analysis was accurate and aligned with the project requirements?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
233
Q

Can you explain the role of Employers Requirements in the contract and how you ensured these were clearly communicated to the contractor?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
234
Q

How did you ensure that the contract drafting and issuing process met the Client’s expectations and adhered to legal requirements?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
235
Q

How did you handle the Contractors Design Portion (CDP) items in the contract? How did you ensure that these were clearly defined and agreed upon by all parties?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
236
Q

When working on contracts, how do you ensure that all parties are aware of their contractual obligations and responsibilities?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
237
Q

How do you approach negotiating contract terms such as Liquidated Damages or Completion Dates with the contractor or client?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
238
Q

Can you describe a time when you encountered a contractual dispute or disagreement? How did you resolve it?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
239
Q

What lessons have you learned from drafting contracts that you would apply to future projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
240
Q

How do you ensure that contracts are compliant with relevant legal standards and industry best practices?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
241
Q

What do you consider the key risks in contract management, and how do you mitigate them when drafting or managing a contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
242
Q

Can you explain your reasoning for advising the client not to value off-site materials that were not listed in the contract for the Berners Street project? What risks did you foresee in doing so without a vesting certificate?

A
243
Q

What is a vesting certificate, and why is it important when valuing off-site materials in construction contracts?

A
244
Q

How do you mitigate risks related to contractor insolvency when valuing off-site materials? Can you explain the steps you would take to protect the client’s interests?

A
245
Q

When advising the client on their final payment during the Christmas holidays, how did you ensure that contractual payment deadlines were met? What was the potential risk of delaying the payment?

A
246
Q

How did you negotiate with the contractor to adjust the valuation date, and what strategies did you employ to ensure an agreement was reached while protecting the client’s interests?

A
247
Q

What are the potential penalties or risks associated with late payments in a JCT contract, and how can they be avoided?

A
248
Q

Can you explain the process of advising a client on the most appropriate contract form for a project, using the example of the TWPS Pumping Station? What factors did you consider when recommending the JCT Minor Works contract over the Intermediate Building Contract?

A
249
Q

How did you ensure that the Minor Works Contract was suitable for the enabling works package at TWPS? What were the key factors that led you to this recommendation?

A
250
Q

Can you explain the difference between a Minor Works Contract and an Intermediate Building Contract? In what situations would each be more appropriate?

A
251
Q

How do you advise a client when there is no requirement for Contractor Design Portion (CDP) in a contract? What risks are reduced when CDP is not included?

A
252
Q

How did you ensure that the client’s prior experience with the Minor Works Contract was fully considered when advising on the most suitable contract form for the TWPS project?

A
253
Q

In your experience, how do you approach contract negotiations with contractors when there is a potential for disagreement over payment terms or contractual clauses?

A
254
Q

How do you ensure that the contractual mechanisms (such as payment terms, LADs, retention) are clearly communicated to the client and understood by all parties during contract negotiations?

A
255
Q

When advising a client on contract selection, how do you assess the scope of works and design information to ensure that the correct contract is chosen?

A
256
Q

Can you provide an example of a situation where your advice on a contract helped mitigate a potential dispute or financial risk for the client?

A
257
Q

How do you ensure that contract terms are applied correctly and fairly throughout the duration of a project? How do you monitor compliance with the contract?

A
258
Q

How do you manage client expectations when there are delays or potential contractual issues? Can you provide an example where this occurred in one of your projects?

A
259
Q

Can you explain the process of managing contract amendments? Have you advised on amending any contracts in your experience?

A
260
Q

What challenges have you encountered when advising clients on contract issues, and how did you overcome them?

A
261
Q

How do you ensure that your contractual advice is aligned with best practices and industry standards?

A
262
Q

Can you explain the difference between a VRF (Variable Refrigerant Flow) system and a traditional 4-pipe heating and cooling system? In what situations would you recommend using a VRF system?

A
263
Q

What are the advantages and disadvantages of using a VRF system in a commercial building?

A
264
Q

What do you understand by the term simultaneous heating and cooling in a building, and why is it important when selecting the right HVAC system?

A
265
Q

Can you explain the role and advantages of prefabrication in construction, particularly in terms of modular and panelised construction?

A
266
Q

How does modular construction help reduce construction time, improve quality, and reduce costs? Can you provide examples of where this might be suitable?

A
267
Q

What are the key considerations when recommending panelised construction? How does it differ from traditional construction methods?

A
268
Q

Can you explain how prefabrication can improve the sustainability and efficiency of a construction project?

A
269
Q

What factors would you consider when determining whether to use prefabrication or on-site construction for a project?

A
270
Q

Can you explain what human-centric lighting systems are and how they function? What benefits do they offer in terms of productivity and well-being?

A
271
Q

How does circadian rhythm relate to human-centric lighting systems, and why is it important in building design?

A
272
Q

What are the main environmental benefits of using human-centric lighting systems in a commercial building?

A
273
Q

How do building services (MEP systems) such as heating, cooling, and lighting impact the overall performance and efficiency of a building?

A
274
Q

What considerations would you take into account when selecting an appropriate MEP system for a new commercial building?

A
275
Q

Can you explain how MEP services influence the cost, design, and construction of a project?

A
276
Q

How do you keep up-to-date with new developments in construction technologies and building services? Can you provide examples from recent CPD seminars you have attended?

A
277
Q

What are some key challenges associated with implementing new construction technologies in projects, and how can they be addressed?

A
278
Q

Can you explain how environmental services (such as heating, cooling, and lighting) contribute to the overall sustainability goals of a building?

A
279
Q

How do you ensure that the construction technologies recommended align with sustainability and energy efficiency targets?

A
280
Q

What role do building regulations and environmental standards play in the selection of construction technologies and MEP systems?

A
281
Q

Can you explain the benefits of automation in modern building services, and how automated systems improve building efficiency?

A
282
Q

Can you explain why a gas suppression system was chosen over a sprinkler system in the basement plant areas of 1 Welbeck Street? What are the key differences between the two systems?

A
283
Q

How did you approach questioning the need for a gas suppression system, and what did you learn from the design engineer’s explanation?

A
284
Q

What factors should be considered when specifying fire suppression systems in healthcare environments?

A
285
Q

How do you balance the need for cost efficiency with ensuring long-term operational protection when reviewing MEP designs?

A
286
Q

How does the inclusion of a gas suppression system impact the MEP budget in comparison to using sprinklers, and how would you communicate this to the client?

A
287
Q

Can you explain how you identified the need for a nurse call system when it wasn’t shown on the drawings? What led you to make this assumption?

A
288
Q

How do you ensure that all necessary MEP services are accounted for in the design when certain elements are missing from the drawings or specification?

A
289
Q

What steps did you take to confirm the inclusion of the nurse call system with the services engineer, and how did this affect the overall project budget?

A
290
Q

How do you manage communication with design teams to ensure assumptions are confirmed and reflected in later design stages?

A
291
Q

How would the omission of critical systems, like the nurse call system, impact the overall functionality and compliance of a private healthcare facility?

A
292
Q

Can you describe your process for reviewing interim payment applications against the actual work completed on-site? How did you identify that only 50% of the basement smoke extract system had been installed?

A
293
Q

How do you use construction issue design information to assess the accuracy of contractor payment applications?

A
294
Q

What were the key challenges in identifying discrepancies between the contractor’s payment application and the actual work completed, and how did you resolve these with the contractor?

A
295
Q

How do you maintain fairness and accuracy in your payment recommendations while maintaining positive relationships with contractors?

A
296
Q

Can you explain how discrepancies in MEP installations can affect the overall construction timeline and budget, and how do you mitigate these risks?

A
297
Q

How do you apply your understanding of MEP systems to ensure designs are cost-effective and fit for purpose?

A
298
Q

Can you describe the key considerations when reviewing MEP designs for healthcare facilities versus office buildings?

A
299
Q

How do you ensure that the construction technology used aligns with the client’s needs and budget?

A
300
Q

What is your process for identifying potential scope gaps in MEP systems during the design stage, and how do you handle these with the design team?

A
301
Q

How do you ensure quality control and compliance with the specified MEP systems during site visits and interim valuations?

A
302
Q

Can you provide examples of how you have used value engineering to improve the efficiency of MEP systems while maintaining functionality?

A
303
Q

How do you handle instances where MEP design information is incomplete or unclear, and what steps do you take to ensure that critical elements are not overlooked?

A
304
Q

Can you explain the benchmarking process you used for the CAT-A heating and cooling system? How did you identify that the design was above the benchmark rate?

A
305
Q

How did you approach the services engineer with your benchmarking analysis, and how was the discrepancy in the number of downflow units resolved?

A
306
Q

What was your rationale behind proposing a hybrid VRF solution to the client? What are the key differences between an AET system and a hybrid VRF system in terms of cost and performance?

A
307
Q

How do you manage the client’s expectations when cost plan estimates exceed the benchmark rates, especially at early design stages such as Stage 2?

A
308
Q

Can you describe the potential risks of waiting for further calculations before adjusting the cost plan, and how do you communicate these risks to the client?

A
309
Q

How do you ensure the client understands the technical implications of selecting alternative heating and cooling systems, such as the AET versus hybrid VRF options?

A
310
Q

How did you balance the cost implications of including three downflow units per floor with the need to maintain flexibility in the design as further calculations were pending?

A
311
Q

What is your approach to advising the client on system alternatives when the design team’s proposals exceed the set budget benchmarks?

A
312
Q

How do you communicate technical issues and cost discrepancies to clients in a way that is clear and understandable, especially when discussing complex systems like HVAC?

A
313
Q

Can you give examples of how you ensure that your cost advice is both timely and accurate, particularly when uncertainties in the design stage arise?

A
314
Q

What tools or methods do you use to present cost comparisons between different MEP systems to clients, and how do you support them in making informed decisions?

A
315
Q

How did you evaluate the cost impact of using the Artus fan coil units for the client, and what were the key financial benefits in comparison to traditional fan coil units?

A
316
Q

Can you explain how the Artus fan coil units help achieve a higher BREEAM rating and how this impacts the building’s operational efficiency?

A
317
Q

What were the main factors that led to your recommendation of using Artus units to improve BREEAM certification and reduce embodied carbon on the project?

A
318
Q

What process did you follow to develop a cost option appraisal for the Artus units? What key elements did you focus on to ensure the client had a comprehensive understanding of the cost implications and benefits?

A
319
Q

How do you ensure that sustainable solutions, such as the Artus units, are both viable and cost-effective for the client, especially when trying to achieve environmental certifications like BREEAM?

A
320
Q

How did you collaborate with the services engineer to understand the potential of the Artus fan coil units for the project? What technical and financial considerations did you account for in your recommendation?

A
321
Q

How do you ensure that the sustainability criteria in projects, such as aiming for BREEAM Outstanding, are effectively balanced with the client’s budget?

A
322
Q

How do you communicate the long-term benefits of using more sustainable building technologies like Artus units to a client who may be more focused on short-term costs?

A
323
Q

How do you ensure that the sustainability criteria in projects, such as aiming for BREEAM Outstanding, are effectively balanced with the client’s budget?

A
324
Q

How do you communicate the long-term benefits of using more sustainable building technologies like Artus units to a client who may be more focused on short-term costs?

A
325
Q

How do you advise the client on selecting sustainable MEP systems when considering both cost and sustainability impacts?

A
326
Q

How do you handle client expectations when they inquire about ways to achieve higher BREEAM ratings while also keeping within a specific cost range?

A
327
Q

What challenges did you face when preparing the cost option appraisal for the Artus units, and how did you ensure that your advice aligned with the client’s objectives for sustainability and cost?

A
328
Q

What is your approach to advising clients on cost-effective solutions while maintaining project quality and sustainability goals?

A
329
Q

Can you provide an example where your understanding of construction technology and environmental services directly influenced the client’s decision-making process?

A
330
Q

How do you ensure that engineering solutions proposed by design teams align with the project’s financial goals while also considering operational efficiency and sustainability?

A
331
Q

How do you mitigate the risks of rising costs during the design stage, particularly with complex MEP systems like heating and cooling?

A
332
Q

How do you advise the client on potential cost-saving strategies without compromising the quality or functionality of the proposed systems?

A
333
Q

Can you give an example where you successfully managed a situation where the client’s original brief or budget had to be adjusted due to unforeseen technical complexities?

A
334
Q

How do you ensure that clients are fully informed of the technical and financial implications of MEP design changes, and what tools do you use to help them make informed decisions?

A
335
Q

Can you explain the key differences between traditional, design and build, and construction management procurement routes?

A
336
Q

How do time, cost, quality, and risk influence the selection of a procurement method for a project?

A
337
Q

What are the key factors that would make a client choose management contracting over other procurement methods?

A
338
Q

In what types of projects would design and build be the most appropriate procurement route, and why?

A
339
Q

How does the client’s priorities influence the choice between traditional and design and build procurement routes?

A
340
Q

What are the key considerations when advising a client on the most suitable procurement route for their project?

A
341
Q

Can you explain how client risk appetite might influence the selection of a procurement route?

A
342
Q

How does quality control differ in the traditional procurement route compared to the design and build route?

A
343
Q

Can you explain the differences between single-stage and two-stage tendering? In what circumstances would you recommend each?

A
344
Q

What are the advantages and disadvantages of negotiated tendering, and when might it be appropriate to use it?

A
345
Q

Can you describe a scenario where two-stage tendering might be more beneficial than single-stage tendering for a client?

A
346
Q

How does a negotiated tender differ from a competitive tender, and when would it be appropriate for a client to use this approach?

A
347
Q

What key documents are typically included in a tender pack, and why are they important?

A
348
Q

Can you explain the purpose of a preliminary qualification questionnaire (PQQ) and why it is used in the tendering process?

A
349
Q

What is the role of a tender report, and why is it important in the decision-making process?

A
350
Q

What key documents are typically included in a tender pack, and why are they important?

A
351
Q

What is the role of a tender report, and why is it important in the decision-making process?

A
352
Q

How do you ensure that the tender documents accurately reflect the project requirements and client’s objectives?

A
353
Q

What is the purpose of prequalification in the tendering process, and what factors are considered during prequalification?

A
354
Q

How do you assess a contractor’s suitability through the prequalification questionnaire (PQQ) process?

A
355
Q

Why is it important to conduct a prequalification process before issuing an invitation to tender?

A
356
Q

What are the risks of not carrying out prequalification before inviting contractors to tender?

A
357
Q

What criteria are typically evaluated during the prequalification stage to ensure the suitability of contractors?

A
358
Q

How do you balance the need for cost control with ensuring the contractor has the right experience and capabilities for the project?

A
359
Q

What are the advantages and disadvantages of using a two-stage tender compared to a single-stage tender?

A
360
Q

How does the client’s budget influence the selection of a procurement route and tendering strategy?

A
361
Q

How do the risks associated with the project influence the choice of procurement method?

A
362
Q

What risks are associated with the tendering process, and how can they be managed or mitigated?

A
363
Q

How do different tendering strategies (single-stage, two-stage, negotiated) impact the allocation of risk between the client and the contractor?

A
364
Q

Can you describe the prequalification questionnaire (PQQ) process you undertook for the soft strip works at 21-29 Glasshouse Street?

A
365
Q

What were the key factors you considered when preparing the PQQ document and what sections were included?

A
366
Q

How did you ensure the contractors selected for the PQQ had the appropriate experience and capability for the project?

A
367
Q

How did you assess contractor financial information to determine their suitability for the project?

A
368
Q

Can you explain how you used the scoring matrix to assess and compare the contractor responses?

A
369
Q

What criteria were used to create the contractor shortlist based on the PQQ scoring?

A
370
Q

How did you evaluate the capabilities of the contractors based on their PQQ submissions?

A
371
Q

What challenges did you encounter in the PQQ process, and how did you overcome them?

A
372
Q

How did you ensure transparency and fairness in the contractor selection process?

A
373
Q

Can you explain the steps you took to collate the PQQ responses and present them to the client team?

A
374
Q

How did you involve the client team in the decision-making process for selecting contractors during the PQQ stage?

A
375
Q

Can you explain the process you followed to normalise the MEP tenders for the 50 Berkeley Street project?

A
376
Q

How did you calculate costs for missed items in each of the tenders, and what method did you use to determine a fair cost?

A
377
Q

How did you manage the clarification process, and what documentation did you use to track contractor responses?

A
378
Q

What challenges did you face in the tender normalisation process, and how did you overcome them?

A
379
Q

Can you explain how you used your knowledge of procurement and tendering to advise the client during the contractor selection process for both projects?

A
380
Q

How did you ensure the selected contractors were able to meet the time, cost, quality, and risk expectations of the client?

A
381
Q

What lessons did you learn from conducting the PQQ process for 21-29 Glasshouse Street, and how will these influence your future procurement activities?

A
382
Q

How did your experience with normalising tenders at 50 Berkeley Street help refine your approach to tender analysis?

A
383
Q

Can you walk us through the tender recommendation report you prepared for the 21-29 Glasshouse Street project?

A
384
Q

How did you assess that Contractor A was the most suitable for the project based on their cost, programme, and sustainability proposals?

A
385
Q

Can you explain how you determined which contractor offered the highest percentage of cost certainty during the tender process for 21-29 Glasshouse Street?

A
386
Q

What were the key sustainability proposals that made Contractor A stand out, and how did these align with the client’s project objectives?

A
387
Q

How did the programme duration comparison, prepared by the project manager, factor into your recommendation for the most suitable contractor?

A
388
Q

Can you explain the process you followed to advise the client on the procurement strategy for Clifton Street?

A
389
Q

Why did you recommend a single-stage design and build procurement route for the project, and how did it align with the client’s key requirements?

A
390
Q

What specific project characteristics made a single-stage design and build more suitable than other procurement routes for Clifton Street?

A
391
Q

Can you explain the importance of cost control in both the pre-contract and post-contract stages of a project?

A
392
Q

What are the key differences between pre-contract and post-contract cost control?

A
393
Q

Why is it important for a QS to maintain a change log during the pre-contract stage, and how does it help manage cost control?

A
394
Q

What are the main components of a cost report, and why are they important to a client?

A
395
Q

Can you explain the purpose of provisional sums and how they are used in a cost report?

A
396
Q

How do post-contract changes and contingency adjustments affect the overall project cost?

A
397
Q

Why is it important to identify and track risk items in a cost report?

A
398
Q

What is the significance of cashflow forecasting in a cost report, and how does it help manage the project’s financial health?

A
399
Q

Can you explain the importance of a robust change control process on a project?

A
400
Q

How does accurate valuation of change help in managing project finances?

A
401
Q

What methods or principles have you learned to ensure that changes are valued correctly during a project?

A
402
Q

What are the typical valuation rules that you apply when valuing changes on a project?

A
403
Q

How do these rules ensure that the valuation of variations is fair and accurate for both the client and contractor?

A
404
Q

Can you explain the key principles outlined in the RICS Black Book on Cashflow Forecasting?

A
405
Q

Why is cashflow forecasting essential to a construction project, and how does it influence decision-making for both the client and contractor?

A
406
Q

How do you create a pre-contract cashflow forecast, and what factors do you consider?

A
407
Q

What indicators would suggest that a contractor is ahead or behind on cashflow during a project?

A
408
Q

What impact does a contractor being ahead or behind on cashflow have on the overall financial health of the project?

A
409
Q

How can a QS help a client monitor and manage cashflow throughout the project lifecycle?

A
410
Q

Can you explain the role of contingency in project finances and how it is managed in cost reports?

A
411
Q

How do you identify risk items in a project, and how are these factored into the financial management of a project?

A
412
Q

Why is it important for a QS to clearly communicate the financial progress of a project to the client through cost reports?

A
413
Q

How do cost reports help clients make informed decisions about the financial status of their projects?

A
414
Q

Can you explain how the pre-contract cost estimation process ties into the financial management of a project?

A
415
Q

What tools or methods have you used to ensure that the initial budget is maintained throughout the project?

A
416
Q

Can you describe how financial forecasting helps mitigate potential financial risks on a project?

A
417
Q

How do provisional sums and allowances in the cost report help the client understand the financial flexibility of the project?

A
418
Q

Can you explain how you used cost reporting to actively manage costs during the Berners Street project?

A
419
Q

How did you ensure that the cost report accurately reflected the project’s financial status post-contract?

A
420
Q

How do you balance provisional sums and track their expenditure on a project? Can you provide an example?

A
421
Q

Can you describe your approach to negotiating cost agreements for changes in the project scope?

A
422
Q

How do you ensure that these negotiated costs are fairly represented in the cost report?

A
423
Q

What methods did you use to communicate cost agreement changes to the client and contractor?

A
424
Q

How did attending post-contract meetings with the design team and contractor help you manage the project’s financial position?

A
425
Q

Can you explain the process of tracking cost changes and how this impacted the overall project budget?

A
426
Q

How did you update the cashflow position during post-contract meetings, and what factors influenced these updates?

A
427
Q

How did you use cost reports to project the anticipated final account for the Berners Street project?

A
428
Q

How did you ensure that the final account projection accounted for risk allowances?

A
429
Q

Can you explain the importance of balancing the anticipated final cost with the project’s risk allowance to the client?

A
430
Q

How did your cost reporting enable the client to make proactive decisions throughout the project?

A
431
Q

Can you describe an instance where your financial reporting led to a critical decision by the client?

A
432
Q

Can you explain how you prepared the cashflow forecast for MEP-based packages on the 50 Berkeley Street project?

A
433
Q

What key elements did you consider when preparing the cashflow forecast for different MEP systems (e.g., heating, cooling, ventilation)?

A
434
Q

How did you ensure that the forecast accurately reflected the phased nature of MEP installation on the project?

A
435
Q

How did you account for advanced payments for certain work packages, such as lifts, in your cashflow forecast?

A
436
Q

Why is it important to consider both advanced payments and retentions in a cashflow forecast, and how does it impact the client’s cash position?

A
437
Q

How do you ensure that clients receive timely updates regarding the financial health of the project?

A
438
Q

How do you incorporate risk management into your financial reporting and forecasting?

A
439
Q

Can you explain how you valued the change to the space heating and air conditioning system on the 20 Air Street project?

A
440
Q

Can you provide an example of how you adjusted a cashflow forecast or cost report to account for an identified risk?

A
441
Q

What specific JCT valuation rules did you apply in assessing the cost of replacing the FCUs?

A
442
Q

How did you decide which contract rates to use, and how did you adjust them to reflect the change?

A
443
Q

What steps did you take to ensure that your valuation of the change was accurate and fair to both the client and the contractor?

A
444
Q

Can you discuss the value engineering options you proposed to the client to offset the cost increase on the 20 Air Street project?

A
445
Q

How did you present the cost-benefit analysis of these options to the client, and what were the reasons they chose not to proceed with them?

A
446
Q

In what situations would you recommend accepting value engineering measures versus increasing the budget?

A
447
Q

How did you monitor the cashflow for the MEP package on the 36-38 Berkeley Square project?

A
448
Q

Can you explain how you valued the omission of the CAT-A MEP installation on the 36-38 Berkeley Square project, including the cost of abortive works?

A
449
Q

What considerations did you take into account when advising the client about the financial impact of omitting works that were partially completed?

A
450
Q

How did you ensure that the valuation of the omission was fair and transparent to the client and contractor?

A
451
Q

How did you use the CSA and Subcontractor’s schedule of rates to value the cost of the CAT-A MEP omission?

A
452
Q

What advice did you give the client on the outturn cost based on these rates, and how did you manage their expectations?

A
453
Q

Can you explain how you advised the client on the need to increase the budget for the 20 Air Street project after the FCU replacement?

A
454
Q

What was your approach to managing the client’s expectations when value engineering options were not taken?

A
455
Q

Can you describe how you factored in financial risk allowances when advising the client on budget adjustments?

A
456
Q

How do you assess whether a project change is financially viable for the client?

A
457
Q

What steps do you take to ensure the client understands the long-term financial impact of accepting or rejecting a project change?

A
458
Q

How do you present complex financial data, such as the implications of project changes or cash flow adjustments, in a way that is easily understandable to your client?

A
459
Q

How do you advise a client when there is a conflict between their design aspirations and the financial constraints of the project?

A
460
Q

Have you ever had a situation where the client disagreed with your financial advice? How did you handle the situation, and what was the outcome?

A
461
Q

How do you approach negotiating with contractors or subcontractors on financial disputes or disagreements regarding valuations?

A
462
Q

What is the purpose of the New Rules of Measurement (NRM), and why is it important in the quantification process?

A
463
Q

Can you explain the different NRM sections and how they apply to various stages of a construction project?

A
464
Q

How do you ensure consistency and accuracy when using NRM in quantification?

A
465
Q

What are the key principles of quantifying elements like concrete and steel frames under the NRM?

A
466
Q

Why is accuracy critical in both the pre-contract and post-contract phases of construction?

A
467
Q

Can you explain the consequences of inaccurate measurements in a construction project and how this can impact cost control?

A
468
Q

Can you explain the differences between International Property Measurement Standards (IPMS) and the RICS Code of Measuring Practice?

A
469
Q

What are the reasons for the introduction of the IPMS, and how does it change the way areas are measured compared to the previous system?

A
470
Q

How do the classification and measuring principles differ between the two systems?

A
471
Q

Can you define Gross Internal Area (GIA) and Net Internal Area (NIA), and explain their significance in building measurement?

A
472
Q

How do these areas differ from each other, and in what contexts are they most commonly used?

A
473
Q

How do you use CAD software to accurately measure areas within a building?

A
474
Q

What are the advantages of using CAD tools for quantification and costing purposes?

A
475
Q

Can you describe a situation where the use of CAD helped improve your accuracy in quantification?

A
476
Q

Besides CAD software, what other tools or techniques do you use to ensure accurate measurements during the quantification process?

A
477
Q

How do you verify the accuracy of your measurements before submitting them in cost plans or tenders?

A
478
Q

Why is it important to use up-to-date cost data when preparing cost estimates or pricing works pre-contract?

A
479
Q

How do you ensure that the cost data you use is current and relevant to the project at hand?

A
480
Q

What sources do you rely on for obtaining accurate and reliable cost data?

A
481
Q

What are the different forms of cost data used in quantification and costing, and in which situations would you use each type?

A
482
Q

Can you give examples of how different cost data sources are applied to different construction elements or stages?

A
483
Q

How do the processes of quantification and costing differ between the pre-contract and post-contract phases of a project?

A
484
Q

What are the key challenges in quantification during the post-contract phase, particularly in relation to variations and changes?

A
485
Q

How do you apply the variation rules during the post-contract phase to ensure accurate valuation of changes?

A
486
Q

Can you explain the importance of correctly quantifying and costing variations in a construction contract?

A
487
Q

How do you reconcile quantities and costs when comparing pre-tender estimates with contractor tender returns?

A
488
Q

What is your approach to ensuring that any discrepancies in quantities are identified and resolved?

A
489
Q

What are the key cost drivers you consider when quantifying and costing a construction project?

A
490
Q

How do you ensure that your cost estimates reflect the actual conditions and requirements of the project?

A
491
Q

Can you provide an example where you applied the RICS Code of Measuring Practice in a live project, and how did it ensure accurate quantification?

A
492
Q

How do you balance the need for adherence to measurement standards with the practicalities of a live construction site?

A
493
Q

How do you maintain quality control when preparing quantities and pricing for a construction project?

A
494
Q

What checks do you perform to ensure that your quantifications are accurate and free from errors?

A
495
Q

Can you explain the differences in the quantification process at various RIBA Plan of Works Stages (e.g., Stage 1 vs Stage 4)?

A
496
Q

How do you ensure that your quantification at early design stages (e.g., RIBA Stage 1 or 2) is accurate enough to inform cost planning?

A
497
Q

What challenges do you encounter when quantifying construction works at later design stages (e.g., Stage 3 or 4), and how do you address them?

A
498
Q

How do you approach the quantification of MEP systems in a complex refurbishment project like 50 Berkeley Street?

A
499
Q

What factors do you consider when quantifying MEP works, and how do you ensure accuracy in your measurements?

A
500
Q

How do you ensure alignment between your area schedules and the architectural design during the quantification process?

A
501
Q

How did you prepare the pricing schedule for the tender pack at 50 Berkeley Street?

A
502
Q

What key items did you include in the pricing schedule, and how did you ensure it was clear and comprehensive for contractors to price?

A
503
Q

How did you use the pricing schedule and contractor returns to form part of the contract sum analysis at 50 Berkeley Street?

A
504
Q

What approach do you take when analyzing tender returns to ensure the contract sum reflects the full scope of works?

A
505
Q

How do you ensure that tender documents and pricing schedules are clear enough to avoid discrepancies between contractor bids?

A
506
Q

How do you address any gaps or missing items identified in the contractor returns?

A
507
Q

Can you explain how you approached costing the post-contract change at Arding & Hobbs related to the terrace and 5th-floor redesign?

A
508
Q

When there are no tendered rates available, what methodology do you use to ensure the new rates are fair and accurate?

A
509
Q

How do you apply the valuation rules when assessing post-contract changes to ensure the client is not overpaying or underpaying?

A
510
Q

Can you describe a situation where you had to use quotations and adjust contract rates to cost a variation, and what steps you took to ensure accuracy?

A
511
Q

How do you approach measuring elements like MEP systems and structural elements where detailed design information is not always available?

A
512
Q

How do you handle quantification when there is limited or incomplete design information, such as at RIBA Stage 1 or 2?

A
513
Q

How do you ensure your measurements are still relevant and useful for cost estimation despite information gaps?

A
514
Q

Can you explain the process of producing area schedules for a project like Vine Hill, and how you ensured they were accurate?

A
515
Q

How do you account for differences in measurement definitions (e.g., GIA, NIA, IPMS) when producing area schedules?

A
516
Q

How do you use quotations and adjusted contract rates to form an accurate assessment of the cost of works in a post-contract change?

A
517
Q

How do you ensure that cost control is maintained during the post-contract phase, especially when handling change management?

A
517
Q

How do you ensure that the rates you use in post-contract changes reflect market conditions and the contractor’s obligations?

A
518
Q

What techniques do you use to minimize cost risks when pricing works for both pre-contract and post-contract stages?

A
519
Q

How did you advise the client on the post-contract change resulting from the damaged ductwork at 20 Air Street?

A
520
Q

What factors did you consider when advising the client on the cost impact of replacing ductwork, grilles, dampers, and insulation?

A
521
Q

How do you ensure that post-contract changes are priced fairly and in accordance with contract terms?

A
522
Q

Can you explain how you used adjusted contract rates to advise the client on the post-contract change?

A
523
Q

How do you determine if the adjusted rates are reasonable, and what steps do you take if there are discrepancies in the pricing?

A
524
Q

How do you advise clients on changes that arise from unforeseen conditions (e.g., damaged ductwork) during a project?

A
525
Q

What strategies do you use to manage client expectations and minimize the impact of unexpected changes on the project budget?

A
526
Q

How did you manage the contractual implications of the post-contract change at 20 Air Street in terms of time and cost?

A
527
Q

What advice did you give the client to ensure the change was properly recorded and managed under the contract?

A
528
Q

How did you advise the client on the impact of changing the reception lighting and furniture design midway through the tender at 50 Stratton Street?

A
529
Q

What are the key risks involved in making changes during a live tender, and how did you communicate these to the client?

A
530
Q

Why did you advise the client to issue a tender addendum for the change in reception design?

A
531
Q

How do you ensure that all contractors are fully informed about scope changes during the tender period, and what steps do you take to avoid any miscommunication?

A
532
Q

What advice did you give regarding the likely extension of the tender period due to the client’s changes, and how did you assess the impact on the overall project timeline?

A
533
Q

How do you balance the need for design changes with the requirement to maintain the project programme?

A
534
Q

Can you describe a situation where a client requested a change that had significant cost implications, and how you handled that conversation?

A
535
Q

Did you propose any value management or cost-saving alternatives for the changes at 20 Air Street or 50 Stratton Street?

A
536
Q

How do you incorporate risk allowances and contingencies into your cost advice when dealing with unforeseen changes on-site?

A
537
Q

How do you advise clients on balancing risk and cost control while managing project variations?

A
538
Q

In what situations would you recommend extending a tender period, and how do you assess the potential impact on the project delivery?

A
539
Q

How do you handle contractor queries that arise from tender addendums or post-contract changes?

A
540
Q

What advice do you provide to clients when contractors request clarifications or adjustments to their bids due to mid-tender changes?

A
541
Q

How do you ensure that contractors have fully accounted for scope changes, such as the reception design changes at 50 Stratton Street, in their tender returns?

A
542
Q

What steps do you take to ensure that all tender returns are fairly evaluated in light of the changes requested by the client?

A
543
Q

Can you explain what is meant by risk in the context of a construction project?

A
544
Q

How does risk affect the overall management of a construction project?

A
545
Q

What are the different categories of risk as outlined in NRM 1?

A
546
Q

Can you provide examples of risks that might fall under each category (e.g., financial, environmental, design risks)?

A
547
Q

Why is it important to have a risk management process in place for construction projects?

A
548
Q

How can effective risk management help mitigate unexpected costs and other project issues?

A
549
Q

Can you outline the key steps in a risk management process?

A
550
Q

What is the significance of identifying, assessing, and mitigating risks?

A
551
Q

What role does a Quantity Surveyor play in managing risks on a project?

A
552
Q

How does a QS contribute to minimizing risks related to cost, time, and quality?

A
553
Q

How are risks typically allocated between the Client and the Contractor?

A
554
Q

Can you give examples of risks that are usually allocated to the client versus those allocated to the contractor?

A
555
Q

What is a risk register, and why is it important in managing construction risks?

A
556
Q

How does a risk register help in identifying and tracking risks throughout the project lifecycle?

A
557
Q

What are the key components of a risk register?

A
558
Q

Can you explain how risks are categorized, assessed, and monitored within a risk register?

A
559
Q

How does NRM 1 address the management and allocation of risks in construction projects?

A
560
Q

How does the use of NRM 1 assist in ensuring that risks are quantified and properly accounted for in cost plans?

A
561
Q

How does understanding NRM 1 help in mitigating risks at various stages of a construction project?

A
562
Q

How is risk communicated to the project’s key stakeholders such as the client, contractor, and design team?

A
563
Q

Can you provide an example of how a risk identified through NRM 1 might be mitigated by a QS?

A
564
Q

Why is collaboration between the project team important when managing risks?

A
565
Q

How can the design team and contractor help mitigate specific risks identified by the QS?

A
566
Q

Can you explain the process you followed to identify the risk related to the dummy chilled ceiling panels on the 20 Giltspur Street project?

A
567
Q

How do you ensure that all risks are identified as early as possible in a project?

A
568
Q

How did you assess the financial implications of the risks you identified, particularly the dummy chilled ceiling panels at 20 Giltspur Street?

A
569
Q

How do you determine the probability and impact of a risk on the project?

A
570
Q

How do you approach costing when dealing with unknowns or incomplete designs during the early stages of a project?

A
571
Q

How did you evaluate and rate the access risks for the Clifton Street refurbishment?

A
572
Q

What criteria do you use to rate risks based on their probability and impact?

A
573
Q

What strategies do you use to ensure clients understand the severity and implications of potential risks?

A
574
Q

How did you communicate the material specification risk to the client on the 20 Giltspur Street project?

A
575
Q

Can you provide an example of how formal risk workshops helped mitigate a potential risk?

A
576
Q

How did you propose or implement risk mitigation measures for the risks identified on the Clifton Street project?

A
577
Q

Can you explain the process you followed to quantify the financial impact of the major risks on the Clifton Street project?

A
578
Q

Can you provide an example of how your risk report influenced client decision-making on either the Clifton Street or 20 Giltspur Street projects?

A
579
Q

How do you apply lessons learned from past projects to improve future risk management practices?

A
580
Q

How do you ensure that the financial impact of risks is incorporated into cost plans and contingencies?

A
581
Q

What were the key factors you considered when proposing the rainwater harvesting and hybrid VRF systems?

A
582
Q

How did you approach the costing of these systems to ensure they were achievable within the project budget?

A
583
Q

Can you explain how roof space limitations and planning implications impacted your recommendation for the PV panels?

A
584
Q

What alternative solutions did you propose to the client when the photovoltaic panels were ruled out?

A
585
Q

How did you calculate the W/m² for each lighting option, and how did this affect the client’s decision-making process?

A
586
Q

How do you assess the energy efficiency of various lighting systems and balance this with cost considerations?

A
587
Q

How do you ensure that proposed systems align with the BREEAM criteria for achieving higher ratings?

A
588
Q

Can you explain how budget constraints can influence achieving sustainability goals on a project?

A
589
Q

How does the W/m² metric impact the overall energy efficiency of a building?

A
590
Q

What other metrics or benchmarks do you use to evaluate the sustainability of building systems?

A
591
Q

How did you communicate the long-term benefits of the sustainable systems, such as rainwater harvesting and hybrid VRF, to the client?

A
592
Q

How do you ensure that clients understand the energy efficiency and lifecycle costs of the systems you’re recommending?

A
593
Q

What factors did you consider regarding the building layout when proposing the rainwater harvesting and hybrid VRF systems?

A
594
Q

How do you ensure that proposed sustainable systems are fully integrated into the design and construction process?

A
595
Q

How do you work with design teams to ensure that energy efficiency and sustainability are considered at all stages of the project?

A
596
Q

How do you identify and assess potential sustainability risks during the design and cost planning process?

A
597
Q

What factors do you consider when making trade-offs between sustainability features and staying within the project budget?

A
598
Q

How do you demonstrate the value of sustainability to clients, even when there are initial cost premiums?

A
599
Q

How do planning regulations influence your ability to propose sustainable systems on a project?

A
600
Q

What steps can be taken to address planning challenges when proposing sustainability measures like photovoltaic panels?

A
601
Q

How do you stay up-to-date with the latest sustainability standards and technologies?

A
602
Q

Can you provide an example of how a past experience has influenced your approach to sustainability on a recent project?

A