Quantification and Costing (Level 3) Flashcards

1
Q

What is NRM?

A

New Rules of Measurement (1,2 and 3) provides a standard set of measurement rules and essential guidance for the cost management of construction projects and maintenance works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three NRM?

A

1 = Order of cost estimating and cost planning for capital building works.

2 = Detailed measurement for building works.

3 = Order of cost estimating and cost planning for building maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When were the new issues effective from?

A

The were effective from 1 December 2021

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the RICS code of measuring practice?

A

The RICS code of measuring practice was produced to provide precise definitions of how to measure buildings. This includes GEA, GIA, NIA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is IPMS?

A

International Property Measurement Standard (IPMS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why was IPMS introduced?

A

To establish a consistent methodology for measuring buildings around the world.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key differences between IPMS and RICS code of measuring practice?

A

COMP was the previous measurement standard which regulated primarily RICS member nations, whereas the IPMS is now a global measurement standard.

Some key differences in the methods of measurement is that COMP used NIA whereas IPMS uses NLA (net lettable area) - a key difference in this is that areas such as external balconies are included within NLA whereas would not be included in NIA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is BIM?

A

Building Information Modelling - the process of creating and managing digital information about a built asset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the RIBA plan of works?

A

Stages 0-7:

0 = Strategic Definition
1 = Prep and Brief
2 = Concept Design
3 = Developed Design
4 = Technical Design
5 = Construction
6 = Handover
7 = In use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What level of design is required for cost plans?

A

Stage 3 - NBS outline spec
Stage 4 - NBS detailed spec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you provide cost information at various stages?

A

Stage 1-2 Cost Model
Stage 3-4 Cost Plan
Stage 5 Final Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is GEA?

A

Gross External Area is the area of a building measured externally at each floor level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is GIA?

A

Gross Internal Area is the area of a building measured to the internal face of the perimeter walls at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is NIA?

A

Net Internal Area of a building is the usable area measured to the internal finish of the perimeter or party walls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the sources of cost data?

A

Primary, Secondary, First Principles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Primary cost data?

A

Primary cost data is provided by yourself. This would be from market testing and project rates you have previously used. Accurate.

16
Q

What is Secondary cost data?

A

Secondary cost data is data from other sources such as price books or rates from other projects you have not previously worked on. (SPONS)

17
Q

What are first principles sorces of cost data?

A

First principles sources of cost are rates that you build up yourself from the key components.

18
Q

What is an example of first principles source of cost?

A

Ductwork - galv duct, insulation, brackets, bends, dampers, grilles, Sundries & Prelims

19
Q

What are schedules of works?

A

Schedule of works are ‘without quantities’ lists often produced for small projects and alteration work.

20
Q

What are schedules of rates?

A

A quantified list included as part of the contract sum splitting out all the individual items of work e.g. staff, materials

21
Q

How do you carry out valuations?

A

Receive Application, Visit Site and assess the works progression, Negotiate Value of works complete, Issue reccommendation

22
Q

What is an addendum?

A

An addendum is a document that you use to add terms or make changes to an executed contract without invalidating the original.

23
Q

What information is required to measure preliminaries?

A
  • Contract duration.
  • Location.
  • Type of project (New Build vs. Refurb).
  • The size of the project.
  • Temporary works.
  • Security.
  • Methodology.
  • Programme.
  • Services.
  • Employers accommodation.
  • Contractor designed work.
  • Sectional completion.
  • Insurances / Bonds.
24
Q

If it was found that a Bill rate was blatantly wrong for example £100
was included as a rate instead of £1, how would this be resolved?

A
  • The works would be valued in accordance with the agreed rate contained within the contract.
  • If identified within the tender documents prior to the contract being agreed then the rate could be
    amended in accordance with the Tendering rules in place, but otherwise both parties would have to
    stand by the rate.
25
Q

What would you include within the BoQ where works are to be carried
out by Nominated Subcontractor?

A
  • A prime cost sum would be incorporated including:
  • An allowance for the cost of the Nominated Subcontractors work (based on the quotation).
  • An allowance for the contractor to price for attendances such as accommodation, welfare,
    storage, handling, materials & cleaning.
  • An allowance for a percentage addition for any other charges & profit.
26
Q

What is Simpsons Rule?

A

Simpsons is a mathematical formula for approximating the area under a curve over a given interval.

27
Q

How would your approach to measurement change if you worked in Dubai?

A

I would need to measure in accordance with the method of measurement appropriate for that country.

28
Q

How do you measure something unique for example a statute of the
client?

A
  • If it could be broken down easily into the parts that are in accordance with the method of measurement, I would use this as the basis for measurement.
  • Otherwise I would have to insert an item with a detailed description of the works with a section to include a Provisional Sum.
29
Q

How do you deal with ground water under NRM2?

A
  • Ground water is measured under Section 5 for Excavating and Filling.
  • It is measured on an itemised basis with the original below ground level being stated and reference to whether the water is polluted.
  • If the post contract water level differs from the pre-contract level the measurements must be taken and revised accordingly.
  • The method and place of discharge is left to the discretion of the contractor unless stated otherwise.
30
Q

What is a Preamble?

A
  • A preamble is an explanation of a document that is commonly found in contracts, specifications and bills of quantities.
  • It can help with the interpretation of the document.
  • It includes a description of the parties to the contract.
  • The background to the document.
  • Measurement procedures that have been adopted.
31
Q

What are method related charges?

A
  • A method related charge is a one-off item related to the method of carrying out the work and does not form part of the permanent works.
  • They are not considered proportional to the item of works to be carried out.
  • For example provision of temporary propping required for a weakened elevation of an existing building.
32
Q

What are time related charges?

A

Time related charges are method related charges that are considered proportional to time taken to carry
out the works for example plant hire.

33
Q

What are fixed charges?

A

Fixed charges are method related charges that do not vary with time for example Service Connection Charges.