Contract Practice (Level 3) Flashcards
What are some of the key differences between JCT and NEC contracts?
PALM
Programme - included in NEC
Admin - compensation events
Language - JCT legal jargon
Money - JCT includes provisional sums
What is a relevant event?
An event that grants the contractor an extension of time.
What is a relevant matter?
A relevant matter is a matter for which the client is responsible that materially effects the progress of the works. This enables the contractor to claim direct loss and / or expense that has been incurred.
What is an example of a relevant event?
Delayed possession, Employers instructions, adverse weather
What is an example of a relevant matter?
Client instructed change, discovery of fossils/ antiques, civil disruption.
What is the payment timeline under JCT DB 2016?
Total payment cycle is 21 days: 7 days valuation, 14 days payment, 5 days payment cert, 5 days before end pay less notice
Can you name a contractual mechanism in the JCT D&B contract?
Practical completion certificate, DOP, Interim Valuations
What is a Contract administrator?
The contract administrator is used on traditional contracts but purely administers the contract.
What is an Employers Agent?
D&B - The EA is hired to be the agent of the Employer and represent their interests. The EA is effectively stepping into the shoes of the client and will have authority to take decisions which are assigned to the Employer under the contract.
What are liquidated damages?
A genuine pre estimate of loss the client will incur if the completion date is missed by the contractor written into the contract and agreed by both parties on a weekly rate.
What are unliquidated damages?
Unliquidated damages are damages that are payable for a breach, the exact amount of which has not been pre-agreed. The sum to be paid as compensation is said to be ‘at large’ and is determined after the breach occurs by a court.
What is an example of a contract ammendement?
Adjusting the valuation period from 14 to 28 days.
Defects Liability period 6 to 12 months.
Design responsibility shared with contractor.
Third Party Provisions
ER’s take presidence
What are the requirements for vesting?
Information about the two parties, Project Address and Material storage address, Insurance certificate against loss or damage, Schedule of quantity applied, cost of materials
What is novation?
Novation is a process by which contractual rights and obligations are transferred from one party to another. Common on D&B.
What is assignment?
A legal assignment is transferring an interest from one party, called the assignor, to another, the assignee. An assignment entitles the assignee to the performance of a particular contractual obligation conferring a benefit.
What are collateral warranties?
Collateral warranties are agreements which are associated with another ‘primary’ contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.
What is a bond?
A contract bond is used to guarantee that the terms of a contract are fulfilled.
If the contracted party fails to fulfill its duties according to the agreed upon terms, the contract “owner” can claim against the bond to recover financial losses or a stated default provision.
What is a performance bond?
A performance bond is designed to ensure that the contractor performs the works in accordance with the building contract.
What is an advance payment bond?
A contractor may request an advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins.
What are the types of all risk insurance?
Option A, B, C.
A - Contractors all risk
B - Client all risk
C - Joint names (renovations)
What is loss and expense?
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible.
Relevent Matters
Positives of standard form contract?
It saves time
It minimizes transaction cost
It allocates risk in a fair and recognisable way
Industry wide input