Simon Questions Flashcards

1
Q

What was the scope of the PCSA?

A
  • Agree and finalise the methodology
  • Achieve sign-off from the relevant stakeholders
  • Engage the supply chain for a stick/unitised system
  • Agree the contract sum and contract terms
  • Develop scaffold designs and submit to CWG
  • Develop Stage 3 ERs to CPs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why use a PCSA over letter of intent?

A

A letter of intent is typically used when contract terms are being finalised, the design is complete and a start on site is required. A PCSA is more contractually robust, and is intended for when design work is to take place pre-contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was the strategy for using a two-stage tender.

A
  • Design and construction to overlap
  • Early contractor input
  • Attractiveness to market and therefore competitiveness.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If the contractor proposed ‘brokk’ to be used, was it not qualified that it was a contractor risk in terms of any delays associated given there is an occupied building in close proximity?

A

No, noise levels not understood pre-tender, so ERs changed during PCSA as client request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If you cancelled the project, what would be the risk to the client.

A

Financial settlement and risk of no control over demolition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An option was to explore alternative construction methods - as the PM why wasn’t this done from the outset to avoid the delay?

A

As part of the procurement strategy, it was always the intention to utilise the contractor’s experience during the PCSA period through the 2 stage D&B route. I also ensured that the internal hoarding had acoustic properties as part of this due diligence piece. However, this level of noise disruption was unforeseen, but I feel it was managed appropriately with the change in methodology.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Did you not have any statutory obligations with the planning consent in terms of noisy works
* Why weren’t these followed?

A

Our readings were within the statutory tolerances. The issue was with the vibration through the steel frame.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You mention that within the contract, 7 standdown days were agreed. Where was this agreed in the contract?

A

The schedule of amendments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Was a planning consent required?

A

Yes - dealt with by planning consultant. Essentially obligation to match existing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why didn’t you qualify that if the broc system didn’t work that it’s the contractor risk?

A

The level of disruption was not anticipated. However, through our due diligence and engagement with the contractor in the PCSA period, we addressed this and implemented a solution before starting on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is cancelling the project really an option?

A

No, but important to give my client the full picture and present all options before advising on the most suitable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why was it your responsibility for an alternative option. Its a D&B?

A

This was the PCSA period and contract not signed and contract sum not agreed, therefore a change in the employer’s requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you explain how you would draft a programme if starting on site was a key driver for your client

A

Understand key milestones and critical path activities for starting on site. For example, lease start dates, planning (6 weeks for demo under Building Act 1984), LTA processes and timescales, scope for early validations, stakeholder approvals (access passes etc). Then validate these with the necessary stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the critical path.

A

The shortest path of interlinked activities from the start to finish of the project. Any delay to any of these activities would cause a delay to the overall project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If an activity is delayed, but not on the critical path would this impact the completion date?

A

Depends on the amount of free float on the task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is float?

A

Free float is the amount of time a single activity can be delayed without impacting PC, and total float is the amount of time the whole project can be delayed without impacting PC.

17
Q

What is the difference between CAT A and CAT B fitout?

A

Cat A fit out is a basic operational fit out that provides you with a finished, empty space that is ready for you to move into.

Cat B fit out is the process of bringing all the office design elements together to create a functional workplace complete with planting, flooring and furniture.

18
Q

Can you provide me with a sustainable technology you are aware of and how it works.

A

Integration of M&E with BMS. Simple items such as lighting, or more complex with IBS and heating. Sustainable and cost effective.

19
Q

Can you explain how you establish your clients brief.

A
  • Understand key dates
  • Understand budget
  • Understand aesthetic aspirations
  • Functional requirements
  • Key success criteria - sustainability etc
20
Q

If your client changes the brief midway through a project, how would you proceed?

A

The change control procedure.

21
Q

What’s the difference between a feasibility study and a development appraisal?

A

A feasibility study looks at the performance of a project, functional requirements, risks and assumptions, and seeks to determine if the proposed works are feasible and achievable.

A development appraisal seeks to determine the value of land for a developer, and determine if a purchase would be profitable.

22
Q

How do you identify stakeholders on a scheme?

A

Within the stakeholder management plan, I would undertake a stakeholder mapping exercise. List all internal and external stakeholders and prioritise them by their level of influence.

23
Q

If a stakeholder had a high level of influence on your project, how would you deal with them?

A

Regular communciation, take them on site visits, copy them in on reports, provide further information as required, understand their specific needs and ensure they are met.

24
Q

What was the key driver for a two stage tender?

A

design and construction can overlap.

25
Q

When would a single stage tender be best to use.

A

When early contractor involvement is not required, there is less time pressure for a quick start on site, and when the design is complete prior to going out to tender. Possibly for less complex projects.

26
Q

How would you deal with errors in tender returns.

A

Alternative A and B as detailed in the JCT Tendering Note 2017. Alternative A is the price is not amended, and Alternative B is that the price is amended to account for the error.

27
Q

What does the procurement mean.

A

Procurement is the overarching process of obtaining goods and services. Tendering is a specific phase within the procurement period.