Programming and Planning Flashcards
1
Q
How would you develop the tender programme?
A
- Client requirements and key dates
- Experience from similar projects
- Pressure tested by the market
- Structure by RIBA Stages
2
Q
What is the purpose of a programme?
A
- Ensure effective sequencing of the works
- Administrative tool for monitoring progress of the works
- Legally binding if listed as a contract documents
- Assessing extensions of time
- Assisting with resolution of disputes
- Determines cash flow and resources
3
Q
What are key considerations when developing a programme?
A
- Understand client/project objectives
- Constraints
- Estimated durations for tasks
- Sequence
- Resources required
- The market and lead times
- Avoiding long durations on a single task
4
Q
What are the elements of a programme review?
A
- Assess compliance with the scope and tender documents
- Review progress against baseline
- Client reporting
- Assess programme stability
- Assess time risk allowance
- Assess float
- Ensure cost and resource are aligned
- Account for holidays (Christmas etc - other jurisdictions)
5
Q
What is time risk allowance?
A
- Time allocated for likely delays such as crane downtime, adverse weather, plant repairs etc
6
Q
What are SMART principles?
A
- Specific
- Measurable
- Agreed
- Realistic
- Time
7
Q
What is float?
A
- The amount of time a task can be delayed without impacting subsequent tasks or the project’s overall completion.
8
Q
What is free float?
A
- The amount of time a task can be delayed without impacting a subsequent task.
9
Q
What is total float?
A
- The amount of time that a task can be delayed without impacting the overall project completion date.
10
Q
What is terminal float?
A
- The difference between the planned completion date and the contract completion date
- Typically 10% of the overall project duration
11
Q
What is a programme baseline?
A
- The starting point of the programme. Once established, it is used to measure progress and performance.
12
Q
What is the critical path?
A
- The sequence of activities determining the minimum time needed for project completion. Any delay to an activity on the critical path will result in a delay to the completion date of the overall project. It is the long string of interrelated tasks.
13
Q
What are the benefits of critical path analysis?
A
- Prioritising tasks
- Anticipate and avoid bottlenecks
- Identify float
14
Q
What are bottlenecks?
A
- A stage in a project where a task limits or completely prevents progress with subsequent tasks
15
Q
What is a forward pass?
A
- Activities start at the earliest possible point to achieve the planned completion date