Programming and Planning Flashcards

1
Q

How would you develop the tender programme?

A
  • Client requirements and key dates
  • Experience from similar projects
  • Pressure tested by the market
  • Structure by RIBA Stages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of a programme?

A
  • Ensure effective sequencing of the works
  • Administrative tool for monitoring progress of the works
  • Legally binding if listed as a contract documents
  • Assessing extensions of time
  • Assisting with resolution of disputes
  • Determines cash flow and resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are key considerations when developing a programme?

A
  • Understand client/project objectives
  • Constraints
  • Estimated durations for tasks
  • Sequence
  • Resources required
  • The market and lead times
  • Avoiding long durations on a single task
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the elements of a programme review?

A
  • Assess compliance with the scope and tender documents
  • Review progress against baseline
  • Client reporting
  • Assess programme stability
  • Assess time risk allowance
  • Assess float
  • Ensure cost and resource are aligned
  • Account for holidays (Christmas etc - other jurisdictions)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is time risk allowance?

A
  • Time allocated for likely delays such as crane downtime, adverse weather, plant repairs etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are SMART principles?

A
  • Specific
  • Measurable
  • Agreed
  • Realistic
  • Time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is float?

A
  • The amount of time a task can be delayed without impacting subsequent tasks or the project’s overall completion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is free float?

A
  • The amount of time a task can be delayed without impacting a subsequent task.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is total float?

A
  • The amount of time that a task can be delayed without impacting the overall project completion date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is terminal float?

A
  • The difference between the planned completion date and the contract completion date
  • Typically 10% of the overall project duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a programme baseline?

A
  • The starting point of the programme. Once established, it is used to measure progress and performance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the critical path?

A
  • The sequence of activities determining the minimum time needed for project completion. Any delay to an activity on the critical path will result in a delay to the completion date of the overall project. It is the long string of interrelated tasks.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the benefits of critical path analysis?

A
  • Prioritising tasks
  • Anticipate and avoid bottlenecks
  • Identify float
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are bottlenecks?

A
  • A stage in a project where a task limits or completely prevents progress with subsequent tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a forward pass?

A
  • Activities start at the earliest possible point to achieve the planned completion date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a backward pass?

A
  • Activities start at the latest possible date to achieve the planned completion date
17
Q

What is acceleration?

A
  • refers to increasing the originally planned or current rate of progress of the works so as to complete the project earlier than would otherwise be the case.
  • If the Employer wishes to investigate the possibility of achieving practical completion before the Completion Date, the Contract Administrator shall invite proposals from the Contractor in that regard
  • If a contractor receives an invitation to make proposals, it must either provide an ‘Acceleration Quotation’ or explain why it would be impracticable to achieve an early completion of the works
  • The ‘Acceleration Quotation’ must identify the amount of time that can be saved and the amount of the adjustment to the ‘Contract Sum’ that the contractor would require. The quotation must include direct costs, consequential loss and expense and an allowance for the cost of preparing the quotation.
18
Q

What are ways which acceleration could applied to your projects?

A
  • Increased labour
  • Extended working hours
  • Increased plant and machinery – e.g mobile cranes
  • Revised design for buildability
  • New materials with shorter lead times
19
Q

What are the drawbacks of acceleration?

A
  • Law of diminishing returns
  • Reduced quality
  • Increased costs
  • Possible deviations from the clients aspirations
20
Q

What is a programme dropline?

A

The most recognised method of progress reporting. This is a line drawn down the programme on a chosen report date indicating tasks that either are ahead or behind schedule.

21
Q

What is a concurrent delay?

A

Concurrent delay is used to denote a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal effect. However, if the programme is managed properly, this is very unlikely.

22
Q

What is project crashing?

A

Project crashing is compressing your project’s schedule to finish it earlier than your initial target.

23
Q

What is a programme hammock?

A

takes two or more tasks in a programme and shows the actual start of the earliest and the actual completion of the latest. The hammock bar will move as the actual programme tasks move.

24
Q

What is the difference between programming and planning?

A

A programme refers to a defined sequence of tasks and timescales that are required to complete a project. Planning refers to reviewing and organising the wider tasks required to deliver a project, such as teams, resources and wider objectives. This would be captured in a PEP for example.

25
Q

Name some programming software and when you would use them.

A

MS Project, Asta, Primeavera. I am only familiar with MS Project, but it is a well known format that is compatible with most members of the professional team.

26
Q

What is a work breakdown structure (WBS)?

A

A hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work.

27
Q

What is programme lead?

A

A successor activity starts before a predecessor activity finishes - e.g. loading out all brickwork on scaffold ahead of programme

28
Q

What is programme lag?

A

A required delay in the start of a predecessor activity - e.g. plaster drying before a mist coat, and subsequent coats of paint drying before a next or final coat.

29
Q

Is the programme a contract document under JCT?

A

No, although it is often appended to the contract. Therefore the client cannot penalise the contractor missing line item dates on the programme, unless each was an individual section completion (which wouldn’t happen in practice). The contractor is response for the programme activities, but must achieve the defined Sectional and Practical Completion dates. The programme IS a contract document under NEC.

30
Q

Who owns float under JCT?

A

The Contractor. Under NEC, float can be owned by different parties.

31
Q

What is a base date on a programme?

A

Under JCT, this is the allocation of risk for statutory changes. The base date is usually the date of the tender submission.

32
Q

What metrics would you use to review a programme at tender?

A
  • Experience from similar projects -
  • Benchmark data within Arcadis to validate
  • Look at lead times and ask for confirmation of orders
33
Q

What is a concurrent delay?

A

the situation on a project which is suffering delay in which two or more independent events have occurred which, if either had occurred on their own, would have caused delay to the project.

34
Q

What is time at large?

A

Time at large usually means that there is no enforceable date for completion, and the contractor then only has an implied obligation to complete the works within a ‘reasonable time’.

35
Q

What is cash flow important within programme?

A
  • understanding expenditure vs budget from both a client and contractor perspective. Essentially, ensuring both parties can remain in business.