Pre-Qual Questions Flashcards
Why did they use a bespoke change control procedure?
The JCT makes provision for instructions, but does not provide a specific procedure for change. Therefore, a bespoke change control procedure was used.
Would you recommend to the Client deviating away from the standard contract?
Only if it had benefit to my client, for example:
- change control
- retention
- Rectification period
- Stand down days etc
How were changes dealt with under the procedure?
Smartsheet - client raised, contractor/designer review, QS review, client approval. 3 days contractor/designer, 3 days 3 days QS, 5 days client. However, these are maximum limits and are often completed quicker.
How are CDP changes dealt with?
Depends if raised by the client or by the contractor.
Was a collateral warranty in place? Pro’s & con’s
Yes, with the sub-contractors. This firstly gives the client the ability to sue them, but also step in rights if the main contractor was to go bust. The client could then continue with the sub-contractors to complete the project.
Pro’s - same design team, client assurance, TPR don’t have step in rights, client can draft the collateral warranty. Only downside may be increased legal fees and administrative costs.
No need for collateral warranty with Main Contractor as there is a direct contractual link.
Under JCT standard building contract who is responsible for pricing change?
The contractor would price the change, but it would have to be agreed with the client before being instructed.
What happens if there are disagreements over the value of a change?
Where agreement has not been reached, the quantity surveyor is obliged to carry out a valuation
of the variation in accordance with the ‘Valuation Rules’. In reality, the quantity surveyor will often be
acting for the employer in reaching mutual agreement. Imposing a valuation is to be a least favoured option.
What happens if a contractor refuses to implement an instruction?
The Employer has the right to issue a notice to the Contractor which after 7 days allows the Employer to employ others to complete the instruction and the additional costs can be deducted from the Contractor.
What are the contract documents under JCT SBC?
- The printed contract.
- The Contract Sum analysis.
- The Stage 4 design information.
- The BIM protocol (if applicable).
What are the contract documents under JCT D&B?
- The printed contract.
- The Contract Sum analysis.
- The Employer’s Requirements.
- The Contractor’s Proposals.
- The BIM protocol (if applicable).
What are the elements of a contract?
- The Agreement (recitals, particulars, attestation), the Conditions, Schedules.
What 3 documents are required as a basis for the CDP.
What documents were included in the contract for the ERs?
Arup specification and Stage 3 architectural drawings.
What insurances were in place in addition to the works insurance?
Works insurance was JCT option C - professional indemnity and public liability.
What dispute resolution procedures are available?
- Negotiation
- Mediation
- Adjudication
- Arbitration
- Litigation