Sequence Activities Flashcards

Planning

1
Q

What is Sequence Activities process?

A

Identifying and documenting the relationships among the project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Precedence Diagramming Method (PDM)?

A

A technique used in Critical Path Methodology (CPM) to graphically display a network diagram showing activity dependencies by one or more logical relationships to show the sequence in which the activities are to be performed. (Also know as Acitvity-On-Node - AON)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 4 PDM’s relationships?

A

1) Finish-to-Start, 2) Finish-to-Finish, 3) Start-to-Start, 4) Start-to-Finish; Finish-to-Start is the most commonly used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Dependency Determination?

A

A technique used to identify the type of dependency used to create logical relationships between the predecessor and successor activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 4 types of Dependency Determination?

A

1) Mandatory (Hard Logic), 2) Discretionary (Soft Logic or Preferred), 3) External, 4) Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Mandatory Dependency?

A

Dependencies that are contractually or physical limitations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Discretionary Dependency?

A

Based on best practices where a specific sequence is desired, even though there may be other acceptable sequences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is External Dependency?

A

Dependencies outside the project team’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Internal Dependency?

A

Dependencies within the project team’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is leads and lag?

A

Lead is a technique where the amount of time can be advanced (head start on 2nd activity) and lag is a technique where the amount of time can be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Project Schedule Network Diagram?

A

An output and is the visual representation of the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly