What is the purpose of Control Schedule process?
To monitor the status of the project, to update project progress and manage changes to the schedule baseline.
What are the outputs of Control Schedule process?
1) Work Performance Information, 2) Schedule Forecast, 3) Change Requests, 4) Project Mgmt Plan Updates, 5) Project Documents Updates, 6) OPA updates
What refers to the most recent schedule with notations to indicate updates, completed activities, and started activities as of the indicated data date?
Project Schedule
What is Schedule Forecast?
Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated.
What is the purpose of Performance Reviews?
To measure, compare, and analyze schedule performance such as actual start date and finish dates, percentage complete, remaining duration of work in progress.
What techniques are used for Performance reviews?
1) Trend Analysis, 2) Critical Path Method, 3) Critical Chain Method, 4) Earned Value Mgmt (EVM)