Plan Schedule Management Flashcards
Planning
What is the purpose of the Plan Schedule Management process?
Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
What is documented in the Schedule Management Plan?
1) Project Schedule Model Development, 2) Level Of Accuracy, 3) Unites of Measure, 4) Organizational Procedure Links, 5) Project Schedule Model Maintenance, 6) Control Thresholds, 7) Rules of Performance Measurements
What is Control Thresholds?
Variance thresholds for monitoring schedule performance before some action is needed. Measure as percentage.
The Schedule Management Plan will be incorporated into what document?
Project Management Plan