Plan Schedule Management Flashcards

Planning

1
Q

What is the purpose of the Plan Schedule Management process?

A

Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is documented in the Schedule Management Plan?

A

1) Project Schedule Model Development, 2) Level Of Accuracy, 3) Unites of Measure, 4) Organizational Procedure Links, 5) Project Schedule Model Maintenance, 6) Control Thresholds, 7) Rules of Performance Measurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Control Thresholds?

A

Variance thresholds for monitoring schedule performance before some action is needed. Measure as percentage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Schedule Management Plan will be incorporated into what document?

A

Project Management Plan