Estimate Activity Durations Flashcards

Planning

1
Q

What is the purpose to Estimate Activity Durations?

A

Process of estimating the number of work periods needed to complete individual activities with estimated resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Effort?

A

The amount of work units or labor units necessarily to finish an activity. (i.e. 4 hours, 6 weeks, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Duration?

A

The number of work periods needed to complete an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the difference between Effort and Duration?

A

A resource could spend 10 hours (effort) over 3 weeks (duration) reviewing a specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Standard Deviations (Sigma)?

A

Percentage chance of being within the mean (range). ( 1 Sigma = 68.26%, 2 Sigma = 93.26%, 3 Sigma = 99.73%, 6 Sigma + 9.99984%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the tool and techniques to Estimate Activity Duration?

A

1) Expert Judging, 2) Analogous Estimating, 3) Parametric Estimating, 4) Three-Point Estimating, 5) Group Decision Techniques, 6) Reserve Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Analogous Estimating (Top Down Estimating)?

A

Using similar previous project as a reference for your current project, making adjustments for know differences. Used when there is a limited amount of detail information about the project. Least accurate but fastest method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Parametric Estimating?

A

Estimating technique in which an algorithm is used to calculate cost or duration base on historical data and project parameters. Use per unit of value to come up with estimation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Three-Point Estimating?

A

Estimating technique used to estimate cost or duration by applying an average of optimistic (tO), pessimistic (tP), and most likely (tM) when there is uncertainty with the individual activity estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you determine Expected Duration (tE) in Triangular Distribution?

A

tE = (tO + tM + tP) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you determine Expected Duration (tE) in Beta Distribution (PERT)?

A

tE = (tO + 4tM + tP) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you determine Activity Standard Deviation?

A

SD = (tP - tO) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you determine Range of Estimate?

A

Expected Activity Duration +/- Activity Standard Deviation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Reserve Analysis?

A

Analytical technique to determine contingency reserves to the schedule to account for uncertainties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Management Reserves?

A

Specified amount set aside for management control purpose and are reserved to address the “unknown-unknowns” that can affect a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly