Section 8A - Repairs, Alterations & Rerating (API 570 pg 62-64) Flashcards
- When repairs are conducted on a piping system, the repairs should meet the requirements of the API 570 and:
A. ASME Section VIII
B. ASME B31.3
C. ASME B31.3 or the original construction code
D. Any piping code selected by the Engineer
C. ASME B31.3 or the original construction code
- All repair and alteration work must be performed by:
A. A jurisdictional agency
B. A Repair Organization
C. The Authorized Inspection Agency
D. Anyone approved by the Piping Inspector
B. A Repair Organization
- Before work is started, all repair & alterations to piping systems must be authorized by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- Before the work is started, all repairs to piping systems must be authorized by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- Before the work is started, all piping alterations must be authorized by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
C. Authorized Inspector and Piping Engineer
**Ask Mark Smith to clarify this question.
- Who designates needed inspection hold points during repairs and alterations of piping?
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- An inspector may give prior general authorization for limited repairs provided that:
A. These repairs will not require a pressure test
B. These repairs will not require any NDE Examinations
C. These repairs are done only to P1 or P3 materials
D. The inspector is satisfied with the competency of the Repair Organization
D. The inspector is satisfied with the competency of the Repair Organization
- An old piping system has experienced significant corrosion. About 250 ft of an 8 NPS SA-106 piping is being replaced. This activity must be authorized by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- An old piping system has experienced significant corrosion. The 125 ft of 6 NPS SA-53-B piping system will be upgraded with 9 Cr piping. This activity must be authorized by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
C. Authorized Inspector and Piping Engineer
- Prior to completing a piping system repair, all proposed materials must be approved by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
D. Authorized Inspector or Piping Engineer
- During alterations most of the code requirements come from:
A. API 570
B. ASME B31.3
C. ASME B31.3 or the original construction code
D. The original construction code
C. ASME B31.3 or the original construction code
- Prior to a piping system repair, all proposed NDE and testing must be approved by the:
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
D. Authorized Inspector or Piping Engineer
- During piping system alterations, hold points shall be designated by:
A. The Authorized Inspector
B. The Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. The Authorized Inspector
- Who should approve on-stream welding of in-service piping systems?
A. Authorized Inspector
B. Piping Engineer
C. Both Authorized Inspector and the Piping Engineer
D. Corporate Metallurgist
E. Owner/User
E. Owner/User
- Weld repair of cracks that have occurred on in-service piping should NOT be attempted without consulting the:
A. Authorized Inspector
B. Piping Engineer
C. Inspector & Engineer
D. Either the inspector or Engineer
E. Fitness for service expert
B. Piping Engineer
- During repairs or alterations, who should approve work at designated hold points?
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- Once a piping repair is complete, who should approve the finished work?
A. Authorized Inspector
B. Piping Engineer
C. Authorized Inspector and Piping Engineer
D. Authorized Inspector or Piping Engineer
A. Authorized Inspector
- Once piping system alteration work is complete, the finished work should be approved by:
A. The Authorized Inspector
B. The Piping Engineer
C. Both Authorized Inspector and Piping Engineer
D. Either Authorized Inspector or Piping Engineer
A. The Authorized Inspector
- A 24 NPS carbon steel elbow is being replaced. Once the elbow installation is completed, who should check that the work was done correctly?
A. Authorized Inspector
B. NDE Examiner
C. Piping Engineer
D. Either inspector or Piping Engineer
A. Authorized Inspector
- A new 4 NPS line is being tied into a 12 NPS Schedule 160 chrome pipe. The unit startup is dependent on the completion of this work. Due to the critical timing, it is extremely important that this tie-in is in the designed location. Once the Repair Organization marks the tie-in location on the 12 NPS pipe, who should verify that the tie-in location is correct?
A. NDE Examiner
B. Owner/User
C. Maintenance Department personnel
D. Authorized Inspector
D. Authorized Inspector
- A full encirclement welded split sleeve shall be designed by:
A. The Authorized Inspector
B. The piping engineer
C. A professional Engineer
D. A fitness for service consultant
B. The piping engineer
- Longitudinal cracks on in-service piping systems shall NOT be repaired using a fillet-welded patch unless:
A. proper NDE has been performed and reviewed by the Authorized Inspector.
B. proper NDE has been performed and reviewed by the Piping Engineer
C. The all-knowing Piping Engineer uses a crystal ball and foresees that the crack will not grow beyond the clamp
D. The piping Engineer determines, without a crystal ball, that the crack will not grow beyond the clamp
D. The piping Engineer determines, without a crystal ball, that the crack will not grow beyond the clamp
- A deep longitudinal crack is discovered on a straight run length of 48” pipe. Based on expert analysis, it is expected that crack will grow. Which of the following repairs could be performed?
A. Fillet-welded split sleeve
B. Flush Patch
C. Non-welded pipe clamp
D. Non-welded pipe clamp with stays to account for axial forces
B. Flush Patch
- A deep corroded area is found on a pipe system. A temporary repair may be made by fillet welding a split sleeve as long as the specified minimum yield strength of the pipe is: (Open book)
A. ≤ 20,000 psi
B. ≥ 20,000 psi
C. ≤ 40,000 psi
D. ≥ 40,000 psi
E. ≤ 70,000 psi
F. ≥ 70,000 psi
C. ≤ 40,000 psi