Section 6B - Interval & Extent Of Inspection (API 570 pg 47-51) Flashcards
- On- site process services that are flammable but slowly vaporize during a release, such as those that operate below the boiling point but above the flash point, are considered:
A. Class 1 piping
B. Class 2 piping.
C. Class 3 piping.
D. Class 4 piping.
B. Class 2 piping.
- On-site process services that are flammable but do NOT significantly vaporize during a release, such as those that operate below the flash point, are considered:
A. Class 1 piping
B. Class 2 piping.
C. Class 3 piping.
D. Class 4 piping.
C. Class 3 piping.
- An on-site piping system was classified by B31.3 as category D. What is the API 570 classification for this piping?
A. Class 1 piping
B. Class 2 piping.
C. Class 3 piping.
D. Class 4 piping.
D. Class 4 piping.
- Off-site gasoline is considered as:
A. Class 1 piping
B. Class 2 piping.
C. Class 3 piping.
D. Class 4 piping.
C. Class 3 piping.
- Off-site caustic is considered as:
A. Class 1 piping
B. Class 2 piping.
C. Class 3 piping.
D. Class 4 piping.
C. Class 3 piping.
- In petrochemical industry, the majority of the unit process piping is classified as:
A. Class 1
B. Class 2
C. Class 3
D. Class 4
B. Class 2
- Inspection of class 4 piping is:
A. Optional.
B. Based on environmental impacts.
C. Based on health and safety impacts.
D. Completed at least every 10 years.
A. Optional.
- Inspection of class 4 piping is based on:
A. Environmental impacts.
B. Health and safety impacts.
C. Business impacts.
D. Corrosion specialist’s opinion.
C. Business impacts.
- External inspection intervals on piping can be established by using a valid RBI assessment conducted in accordance with:
A. API 570.
B. API 578.
C. API 579.
D. API 580.
D. API 580.
- Which of the following is NOT a factor that could affect the likelihood of CUI on an existing piping system?
A. Local climate conditions.
B. The condition of the coating system.
C. Process fluids.
D. Insulation design and condition.
C. Process fluids.
- CUI can occur on insulated carbon steel piping systems operating between:
A. 25–250°F.
B. 10–350°F.
C. 40–125°F.
D. 120–400°F.
B. 10–350°F.
- CUI is found at a damaged insulation area. What should be done?
A. Inspect additional areas of the piping system.
B. Inspect a minimum of 50% of the piping system.
C. Strip insulation and inspect 100% of the affected piping system.
D. Inspector stands in the pipe rack and shouts “Eureka, I found it!”
A. Inspect additional areas of the piping system.
- A class 4 piping system has some damaged insulation. How many of the damaged areas should be inspected? (Open book)
A. 25%
B. 50%
C. 75%
D. 100%
E. Inspection is optional
E. Inspection is optional
- A class 1 piping system has some damaged insulation. How many of the damaged areas should be inspected? (Open book)
A. 25%
B. 50%
C. 75%
D. 100%
C. 75%
- A class 3 piping system has some damaged insulation. How many of the damaged areas should be inspected? (Open book)
A. 25%
B. 50%
C. 75%
D. Inspection is optional
A. 25%
- A class 1 piping system is being inspected for CUI. How many of the non-damaged areas should be inspected? (Open book)
A. 10%
B. 25%
C. 33%
D. 50%
E. 75%
F. 100%
D. 50%
- A class 3 piping system is being inspected for CUI. How many of the non-damaged areas should be inspected? (Open book)
A. 10%
B. 25%
C. 33%
D. 50%
E. 75%
F. Inspection is optional.
A. 10%
- What is the recommended extent of CUI inspection at non-damaged locations on class 2 piping systems? (Open book)
A. 75%
B. 50%
C. 33%
D. 10%.
C. 33%
- When thickness measurements are conducted on a pipe circuit, each thickness measurement set should include:
A. A representative #of CML’s.
B. All CMLs
C. At least 50% of the CMLs
D. At least 75% of the CMLs
A. A representative #of CML’s.
- When thickness measurements are taken, each thickness measurement set should include:
A. All CMLs
B. CMLs on each type of component, e.g. ells, tees.
C. The CML with the lowest remaining corrosion allowance.
D. The CML with the longest remain life.
B. CMLs on each type of component, e.g. ells, tees.
- When thickness measurements are conducted , each thickness measurement set should include:
A. The CML with the highest corrosion rate.
B. The CML with the earliest renewal date.
C. The CML with the lowest remaining corrosion allowance.
D. All CMLs in the piping circuit.
B. The CML with the earliest renewal date.
- Thickness measurements on a pipe circuit are due. This circuit is subject to non-uniform corrosion. Who is responsible to determine the specific CMLs that need to be measured?
A. Authorized inspector.
B. Corrosion specialist.
C. Authorized inspector in consultation with the corrosion specialist.
D. Authorized inspector in consultation with the piping engineer.
E. Authorized inspector in consultation with either the corrosion specialist or the Piper engineer.
E. Authorized inspector in consultation with either the corrosion specialist or the Piper engineer.
- Which two methods can be used to manage the thickness measurement’s program?
A. Circuit analysis and point-to-point methods.
B. Circuit analysis and exponential methods.
C. Exponential and point –to– point methods.
D. Point–to-point and relative analysis methods.
E. Relative analysis and circuit analysis methods.
A. Circuit analysis and point-to-point methods.
- The point – to - point method for thickness measurements may lead to:
A. Failures if not closely managed.
B. Frequent inspections if not closely managed.
C. Overly conservative corrosion rates.
D. Overly conservative inspection intervals.
B. Frequent inspections if not closely managed.