Section 5C - Inspection Examination & Testing (API 570 pg 37-41) Flashcards
- When designating an injection point circuit, the recommended upstream limit of the injection point circuit is a minimum of:
A. 12 inches or 3 pipe diameters, whichever is less
B. 12 inches or 3 pipe diameters, whichever is greater
C. 12 inches or 10 pipe diameters, whichever is less
D. 12 inches or 10 pipe diameters, whichever is greater
B. 12 inches or 3 pipe diameters, whichever is greater
- When designating an injection point circuit, the recommended downstream limit of the injection point circuit is a minimum of:
A. 25 feet from the injection point
B. The 2nd change in direction
C. 25 feet past the second change in direction
D. The lesser of 2nd change in direction or 25 feet past the 1st change in direction
D. The lesser of 2nd change in direction or 25 feet past the 1st change in direction
(Answer key says E but there is no E, looks like answer is D)
- An injection point circuit is subject to localized corrosion. Which of the following is NOT necessarily applicable when selecting CML locations for this circuit?
A. Add grid with UT reading points spaced ≤2” apart
B. Add CML at the expected impingement point of the injection point
C. Add CML at the upstream and downstream limits of the injection point circuit
D. Add CML at the intermediate locations along straight sections of this circuit
A. Add grid with UT reading points spaced ≤2” apart
- Injection point circuit is subject to localized corrosion. Which of the following is not necessarily a preferred NDE method for examining this circuit?
A. Guided Wave Examination
B. Profile RT
C. Spot UT with a grid
D. UT scanning
A. Guided Wave Examination
- During scheduled inspections of injection points, more extensive inspections should be applied to area beginning 12 inches upstream of the injection nozzle and continuing:
A. At least 3 pipe diameters downstream of the injection point
B. At least 10 pipe diameters downstream of injection point
C. To the first change in flow direction
D. To 25 feet past the 1st change in direction
B. At least 10 pipe diameters downstream of injection point
- A pressure test on a process piping is normally conducted to the requirements of:
A. ASME B16.5
B. ASME B31.3
C. ASME Section VIII Div 1
D. API 598
B. ASME B31.3
- When a tightness test is performed on a pipe, the test pressure is:
A. Based on the construction code’s test pressure
B. Based on the current code’s test pressure
C. Specified by the Inspector
D. Specified by the Owner/User
D. Specified by the Owner/User
- A cracked circumferential weld is repaired by welding. Instead of pressure testing the entire piping circuit, only this weld and a couple inches of pipe will be pressure tested (using a test plug). The substitution of a component pressure test instead of testing the entire circuit requires approval of:
A. The Inspector
B. The engineer
C. Either the inspector or the engineer
D. Both inspector or engineer
B. The engineer
- A pressure test on a piping system that is altered should be:
A. Done after any required PWHT has been completed
B. Held a minimum of 15 minutes
C. Checked with gauge that has a maximum range of 5 times the test pressure
D. Done prior to priming or painting of welds
A. Done after any required PWHT has been completed
- A hydrotest is planned for a large diameter low-chrome pipe. Be sure that:
A. The supporting structure is adequate for the weight of the water
B. Low chloride water is used
C. An inhibitor is added to prevent stress corrosion cracking
D. A relief device is added with the set pressure ≤110% of the test pressure
A. The supporting structure is adequate for the weight of the water
- A pressure test cannot be performed using water due to potential contamination of the process. A flammable liquid will be used in-lieu of water. The flashpoint of the test medium must be at least:
A. 50°F
B. 120°F
C. 150°F
D. 400°F
B. 120°F
- When hydrotesting 300 SS piping systems, the maximum chloride must be less than:
A. 50 ppm
B. 100 ppm
C. 200 ppm
D. 250 ppm
A. 50 ppm
- What is a concern when hydrotesting sensitized austenitic stainless steel?
A. Brittle failure
B. Oxygen pitting
C. Polythionic stress corrosion cracking
D. Temper – embrittlement
C. Polythionic stress corrosion cracking
- A hydrotest will be performed on an austenitic SS piping that is subject to polythionic stress corrosion cracking. What type of test fluid should be considered for the hydrostatic test?
A. Alkaline – water solution
B. Low sodium water
C. Potable water
D. Steam Condensate
A. Alkaline – water solution
- Which is NOT required when hydrotesting 300 series stainless steel piping systems?
A. Use low chloride water
B. Raise pressure in small steps
C. Thoroughly drain the piping
D. Thoroughly dry the inside of the pipe
B. Raise pressure in small steps