Q

What is LCO 3.8.1?

A

The following AC electrical sources shall be OPERABLE:

a. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electrical Power Distribution System; and
b. Two Diesel Generators (DGs) each capable of supplying one train of the onsite Class 1E AC Electrical Power Distribution System.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is LCO 3.8.1 Applicable?

A

MODES 1, 2, 3, and 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is condition A of LCO 3.8.1?

A

One offsite circuit inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the required actions and completion times for Condition A of LCO 3.8.1 (one offsite circuit inoperable)?

A

Perform SR 3.8.1.1 (offsite source check) for OPERABLE offsite circuit within 1 hour and once every 8 hours thereafter.

AND

Restore offsite circuit to OPERABLE status within 72 hours and 10 days from the date of discovery to meet LCO.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is condition B of LCO 3.8.1?

A

One DG inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the required actions and completion times for Condition B of LCO 3.8.1 (one DG inoperable)?

A

Perform SR 3.8.1.1 (offsite source check) for the OPERABLE offsite circuit(s) within 1 hour and once every 8 hours thereafter.

AND

Declare required feature(s) supported by the inoperable DG inoperable when its redundant required feature(s) is inoperable within 4 hours

AND

Determine OPERABLE DG is not inoperable due to common cause failure with 24 hours OR perform a SR 3.8.1.2 (start test) for OPERABLE DG within 24 hours

AND

Restore DG to OPERABLE status within 7 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is condition C of LCO 3.8.1?

A

Two offsite circuits inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the required actions and completion times for Condition C of LCO 3.8.1 (Two offsite circuits inoperable)?

A

Declare required feature(s) inoperable when its redundant required feature(s) is inoperable within 12 hours.

AND

Restore one offsite circuit to OPERABLE status within 24 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is condition D of LCO 3.8.1?

A

One offsite circuit inoperable.

AND

One DG inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the required actions and completion times for Condition D of LCO 3.8.1 (One offsite circuit inoperable AND One DG inoperable.)?

A

NOTE: Enter applicable Conditions and Required Actions of LCO 3.8.9, “Distribution Systems - Operating,” when Condition D is entered with no AC power source to any train.

Restore offsite circuit to OPERABLE status.with 12 hours.

OR

Restore DG to OPERABLE status within 12 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is condition E of LCO 3.8.1?

A

Two DGs inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the required actions and completion times for Condition E of LCO 3.8.1 (Two DGs inoperable.)?

A

Restore one DG to OPERABLE status with 2 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is condition F of LCO 3.8.1?

A

Required Action and Associated Completion Time of Condition A, B, C, D, or E not met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the required actions and completion times for Condition F of LCO 3.8.1 (Required Action and Associated Completion Time of Condition A, B, C, D, or E not met.)

A

Be in MODE 3 in 6 hours.

AND

Be in MODE 5 in 36 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is condition G of LCO 3.8.1?

A

Three or more AC sources inoperable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the required actions and completion times for Condition G of LCO 3.8.1 (Three or more AC sources inoperable)?

A

Enter LCO 3.0.3. immediately

17
Q

What is SR 3.8.1.1 and its required frequency?

A

Verify correct breaker alignment and voltage for

each offsite circuit every 7 days.

18
Q

What is SR 3.8.1.2 and its required frequency?

A

Every 31 days, Verify each DG starts from standby conditions and
achieves:

a. In ≤ 10 seconds, ready-to-load status; and
b. Steady state voltage ≥ 2280 V and ≤ 2520 V,
and frequency ≥ 59.5 Hz and ≤ 61.2 Hz.

19
Q

What is SR 3.8.1.3 and its required frequency?

A

Every 31 days, Verify each DG is synchronized and loaded, and operates for ≥ 60 minutes:
a. For ≥ 15 minutes loaded to greater than or
equal to peak accident load; and
b. For the remainder of the test at a load
≥ 2300 kW and ≤ 2500 kW.

NOTE: 1. Momentary transients outside the load range
do not invalidate this test. 2. This Surveillance shall be conducted on only one DG at a time. 3. This Surveillance shall be preceded by and immediately follow without shutdown a successful performance of SR 3.8.1.2.

20
Q

What is SR 3.8.1.4 and its required frequency?

A

Every 31 days, Verify each day tank contains ≥ 2500 gallons of fuel oil.

21
Q

What is SR 3.8.1.5 and its required frequency?

A

Every 18 months, Verify each DG rejects a load greater than or equal to its associated single largest post-accident load, and: a. Following load rejection, the frequency is ≤ 68 Hz; b. Within 3 seconds following load rejection, the voltage is ≥ 2280 V and ≤ 2640 V; and c. Within 3 seconds following load rejection, the frequency is ≥ 59.5 Hz and ≤ 61.5 Hz.

22
Q

What is SR 3.8.1.6 and its required frequency?

A

Every 18 months, Verify each DG, operating at a power factor ≤ 0.9, does not trip, and voltage is maintained ≤ 4000 V during and following a load rejection of ≥ 2300 kW and ≤ 2500 kW.

23
Q

What is SR 3.8.1.7 and its required frequency?

A

NOTE: This Surveillance shall not be performed in MODE 1, 2, 3, or 4.

Every 18 months, Verify on an actual or simulated loss of offsite power signal:
a. De-energization of emergency buses;
b. Load shedding from emergency buses;
c. DG auto-starts from standby condition and:
1. energizes permanently connected loads in ≤ 10 seconds,
2. energizes auto-connected shutdown
loads through automatic load
sequencer,
3.Maintains steady state voltage ≥ 2280 V and ≤ 2520 V,
4.Maintains steady state frequency ≥ 59.5 Hz and ≤ 61.2 Hz, and
5. supplies permanently connected loads for ≥ 5 minutes.

24
Q

What is SR 3.8.1.8 and its required frequency?

A

Every 18 months, Verify each DG, operating at a power factor ≤ 0.9, operates for ≥ 24 hours:
a. For ≥ 100 minutes loaded ≥ its peak
accident loading; and
b. For the remaining hours of the test loaded
≥ 2300 kW and ≤ 2500 kW.

25
Q

What is SR 3.8.1.9 and its required frequency?

A

NOTE: This Surveillance shall not be performed in
MODE 1, 2, 3, or 4.

Every 18 months, Verify each DG:
a. Synchronizes with offsite power source while
supplying its associated 2400 V bus upon a
simulated restoration of offsite power;
b. Transfers loads to offsite power source; and
c. Returns to ready-to-load operation.

26
Q

What is SR 3.8.1.10 and its required frequency?

A

NOTE: This Surveillance shall not be performed in MODE 1, 2, 3, or 4.

Every 18 months, Verify the time of each sequenced load is within ± 0.3 seconds of design timing for each automatic load sequencer.

27
Q

What is SR 3.8.1.11 and its required frequency?

A

NOTE: This Surveillance shall not be performed in MODE 1, 2, 3, or 4.

Every 18 months, Verify on an actual or simulated loss of offsite power signal in conjunction with an actual or
simulated safety injection signal:
a. De-energization of emergency buses;
b. Load shedding from emergency buses;
c. DG auto-starts from standby condition and:
1. energizes permanently connected
loads in ≤ 10 seconds,
2. energizes auto-connected emergency
loads through its automatic load
sequencer,
3. achieves steady state voltage
≥ 2280 V and ≤ 2520 V,
4. achieves steady state frequency
≥ 59.5 Hz and ≤ 61.2 Hz, and
5. supplies permanently connected loads
for ≥ 5 minutes.