Scope management- PROCESS Flashcards
- Plan scope management
PG-(process group)- planning, KA( Knowledge area) SCOPE, DESC(Description)- provides the how-to- documents for requirements and scope mgmt. 2 key outputs- scope mgmt plan, requirements mgmt plan
2.Collect requirements
pg- planning, KA- SCOPE, desc- collects requirements from stakeholders. 2 key outputs- requirements documentation, requirements traceability matrix.
3.Define scope
pg- planning, KA- SCOPE, desc- develops a detailed scope statement for the project. key output- project scope statement.( PMBOK- pg 155)
4.Create WBS
pg- planning, KA- SCOPE, desc- creates the scope baseline for the project. output- scope baseline.
SCOPE -KNOWLEDGE AREA
Defines and controls the scope baseline for the project
- Validate scope
PG- M+C, KA- Scope Desc- Validates scope by approving the deliverables of the project. 3 Key outputs -Accepted deliverables -Work performance information -Change requests
6.Control scope
PG- Monitoring and controlling M+C, KA- Scope
Desc-Controls the scope baseline and manages changes ( scope creep etc)as required.
2 Key outputs
-Work performance information
-Change requests