Schedule management- PROCESS Flashcards
- Plan schedule mgmt
PG- Planning, KA- Schedule,
Desc- Provides the how-to-document for schedule mgmt.
1 key output
-Schedule mgmt plan ( good resource for the project manager when faced with problems. gives rules.. what techniques or tools will you use)
- Define activities
PG- Planning,KA- Schedule desc- decomposes the scope baseline into activities 4 outputs -Activity lists -Activity attributes -Milestone list -Change request
- Sequence activities
PG- Planning, KA- Schedule
Desc- Defines the sequence of activities in order to optimize the schedule.
Key output
-Project schedule network diagrams( 1 word)
- Estimate activity durations
PG-Planning, KA- Schedule Desc-Estimates the duration required for activities and the overall schedule. 2 Key Output -Duration estimates -Basis of estimates
5.Develop schedule
PG-Planning, KA- Schedule
Desc- creates the schedule baseline for the project.
5 Key outputs:
-Schedule baseline- Its a PROJECT PLAN DOCUMENT doesn’t change. frozen when u approve it. only changes with an approved change request updates. otherwise its frozen and your baseline
-Project schedule- ITS A PROJECT DOCUMENT. day to day, living schedule. If something changes, u just update the document and dont do change requests.
-Schedule data-detailed data of the schedule ( resources/ supporting data)
-Project calendars- availability of workdays for the project( holidays etc)
-Change requests- if u have anything baseline, and start to modify, u might have a change request which changes your scope.
- Control schedule
PG-M+C, KA- Schedule Desc- Controls the schedule baseline and manages changes as required. 3 key outputs - Schedule forecasts -Work performance information -Change requests