Schedule management- Knowledge area Flashcards
Schedule mgmt definition
Develops and controls the schedule baseline for the project
Precision vs accuracy
Precision in schedule ( unit factor for time in project mgmt)- repeat the same value over and over again. but it may not be accurate. A- Accurate- provide a level of accuracy.
Milestone schedule
audience for this report- mgmt
Activity attributes
pg 31, deck
Rolling wave planning
a
PDM
Precedence diagram method
AON
Activity on Node
Mandatory dependencies
also called “hard logic”. A has to come before B
Discretionary dependencies
u have a choice. also called “preferential or soft logic”
4 types of dependencies
FS-Finish of activity A determines THE START OF ACTIVITY B( most common)
SS-Start A to start A
FF-finishA to finish B
SF- start of activity A determines when ACTIVITY b NEEDS TO BE COMPLETED
Lead
u start sooner
Lag
u start later
RBS
Resource breakdown structure-
Analogous estimate- (TIP- Any estimate will have a basis)
called “talk down” estimate ( based on neighbor building tree house). least accurate of all accuracies.
Parametric estimate
asked my neighbor about tree housers. then u ask about square footage. so based on parameters.