SCM 301 FINAL PART 1 Flashcards

1
Q

What is Master Scheduling?

A

determines when products made, when orders filled, and what products are still available (trucks, suvs)

tracks production output and matches this output to actual customer orders, short-term (in weeks or months)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Material Requirements Planning (MRP)?

A

translates the master production schedule into planned orders and calculates the timing and quantity for those orders (parts of suv)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Production Activity Control (PAC)?

A

assures in house manufacturing takes place according to plan; also helps manufacturing managers identify potential problems (INSOURCING)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Vendor Order Management?

A

assures that materials ordered from supply chain partners are received when needed, helps purchasing managers identify potential problems and take corrective actions (OUTSOURCING)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What else is important about Master Scheduling?

A

primary interface point for actual customer orders (controls timing and quantity of production)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the Master Schedule Record track?

A

Forecast Demand
Booked Orders
Projected Inventory Levels
Production Quantities
Available to Promise (ATP)
Master Production Schedule (MPS)
Planning Horizon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Available to Promise (ATP)?

A

number of units that are available for sale to meet customer needs each week, given those that have already been promised to customers

how many additional units can be sold

only calculated in weeks with positive MPS quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Time/Planning Horizon?

A

amount of time that the master schedule record or MRP record extends

longer production/supplier lead times require longer planning horizons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Formula for Projected Ending Inventory for the Master Schedule Record?

A

previous periods EI + MPS quantity – the max of forecasted demand and booked orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Formula for the first week of ATP?

A

Previous periods EI + MPS quantity – sum of all booked orders until next MPS quantity due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Formula for all weeks besides the first of ATP?

A

MPS Quantity – sum of all booked orders until next mps quantity due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the inputs of Material Requirements Planning (MRP)?

A

Master Production Schedule, Bill of Materials File, and Inventory Records File

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What type of demand is Material Requirements Planning (MRP) designed to manage?

A

dependent demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Independent Demand?

A

inventory items whose demand levels are beyond a company’s complete control (end item / finished goods)

determined by customer demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Dependent Demand?

A

inventory items whose demand levels are tired directly to a company’s planned production of another item

if you know independent demand, then you know exact dependent demand items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the advantages of Material Requirements Planning (MRP)? (3)

A

knows exact timing/quantity of items

trace lower level items

tells a firm what needs to be made and when

17
Q

What are the disadvantages of Material Requirements Planning (MRP)? (5)

A

capacity issues

fixed lead times

Uncertainty in shipments and quantity levels

One change in an item has large effects on supply chain

Must be organized because whole supply chain relies on accuracy

18
Q

How do you deal with a variable lead time?

A

lengthen the planning lead times or hold additional inventory as safety stock

19
Q

What is the Bill of Materials (BOM)?

A

listing of all the subassemblies, intermediates, parts, and raw materials that go into a parent assembly

20
Q

What is the Product Structure Tree?

A

shows how the components in the BOM are put together to make the level 0 item

21
Q

What does it mean to explode the BOM?

A

process of working backwards for a level 0 item to determine the quantity and timing of orders

22
Q

What is the Material Requirements Planning (MRP) Record?

A

Comprised of:
gross requirements
scheduled receipts
projected ending inventory
net requirements
planned receipts
planned orders

23
Q

What are Net Requirements?

A

how much more managers have to order, after using up the previous period’s ending inventory, scheduled receipts, and planned receipts

24
Q

What are scheduled receipts?

A

units that are already on order

25
Q

What are planned order receipts?

A

amount that is planned to be ordered to be received at the beginning of the period

26
Q

What is the Formula for Net Requirements?

A

maximum of either 0 OR gross requirements – previous ending inventory – scheduled receipts

27
Q

What is the Formula for Projected Ending Inventory for the Material Requirements Planning (MRP) Record?

A

Ending inventory from previous period + scheduled receipts + planned receipts - gross requirements