Schedule Process Flashcards
Plan Schedule Management
Process Group: planning
Knowledge Area: schedule
Description: provides the for schedule management
Key Outputs: schedule management plan
Define Activities
Process Group: planning
Knowledge Area: schedule
Description: decomposes the scope base line into activities
Key Outputs: activity list, activity attributes, milestone list, change request
Sequence Activities
Process Group: planning
Knowledge Area: schedule
Description: defines the sequence of activities in order to optimize the schedule
Key Outputs: project schedule network diagrams
Estimate Activity Duration
Process Group: planning
Knowledge Area: schedule
Description: estimates the durations required for activities and the overall schedule
Key Outputs: duration estimates, basis of estimates (what estimates were based on?)
Develop Schedule
Process Group: planning
Knowledge Area: schedule
Description: creates the schedule baseline for the project
Key Outputs: schedule baseline (project plan document: frozen when approved, only changes with approved change request), project schedule (project document: living schedule), schedule data (extra information, activity attributes), project calendars, change request
Control Schedule
Process Group: M&C
Knowledge Area: schedule
Description: controls the schedule baseline and manages changes as required
Key Outputs: schedule forecast (unique), work performance information, change request