Integration Processes Flashcards

1
Q

Develop Charter Project

A

Process Group: initiating

Knowledge Area: integration

Description: creates the project charter and authorizes the project to exist.

Key Outputs: project charter, assumption log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Management Plan

A

Process Group: planning

Knowledge Area: integration

Description: creates the project performance baseline in supporting management plans. This process is the alpha and omega of planning. Planning does not finish until completing all the processes on planning column

Key Output: project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Direct and Manage Project Work - majority of budget will be spent, project document (living document which is updated throughout the project, may get assigned to someone once project is closed

A

Process Group: executing (do activity)

Knowledge Area: integration

Description: manages the execution of the project as directed by the project plan

Key output: deliverables, work performance data, issue log, change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Manage Project Knowledge

A

Process Group: executing

Knowledge Area: integration

Description: uses existing knowledge and creates new knowledge to achieve the project objectives

Key Outputs: the lessons learned register (list)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Monitor and Control Project Work

A

Process Group: monitor & controlling

Knowledge Area: integration

Description: monitors the work of the project and adjust it if required

Key Outputs: work performance reports and change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Preform Integrated Change Control

A

Process Group: monitor & controlling

Knowledge Area: integration

Description: approves change request

Key Outputs: approved change request, change log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Close Project of Phase

A

Process Group: closing

Knowledge Area: integration

Description: finalizes activities to close out project or phase

Key Outputs: the final product service or result transition, OPA (organization process assets) updates, final report, final lessons learned register