Schedule Management Flashcards

1
Q

What are the 6 processes associated with the Schedule Management process group?

A
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule
Control Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the 18 components of the Project Management Plan is created in the Plan Schedule Management process?

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the inputs to the Define Activities process?

A

Schedule Management Plan

Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the inputs to the process?

A

Activity List
Activity Attributes
Milestone List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the inputs to the Estimate Activity Durations process?

A

Activity List
Resource Requirements
Resource Calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the inputs to the Develop Schedule process?

A

Activity List
Duration Estimates
Project Schedule Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the tools associated with the Control Schedule process?

A

Iteration Burndown Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the tools associated with the Develop Schedule process?

A
Critical Path Method
Resource Optimization
Leads and Lags
Schedule Compression
Agile Release Planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the tools associated with the Estimate Activity Duration process?

A

Analogous (top-down) Estimating
Parametric Estimating
3 Point Estimating
Bottom Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the tools associated with the Sequence Activities process?

A

Precedence Diagram Method
Dependency Determination
Leads and Lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the tools associated with the Define Activities process?

A

Decomposition

Rolling Wave Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the outputs from the Plan Schedule Management process?

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the outputs from the Define Activities process?

A

Activity List
Activity Attributes
Milestone List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the outputs from the Sequence Activities process?

A

Project Schedule Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the outputs from the Estimate Activity Durations process?

A

Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the outputs from the Develop Schedule process?

A

Project Schedule

Schedule Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the outputs from the Control Schedule process?

A

Work Performance Information
Schedule Forecasts
Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which process group does the process Plan Schedule Management belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which process group does the process Define Activities belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which process group does the process Sequence Activities belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which process group does the process Estimate Activity Durations belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which process group does the process Develop Schedule belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which process group does the process Control Schedule belong to?

A

Monitoring and Controlling

24
Q

What are the four main types of activity dependencies?

A

Mandatory
Discretionary
External
Internal

25
Q

A dependency that cannot be broken is a ___________ dependency.

A

Mandatory

26
Q

A dependency that is not required but follows a best practice is a _________ dependency.

A

Discretionary

27
Q

A dependency that the project team can control is a ___________ dependency.

A

Internal

28
Q

A dependency that is outside of the project’s control and scope is a ________ dependency.

A

External

29
Q

If an activity is allowed to start before its dependent activity is completed then it has a ______.

A

Lead

30
Q

The gap between 2 dependent activities is called a ______.

A

Lag

31
Q

An estimation method for an activity that is based on a previous project is called _________ ___________?

A

Analogous Estimating

32
Q

An estimation technique for an activity that is based on linear extrapolation is called ________ ___________.

A

Parametric Estimating

33
Q

What does PERT stand for?

A

Program Evaluation and Review Technique

34
Q

What is the formula for a beta distribution 3 point estimate?

A

(O+4R+P)/6

35
Q

What is the formula for a triangular distribution 3 point estimate?

A

(O+R+P)/3

36
Q

What is the formula for the standard deviation of a 3 point distribution?

A

(P-O)/6

37
Q

What is the critical path?

A

The combination of activities that cannot be delayed without delaying the project completion date.

38
Q

Who invented the Critical Chain Method?

A

Eli Goldratt

39
Q

Estimating each activity aggressively and adding a lump-sum buffer is called the ________ __________ Method.

A

Critical Chain

40
Q

Name 2 types of resource optimization.

A

Resource Leveling

Resource Smoothing

41
Q

Which type of resource optimization is more disruptive, resource leveling or resource smoothing?

A

Resource Leveling

42
Q

Which resource optimization technique does not change the critical path and the project end date?

A

Resource Smoothing

43
Q

Which schedule compression technique increases cost?

A

Crashing

44
Q

Which schedule compression technique increases risk?

A

Fast tracking

45
Q

Which schedule compression technique involves adding more resources to an activity?

A

Crashing

46
Q

Which schedule compression technique involves adjusting the schedule so that some of the activities overlap?

A

Fast tracking

47
Q

Which type of graphical representation of the schedule is best suited for brief, high level presentations?

A

Milestone chart

48
Q

Which type of graphical representation of the project schedule shows project activities as bars on a calendar?

A

Gantt Chart

49
Q

What is the most detailed graphical representation of a project schedule?

A

Project Schedule Network Diagram

50
Q

What tool is used by Agile teams to show the team’s progress on completing the work on the backlog?

A

Iteration Burndown Chart

51
Q

Schedule Performance Index and Schedule Variance are both types of what?

A

Work Performance Information

52
Q

What is Float or Slack?

A

The amount of time an activity can slip before it changes the critical path.

53
Q

How much float does an activity on the critical path have?

A

Zero

54
Q

What is Free Float or Free Slack?

A

The amount of time an activity can slip before affecting the early start of dependent activities.

55
Q

What is the Delphi Technique?

A

A way to gather expert judgement where each participant does not know who the other participants are.

56
Q

What is an heuristic?

A

A rule of thumb.

57
Q

What is Lag?

A

The delay between an activity and the subsequent one.