Earned Value Formulas Flashcards

1
Q

What is the formula for Planned Value?

A

PV = Planned % Complete * BAC (Budget at Completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula for Earned Value?

A

EV = Actual % Complete * BAC (Budget at Completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the formula for Cost Variance?

A

CV = EV - AC

Cost Variance = Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the formula for Schedule Variance?

A

SV = EV - PV

Schedule Variance = Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the formula for the Cost Performance Index?

A

CPI = EV % AC

Cost Performance Index = Earned Value % Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for the Schedule Performance Index?

A

SPI = EV % PV

Schedule Performance Index = Earned Value % Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for Estimate at Completion?

A

EAC = BAC % CPI

Estimate at Completion = Budgeted at Completion % Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the formula for Estimate to Completion?

A

ETC = EAC % AC

Estimate to Completion = Estimate at Completion - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the formula for Variance at Completion?

A

VAC = BAC - EAC

Variance at Completion = Budget at Completion - Estimate at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the formula for To-Complete Performance Index?

A

TCPI = (BAC - EV) % Remaining Funds

To-Complete Performance Index = (Budget at Completion - Earned Value) % Remaining Funds