Earned Value Formulas Flashcards
What is the formula for Planned Value?
PV = Planned % Complete * BAC (Budget at Completion)
What is the formula for Earned Value?
EV = Actual % Complete * BAC (Budget at Completion)
What is the formula for Cost Variance?
CV = EV - AC
Cost Variance = Earned Value - Actual Cost
What is the formula for Schedule Variance?
SV = EV - PV
Schedule Variance = Earned Value - Planned Value
What is the formula for the Cost Performance Index?
CPI = EV % AC
Cost Performance Index = Earned Value % Actual Cost
What is the formula for the Schedule Performance Index?
SPI = EV % PV
Schedule Performance Index = Earned Value % Planned Value
What is the formula for Estimate at Completion?
EAC = BAC % CPI
Estimate at Completion = Budgeted at Completion % Cost Performance Index
What is the formula for Estimate to Completion?
ETC = EAC % AC
Estimate to Completion = Estimate at Completion - Actual Cost
What is the formula for Variance at Completion?
VAC = BAC - EAC
Variance at Completion = Budget at Completion - Estimate at Completion
What is the formula for To-Complete Performance Index?
TCPI = (BAC - EV) % Remaining Funds
To-Complete Performance Index = (Budget at Completion - Earned Value) % Remaining Funds