Integration Management Flashcards
What are 2 the inputs for Develop Project Charter?
Business Case
Agreements
What are 2 the outputs of Develop Project Charter?
Project Charter
Assumption Log
Which Process Group does Develop Project Charter belong to?
Initiating
What are 2 the inputs to Develop Project Management Plan?
Project Charter
Outputs from other processes
What is the output from Develop Project Management Plan?
Project Management Plan
Which Process Group does Develop Project Management Plan belong to?
Planning
What are 2 the inputs to Direct and Manage Project Work?
Approved Change Requests
Project Management Plan
What are the 4 outputs of Direct and Manage Project Work?
Deliverables
Issues Log
Work Performance Data
Change Requests
Which Process Group does Direct and Manage Project Work belong to?
Executing
What are 2 the inputs to Close Project or Phase?
Accepted Deliverables
Agreements
What are the 3 outputs of Close Project or Phase?
Final Transition
Final Report
Lessons Learned Register Updates
Which Process Group does Close Project or Phase belong to?
Closing
What are the 4 inputs to Monitor and Control Project Work?
Work Product Information (WPI)
Project Management Plan
Schedule Forecast
Cost Forecast
What are 2 the outputs to Monitor and Control Project Work?
Work Performance Reports
Change Requests
Which Process Group does Monitor and Control Project Work belong to?
Monitoring and Controling
What is the input to Manage Project Knowledge?
Deliverables
What is the output from Manage Project Knowledge?
Lessons Learned Registry
What are 2 the tools associated with Manage Project Knowledge?
Knowledge Management
Information Management
What is the tool associated with Monitor and Control Project Work?
Data Analysis